Question

In: Nursing

Part 1: If you were sponsoring a project, would you want to be updated in terms...

Part 1: If you were sponsoring a project, would you want to be updated in terms of cost and schedule variance or cost and performance indexes? Why?

Part 2: Give two examples of why a project might be terminated early for cause and two examples of why a project might be terminated early for convenience.

Solutions

Expert Solution

Cost variance is the difference of earned value and actual cost. Schedule variance is the difference of earned value and planned value. If cost variance is negative then the project is over budget. If schedule variance is negative then the project is behind schedule.

Cost Variance (CV):
Cost variance is basically related with the budget of the project. Cost variance is the difference of the actual cost and the expected cost. Cost Variance is calculated by taking the difference of the Earned Value and the Actual Cost.

Schedule Variance (SV):
Schedule variance basically related with the scheduled time for the project. Schedule variance is the measurement of deviation of consumed time from the scheduled time. Scheduled Variance is calculated by taking difference between Earned Value and Planned Value.

Schedule Variance (SV)

It is imperative for you to keep your project on schedule and Schedule Variance helps you complete on time. It enables you to avoid unnecessary cost overruns due to slip of schedule. Costs increase as you go over the stipulated time.

For example, you have rented some equipment for a specific duration of time and you may end up paying more if you need this equipment for longer. You may need to rent this equipment from other suppliers on an urgent, short-term contract at a higher price.

Schedule Variance is a vital analytical tool, it lets you know if you are ahead of schedule or behind schedule in dollars.

The Formula for Schedule Variance (SV)

You can calculate Schedule Variance by subtracting Planned Value from Earned Value.

Schedule Variance = Earned Value – Planned Value

SV = EV – PV

From the above formula, we can conclude that:

  • You are ahead of schedule if the Schedule Variance is positive.
  • You are behind schedule if the Schedule Variance is negative.
  • You are on schedule if the Schedule Variance is zero.

When the project is complete, the Schedule Variance becomes zero because all Planned Value has been earned.

Schedule Variance (SV)

It is imperative for you to keep your project on schedule and Schedule Variance helps you complete on time. It enables you to avoid unnecessary cost overruns due to slip of schedule. Costs increase as you go over the stipulated time.

For example, you have rented some equipment for a specific duration of time and you may end up paying more if you need this equipment for longer. You may need to rent this equipment from other suppliers on an urgent, short-term contract at a higher price.

Schedule Variance is a vital analytical tool, it lets you know if you are ahead of schedule or behind schedule in dollars.

The Formula for Schedule Variance (SV)

You can calculate Schedule Variance by subtracting Planned Value from Earned Value.

Schedule Variance = Earned Value – Planned Value

SV = EV – PV

From the above formula, we can conclude that:

  • You are ahead of schedule if the Schedule Variance is positive.
  • You are behind schedule if the Schedule Variance is negative.
  • You are on schedule if the Schedule Variance is zero.

When the project is complete, the Schedule Variance becomes zero because all Planned Value has been earned.

Cost Variance (CV)

Cost Variance is as important as Schedule Variance. You must complete your project within the approved budget. Exceeding the planned budget is bad for you and your stakeholders.

Everything is about the money. Clients are very cautious about spending; because any deviation from the cost baseline can affect their profit. In the worst case, they may have to put more money into the project to complete it. This is detrimental if the contract is fixed price.

Cost Variance deals with the cost baseline of the project. It provides you with information on whether you are over or under budget, in dollar terms. Cost Variance is a measure of the cost performance of a project.

The Formula for Cost Variance (CV)

Cost Variance can be calculated by subtracting the actual cost from the Earned Value.

Cost Variance = Earned Value – Actual Cost

CV = EV – AC

We can conclude the following from the above formula:

  • You are under budget if the Cost Variance is positive.
  • You are over budget if the Cost Variance is negative.
  • You are on budget if the Cost Variance is zero.

Two examples of why a project might be terminated early for convenienceare the project profit becomes significantly lower than expected, due to too high project cost or too lowproject revenue, and requirements or specifications change fundamentally so that the underlying contract cannot be changed accordingly.

A termination for cause can only take place if one party cannot completely fulfill their contractual duties. An example of this would be a contractor terminating their contract forcause because the owner failed to pay them in the time that was determined in the contract.

Possible reasons for early termination include: the PI has expended all of the awarded funding in compliance with the award terms and conditions, and has submitted all projectdeliverables; the PI is leaving U-M and theproject will not be transferred or assigned a new PI; and the sponsor has requested anearly

Project termination (or close-out) is the last stage of managing the project, and occurs after the implementation phase has ended. ... A review is then undertaken with the client and other project stakeholders, during which theproject outcomes are evaluated against theproject's stated aims and objectives.


Related Solutions

Describe the action(s) you would take if you were part of a project team tasked to...
Describe the action(s) you would take if you were part of a project team tasked to define requirements and identify system improvements to upgrade or update an existing clinical system. Be sure to include in the discussion general information about the organization and your role on the project team.
You are the project manager for a software development project for an updated management system. The...
You are the project manager for a software development project for an updated management system. The cost of doing it in-house is $27,000. You estimate you'll spend $2,000 per month updating the software with client information, government regulations, and maintenance. You know that a contractor do the programming for your company and charge a fee based on the number of personnel using the program every month. This contractor will charge you $4 per month per user of the accounting system....
If you were delivering a child , would you want to use anesthetic medication ? Would...
If you were delivering a child , would you want to use anesthetic medication ? Would you use the Lamaze method ? Why or why not ? If you were a prospective father , what would your thoughts be ? What are the pros and cons of both methods ?   
If I were evaluating a project I would use ROI as a part of the evaluation...
If I were evaluating a project I would use ROI as a part of the evaluation process. Could we do something like this for a a foreign entity?
. If you were an oligopolist and from only an economic standpoint would you want to...
. If you were an oligopolist and from only an economic standpoint would you want to act as a cartel? Why?
If you were going to Europe, would you want the U.S. dollar to be strong or...
If you were going to Europe, would you want the U.S. dollar to be strong or weak? Interpret the current exchange rate between the U.S. and the Euro (so if an item costs 10 Euros, how much does it cost in U.S. Dollars?) What are freely floating exchange rates? What are fixed exchange rates? Explain how supply and demand affect floating exchange rates. What causes a currency to appreciate and depreciate? What factors influence the exchange rate between countries? Do...
If you were starting a new job, would you want to be paid at the top...
If you were starting a new job, would you want to be paid at the top of your pay range or in the middle? What are the advantages and disadvantages to both? Provide an explanation for your response. Support your response with an APA cited reference(s).
If you were making a product to sell, why would you want to know what activities...
If you were making a product to sell, why would you want to know what activities are driving your overhead costs? Give a short example.
If you were able to genetically alter photosynthesis, propose what you would want to alter and...
If you were able to genetically alter photosynthesis, propose what you would want to alter and what would be the expected positives and negatives of your changes. Pick one plant (not the one you picked in question 3) to alter and explain what benefit your change would have for society
If you were an investor, or considering to become one, which financial statement would you want...
If you were an investor, or considering to become one, which financial statement would you want to look at? Do you consider the Cash Flow Statement significant?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT