Question

In: Operations Management

You are the project manager for a software development project for an updated management system. The...

You are the project manager for a software development project for an updated management system. The cost of doing it in-house is $27,000. You estimate you'll spend $2,000 per month updating the software with client information, government regulations, and maintenance.

You know that a contractor do the programming for your company and charge a fee based on the number of personnel using the program every month. This contractor will charge you $4 per month per user of the accounting system. You will have roughly 1,000 employees using the system each month. You'll need some additional in-house resources to manage the contract, per se, at a rate of an extra $1,100 per month.

(a) How many months can you use the system before it's better to do it in-house instead of hiring a contractor. Show your work! USE THE ALGEBRAIC FORMULATION OF THE PROBLEM! In other words, set the cost of contracting it out equal to the cost of doing it in-house, and solve for the break-even time.

(b) Outsourcing involves more than just possibly saving money. List at least five other factors that should be considered in making this outsourcing decision.

Solutions

Expert Solution

Cost of doing it in-house= Fixed cost + variable cost per month

= $27000+$2000*T

Here T shows the months

Cost of outsourcing/contracting

number of employee*cost per employee* number of the month= 1000*$4*T=$4000T

In-house resources per month cost = $1100*T

equating them

$4000T+$1100T= $27000+$2000T

=>$5100T-$2000T= $27000

=>$3100T= $27000

=>T= 8.70

Rougly it will take 8.7 months to do it in-house

b) Factors to be considered while outsourcing

  1. Technology: Whether the outsourcing agent have adequate technology t do the job
  2. Communication: Whether the agent is receptive and can be accessed every time
  3. Supervision: the contractor should work with minimal supervision and can arrange things on its own
  4. Trained resources: The contractor should have trained staffs with the advanced technology to carry out the activities in a project
  5. Reliable: the contractor should be reliable and has a reputation in the market.

Please comment if any doubt

rate me

thanks


Related Solutions

You are the Project Manager for a major software development project.
a.You are the Project Manager for a major software development project. You are concerned that one of the project constraints is going unbalanced, but the project sponsor is unable to understand your concern since he is not familiar with the concept of project constraints. How would you explain this concept and its significance in project success, to the project sponsor? You can use the Iron Triangle to illustrate the concept.b. Saudi Railways has announced a project to add a new...
Select a software system and / or a device that you are familiar with that either allows or requires the system’s software to be updated.
"Software and System Updates" Please respond to the following:Select a software system and / or a device that you are familiar with that either allows or requires the system’s software to be updated. This system could be specific software that sets on top of an operating system, the operating system itself, a mobile device, or video game consoles. Discuss how the update was applied to the system and describe the changes that the system / software update provided. In addition,...
As a software project manager, list all the software project management control areas and describe one...
As a software project manager, list all the software project management control areas and describe one in detail.                                                                               
You are the project manager of a software development company. Your company receives supplies of chips...
You are the project manager of a software development company. Your company receives supplies of chips from a foreign supplier. Their sales manager has approached you to inform you that if you can increase your order by 30%, the shipment will be free for your organization. This however will bring additional cost of $100 on your current budget that is $5000 p.a. What type of Risk is this? Identify at least three things you can do in response given consideration...
3.You are the project manager of a software development company. Your company receives supplies of chips...
3.You are the project manager of a software development company. Your company receives supplies of chips from a foreign supplier. Their sales manager has approached you to inform you that if you can increase your order by 30%, the shipment will be free for your organization. This however will bring additional cost of $100 on your current budget that is $5000 p.a. What type of Risk is this? Identify at least three things you can do in response given consideration...
List your responsibilities as a Software Development Project Manager, and explain how you measure the success...
List your responsibilities as a Software Development Project Manager, and explain how you measure the success and failure in any project? Give examples.
You are asked to check the feasibility of software development project. The initial development cost is...
You are asked to check the feasibility of software development project. The initial development cost is $10M and the project will require an annual maintenance by the team of engineers and product managers. The annual salary of the team member is $150K. In year 1, the project will require 5 team members and in years 2-4 it will require 10 team members. The subscription revenues start in year 2 and end in year 4 (3 years). The average client pays...
You are completing a software development project. This project is expected to add SIX new features...
You are completing a software development project. This project is expected to add SIX new features to a popular software program you sell to customers. The projected cost for the project is $100,000 and the development is expected to take 5 weeks. At the end of the second week, you spent $17,500 per new software feature and you completed the development of two new features. You are about to start the development of the third new software feature. Based on...
You are a software engineer and project manager, a customer approaches you and wishes you to...
You are a software engineer and project manager, a customer approaches you and wishes you to develop a software product for them Some details The interview process went well with the customer, except there was limited detail, and you are not sure if the customer has sufficient detail. Your engineering group mostly young, freshly out of college, there are few older seasoned engineers that have done large projects before You have a 1 year time limit Your management believes in...
You are a junior manager with expertise in project management and a member of a project...
You are a junior manager with expertise in project management and a member of a project team of a company that just won the bid to develop a new internet banking management system for a major bank in South Africa. The project will entail the following activities along with their respective precedence, duration and cost. Activity Code Activity Immediate Predecessor Normal Time(Weeks) Crashing Time(weeks) Normal Cost Crashing cost 1 A – 12 8 $100000 $104000 2 B A 17 15...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT