Question

In: Accounting

If I were evaluating a project I would use ROI as a part of the evaluation...

If I were evaluating a project I would use ROI as a part of the evaluation process. Could we do something like this for a a foreign entity?

Solutions

Expert Solution

We can do the same for evaluating the ROI using the following approach:-

Return on Investment (ROI) is a monetary measurement that is used to evaluate the efficiency and effectiveness of an investment made by an organisation. Investments take many forms – financial, human capital, equipment, and training programs – to name just a few. This paper will focus on the use of ROI to measure the effectiveness of project management training programs in particular. In the 1970’s, Jack Phillips of the ROI Institute, Inc. developed a Level 5 ROI evaluation, as a follow on to the Kirkpatrick Levels 1 – 4 Evaluation Model (Kirkpatrick and Kirkpatrick, 2005) for the measurement of training programs. Phillips’ Level 5 takes the measurement of the effectiveness of training program to a higher level – converting the benefits of the training to a monetary value, thereby demonstrating its value to the bottom line. The 5 levels of evaluation (Donald Kirkpatrick, 1959 Levels 1 – 4; Jack Phillips, 1970 Level 5) include:

  • Level 1: Reactions (the “smiley” sheet)
    • Did participants like the training they received?
  • Level 2: Learning
    • Are participants confident that they have learned something from the training program?
  • Level 3: Behavior/Application
    • Are participants able to apply what they learned in the training program back on the job?
  • Level 4: Results/Business Impact
    • Did the training show improvement in efficiencies, productivity, profits, costs, reduced turnover?
  • Level 5: ROI
    • Did the training program show a positive ROI?

According to Training Magazine (February 2006), aligning the training department, and therefore the training programs offered within an organisation, with business goals was a top priority for 2006. This alignment is becoming more of a priority for increasing numbers of organisations each year.

Using the ROI Methodology™ to Evaluate Project Management Training Programs

The focus of this section is to provide a general overview of the use of the ROI Methodology™ specifically around the evaluation of a project management training program. The following assumptions are made for the purposes of this example:

  • This is a new project management training program – one which is not already in place within the organisation – which, if successful, will be rolled out to the rest of the organisation
  • There will be a pilot group for the initial project management training program of no more than 20 individuals
  • The reason for project management training is to improve the project management technical skills within the organisation in order to ensure that projects are on time, within budget and formal processes are followed throughout the organisation.

This example follows the Phillips ROI Methodology™ shown above in Exhibit 1. It is provided from a high level overview and does not get into all the details.


Related Solutions

A positive evaluation of a manager would include Residual Income of zero and an ROI greater...
A positive evaluation of a manager would include Residual Income of zero and an ROI greater than the minimum requirement 1) True. 2) False. Question 4 Residual income of $10,000 indicates the manager is earning above the minimum requirement but residual income of zero ($0) indicates the manager is earning below the minimum requirement. 1) True. 2) False. Residual income should not be used to evaluate a profit center. 1) True. 2) False. The World Peace Co. has three divisions:...
A company is evaluating a prospective project. The project would use equipment that the company already...
A company is evaluating a prospective project. The project would use equipment that the company already fully owns. Is the original cost of the equipment part of the initial cost of this prospective project? Why or why not?
You are evaluating a project and during the initial evaluation you determine that there are nine...
You are evaluating a project and during the initial evaluation you determine that there are nine states that could occur along two variables. The first variable is the cost of money, and you predict the following costs and probabilities: -- the company could borrow at a weighted average cost of capital of 8% -- this has a 25% chance of occurring -- the company could borrow at a weighted average cost of capital of 9%-- this has a 40% chance...
A firm is deciding on a new project. Use the following information for the project evaluation...
A firm is deciding on a new project. Use the following information for the project evaluation and analysis:         - The initial costs are $900,000 for fixed assets. The fixed assets will be depreciated straight line to a zero book value over the 3-year life of the project. The fixed assets have an estimated salvage value of $60,000 at the end of the project.         - The project also requires an additional $200,000 for net working capital. All of the...
A firm is deciding on a new project. Use the following information for the project evaluation...
A firm is deciding on a new project. Use the following information for the project evaluation and analysis:         - The initial costs are $900,000 for fixed assets. The fixed assets will be depreciated straight line to a zero book value over the 3-year life of the project. The fixed assets have an estimated salvage value of $60,000 at the end of the project.         - The project also requires an additional $200,000 for net working capital. All of the...
A firm is deciding on a new project. Use the following information for the project evaluation...
A firm is deciding on a new project. Use the following information for the project evaluation and analysis:         - The initial costs are $900,000 for fixed assets. The fixed assets will be depreciated straight line to a zero book value over the 3-year life of the project. The fixed assets have an estimated salvage value of $60,000 at the end of the project.         - The project also requires an additional $200,000 for net working capital. All of the...
A firm is deciding on a new project. Use the following information for the project evaluation...
A firm is deciding on a new project. Use the following information for the project evaluation and analysis: - The initial costs are $900,000 for fixed assets. The fixed assets will be depreciated straight line to a zero book value over the 3-year life of the project. The fixed assets have an estimated salvage value of $60,000 at the end of the project. - The project also requires an additional $200,000 for net working capital. All of the net working...
Part 1: If you were sponsoring a project, would you want to be updated in terms...
Part 1: If you were sponsoring a project, would you want to be updated in terms of cost and schedule variance or cost and performance indexes? Why? Part 2: Give two examples of why a project might be terminated early for cause and two examples of why a project might be terminated early for convenience.
1. If you were evaluating an investment opportunity, which technique would you use and why?
Need a solution on three topics below.  1. If you were evaluating an investment opportunity, which technique would you use and why? 2. When evaluating investments, you can get data from engineering, marketing and sometimes accounting. Do you think any of these organizations have internal biases? If so, as a member of the finance department, how would you deal with them? 3. You have just discovered that your boss favors payback in evaluating investments. Should you try to talk him...
Project Evaluation. Describe the weighted average method of evaluation. How do you use it? How are...
Project Evaluation. Describe the weighted average method of evaluation. How do you use it? How are the weights determined? A university is evaluating whether to continue using their current CRM (Customer Relationship Management) software: PowerCRM - The current system is slow, had two weeks worth of outages last year and frustrates the marketing department because it isn’t flexible. The competitor is SailsForce, a CRM platform developed by a company whose founder also loves ships. It is known for being reliable...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT