Question

In: Accounting

On May 1, 2020, Jackson Construction Company contracted to construct a factory building for a total...

On May 1, 2020, Jackson Construction Company contracted to construct a factory building for a total contract price of $9,600,000. The building was completed by May 31,2022. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2020, 2021, and 2022 are given below.                                                                       

                                                                                                            2020                                    2021                      2022

Contract costs incurred during the year                            $3,400,000            $2,400,000          $2,900,000

Estimated costs to complete the contract at Dec 31           4,600,000             3,100,000                    -0-

Billings                                                                                         1,200,000           4,100,000             4,300,000

"(a)   Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2020, 2021, and 2022. (Ignore income taxes.)

(b) Using the completed-contract method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2020, 2021, and 2022. (Ignore incomes taxes.)"                               

Solutions

Expert Solution


Related Solutions

MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 2019 and...
MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 2019 and was completed in 2020. Information relating to the contract follows: 2019 2020 Costs incurred during the year $ 290,000 $ 150,000 Estimated additional cost to complete 145,000 — Billings during the year 260,000 265,000 Cash collections during the year 240,000 285,000 Required: Record the preceding transactions in MSK’s books assuming it recognizes revenue over time and uses costs incurred to measure the extent to...
On March 1, 2017, Oriole Construction Company contracted to construct a factory building for Fabrik Manufacturing...
On March 1, 2017, Oriole Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,450,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 Contract costs incurred during the year $3,052,800 $2,254,300 $1,962,900 Estimated costs to complete the contract at 12/31 3,307,200 1,962,900 –0– Billings...
On March 1, 2017, Shamrock Construction Company contracted to construct a factory building for Fabrik Manufacturing...
On March 1, 2017, Shamrock Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,390,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 Contract costs incurred during the year $3,003,300 $2,179,700 $2,117,000 Estimated costs to complete the contract at 12/31 3,386,700 2,117,000 –0– Billings...
On March 1, 2017, Pechstein Construction Company contracted to construct a factory building for Fabrik Manufacturing...
On March 1, 2017, Pechstein Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,400,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below. 2017 2018 2019 Contract Costs Incurred during the year $2,208,000 $2,230,000 $2,190,000 Estimated Costs to Complete the Contract at 12/31 $3,520,000 $2,190,000 -0- Billings...
On March 1, 2017, Oriole Construction Company contracted to construct a factory building for Fabrik Manufacturing...
On March 1, 2017, Oriole Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,410,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 Contract costs incurred during the year $2,916,400 $2,079,200 $2,244,400 Estimated costs to complete the contract at 12/31 3,423,600 2,244,400 –0– Billings...
Problem 18-10 On March 1, 2017, Sandhill Construction Company contracted to construct a factory building for...
Problem 18-10 On March 1, 2017, Sandhill Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,310,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 Contract costs incurred during the year $2,871,000 $2,304,900 $2,114,100 (2019 Row) Estimated costs to complete the contract at 12/31...
The Ugenti Construction Company contracted to construct a warehouse building for $2,600,000. Construction began in 2016...
The Ugenti Construction Company contracted to construct a warehouse building for $2,600,000. Construction began in 2016 and was completed in 2017. Data relating to the contract are summarized below:                                                                                    2016                  2017       Costs incurred during the year.................      $   360,000         $1,650,000       Estimated costs to complete as of 12/31.        1,560,000                   -             Billings during the year ..........................           430,000         2,170,000       Cash collections during the year..............           320,000         2,280,000 Required: 1.   Compute the amount of gross...
Thrasher Construction Co. was contracted to construct a building for $975,000. The building is owned by...
Thrasher Construction Co. was contracted to construct a building for $975,000. The building is owned by the customer throughout the contract period. The contract provides for progress payments. Thrasher’s accounting year ends 31 December. Work began under the contract on 1 July 20X5, and was completed on 30 September 20X7. Construction activities are summarized below by year: 20X5 Construction costs incurred during the year, $180,000; estimated costs to complete, $630,000; progress billings during the year, $153,000; and collections, $140,000. 20X6...
In January 2010, Construction Corp. contracted to construct a building for $ 6,000,000. Construction started in...
In January 2010, Construction Corp. contracted to construct a building for $ 6,000,000. Construction started in early 2010 and was completed in 2011. The following additional information is available:                                                                                                    2010                       2011        Costs incurred............................................................. $ 2,430,000            $ 2,700,000        Estimated costs to complete............................................. 2,600,000                         —        Collections during the year.............................................. 2,400,000               3,600,000          Billings for the year …………………………………………..     2,800,000                3,200,000 Used the percentage-of-completion method. Instructions Under the contract-based approach, a)     How much revenue should be reported...
On June 1, 2020, Roman Construction Company Inc. contracted to build an office building for Sicily...
On June 1, 2020, Roman Construction Company Inc. contracted to build an office building for Sicily Corp. for a total contract price of $2,600,000. On July 1, Roman estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Sicily 2020, 2021, and 2022: At At At 12/31/2020 12/31/2021 12/31/2022 Contract...