Question

In: Accounting

During 2020, Grouper Company started a construction job with a contract price of $1,610,000. The job...

During 2020, Grouper Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available.

2020

2021

2022

Costs incurred to date

$434,300 $859,560 $1,073,000

Estimated costs to complete

575,700 242,440 –0–

Billings to date

301,000 897,000 1,610,000

Collections to date

271,000 817,000 1,428,000

Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used.

Prepare all necessary journal entries for 2021. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter 0 for the amounts. For costs incurred use account Materials, Cash, Payables.)

Compute the amount of gross profit to be recognized each year, assuming the completed-contract method is used.

Solutions

Expert Solution

Please hit LIKE button if this helped. For any further explanation, please put your query in comment, will get back to you.
Part 1
2020 2021 2022
Contract price $                                                    1,610,000 $                                                                                 1,610,000 $                                                                                 1,610,000
Actual costs to date $                                                        434,300 $                                                                                    859,560 $                                                                                 1,073,000
Estimated costs to complete $                                                        575,700 $                                                                                    242,440 $                                                                                                -  
Total estimated costs $                                                    1,010,000 $                                                                                 1,102,000 $                                                                                 1,073,000
Estimated gross profit
   (actual in 2022) $                                                        600,000 $                                                                                    508,000 $                                                                                     537,000
Revenue Recognition: 43.00% 78.00%
2020 $434,300/$1,010,000 = 43% x $1,610,000 $                                                                                     692,300
     
2021 $859,560/$1,102,000 = 78% x $1,610,000 = $1,255,800 – 692,300 $                                                                                     563,500
2022 $1,610,000-$692,300-$354,200 $                                                                                     354,200
Gross profit (loss) recognized:
2020 $692,300-$434,300 $                                                                                     258,000
     
2021 $563,500-($859,560-$434,300) $                                                                                     138,240
2022 $354,200-($1,073,000-$859,560) $                                                                                     140,760
Part 2a and 2b
Year 2021
Construction in Progress $                                                                                     425,260
     Various Accounts $                                                                                     425,260
Accounts Receivable $                                                                                     897,000
     Billing on Construction Contracts $                                                                                     897,000
Cash $                                                                                     817,000
     Accounts Receivable $                                                                                     817,000
Cost of Construction $                                                                                     138,240
Construction in progress $                                                                                     425,260
     Revenue from long term contracts $                                                                                     563,500
Completed Contract:
Revenue Recognition: Gross profit (loss) recognized:
2020 $                                                                   -   $                                                                                                -  
2021 $                                                                   -   $                                                                                                -  
2022 $                                                    1,610,000 $                                                                                    537,000
Total $                                                    1,610,000 $                                                                                    537,000

Related Solutions

During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $766,500 $1,076,000 Estimated costs to complete 584,100 328,500 –0– Billings to date 300,000 893,000 1,610,000 Collections to date 267,000 809,000 1,435,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $766,500 $1,076,000 Estimated costs to complete 584,100 328,500 –0– Billings to date 300,000 893,000 1,610,000 Collections to date 267,000 809,000 1,435,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Riverbed Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Riverbed Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. T he following information is available. 2020 2021 2022 Costs incurred to date $383,800 $905,280 $1,063,000 Estimated costs to complete 626,200 198,720 –0– Billings to date 302,000 896,000 1,610,000 Collections to date 271,000 817,000 1,419,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross profit...
During 2020, Blossom Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Blossom Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $393,900 $760,380 $1,059,000 Estimated costs to complete 616,100 341,620 –0– Billings to date 299,000 905,000 1,610,000 Collections to date 268,000 818,000 1,421,000 (a) Your answer is correct. Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in...
During 2020, Flint Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Flint Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $393,900 $760,380 $1,059,000 Estimated costs to complete 616,100 341,620 –0– Billings to date 299,000 905,000 1,610,000 Collections to date 268,000 818,000 1,421,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2017, Larkspur Company started a construction job with a contract price of $1,610,000. The job...
During 2017, Larkspur Company started a construction job with a contract price of $1,610,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $405,900 $766,500 $1,076,000 Estimated costs to complete 584,100 328,500 –0– Billings to date 300,000 893,000 1,610,000 Collections to date 267,000 809,000 1,435,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017 $ Gross profit recognized...
During 2017, Culver Company started a construction job with a contract price of $1,610,000. The job...
During 2017, Culver Company started a construction job with a contract price of $1,610,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date       $393,900       $760,380       $1,059,000 Estimated costs to complete       616,100       341,620       –0– Billings to date       299,000       905,000       1,610,000 Collections to date       268,000       818,000       1,421,000    Compute the amount of gross profit to be recognized each year, assuming the...
During 2020, Shamrock Company started a construction job with a contract price of $1,600,000. The job...
During 2020, Shamrock Company started a construction job with a contract price of $1,600,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $830,680 $1,074,000 Estimated costs to complete 584,100 262,320 –0– Billings to date 302,000 898,000 1,600,000 Collections to date 272,000 818,000 1,420,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Blossom Company started a construction job with a contract price of $1,590,000. The job...
During 2020, Blossom Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $410,000 $901,180 $1,067,000 Estimated costs to complete 590,000 197,820 –0– Billings to date 297,000 903,000 1,590,000 Collections to date 271,000 805,000 1,434,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Sage Company started a construction job with a contract price of $1,620,000. The job...
During 2020, Sage Company started a construction job with a contract price of $1,620,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $444,400 $867,420 $1,060,000 Estimated costs to complete 565,600 230,580 –0– Billings to date 301,000 904,000 1,620,000 Collections to date 272,000 814,000 1,411,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT