In: Accounting
Two-Stage ABC for Manufacturing
Assume Sherwin-Williams Company, a large paint manufacturer, has
determined the following activity cost pools and cost driver levels
for the latest period:
| Activity Cost Pool | Activity Cost |
Activity Cost Driver |
|---|---|---|
| Machine setup | $900,000 |
2,500 setup hours |
| Material handling | 820,000 |
4,000 material moves |
| Machine operation | 400,000 |
20,000 machine hours |
The following data are for the production of single batches of two products, Mirlite and Subdue:
| Mirlite | Subdue | |
|---|---|---|
| Gallons produced | 60,000 | 25,000 |
| Direct labor hours | 400 | 250 |
| Machine hours | 800 | 250 |
| Direct labor cost | $10,000 | $7,500 |
| Direct materials cost | $360,000 | $150,000 |
| Setup hours | 15 | 12 |
| Material moves | 60 | 35 |
Determine the batch and unit costs per gallon of Mirlite and
Subdue using ABC.
Round cost per gallon to two decimal places.
| Product Costs | ||
|---|---|---|
|
Mirlite |
Subdue |
|
| Direct materials | Answer | Answer |
| Direct labor | Answer | Answer |
| Manufacturing overhead: | ||
| Machine setups | Answer | Answer |
| Material handling | Answer | Answer |
| Machine operation | Answer | Answer |
| Total cost per batch | Answer | Answer |
| Gallons produced | Answer | Answer |
| Cost per gallon | Answer | Answer |
| Product Costs | ||
| Mirlite | Subdue | |
| Direct materials | $ 360,000 | $ 150,000 |
| Direct labor | $ 10,000 | $ 7,500 |
| Manufacturing overhead: | ||
| Machine setups | $ 5,400 | $ 4,320 |
| Material handling | $ 12,300 | $ 7,175 |
| Machine operation | $ 16,000 | $ 5,000 |
| Total cost per batch | $ 403,700 | $ 173,995 |
| Gallons produced | 60000 | 25000 |
| Cost per gallon | $ 6.73 | $ 6.96 |
| Activity | Total Overhead | Cost Driver | Total Number | Cost per Cost Driver | |
| a | b | c | d | e = b/d | |
| Machine Setup | $ 900,000 | Setup Hours | 2500 | $ 360 | Per Setup Hour |
| Material Handling | $ 820,000 | Material Moves | 4000 | $ 205 | Per Material Move |
| Machine Operation | $ 400,000 | Machine Hours | 20000 | $ 20 | Per Machine Hour |
| $2,120,000 |