Question

In: Accounting

Two-Stage ABC for Manufacturing Assume Sherwin-Williams Company, a large paint manufacturer, has determined the following activity...

Two-Stage ABC for Manufacturing
Assume Sherwin-Williams Company, a large paint manufacturer, has determined the following activity cost pools and cost driver levels for the latest period:

Activity Cost Pool Activity Cost

Activity Cost Driver

Machine setup $900,000

2,500 setup hours

Material handling 820,000

4,000 material moves

Machine operation 400,000

20,000 machine hours

The following data are for the production of single batches of two products, Mirlite and Subdue:

Mirlite Subdue
Gallons produced 60,000 25,000
Direct labor hours 400 250
Machine hours 800 250
Direct labor cost $10,000 $7,500
Direct materials cost $360,000 $150,000
Setup hours 15 12
Material moves 60 35

Determine the batch and unit costs per gallon of Mirlite and Subdue using ABC.
Round cost per gallon to two decimal places.

Product Costs

Mirlite

Subdue

Direct materials Answer Answer
Direct labor Answer Answer
Manufacturing overhead:
Machine setups Answer Answer
Material handling Answer Answer
Machine operation Answer Answer
Total cost per batch Answer Answer
Gallons produced Answer Answer
Cost per gallon Answer Answer

Solutions

Expert Solution

Product Costs
Mirlite Subdue
Direct materials $   360,000 $   150,000
Direct labor $      10,000 $        7,500
Manufacturing overhead:
Machine setups $        5,400 $        4,320
Material handling $      12,300 $        7,175
Machine operation $      16,000 $        5,000
Total cost per batch $   403,700 $   173,995
Gallons produced 60000 25000
Cost per gallon $          6.73 $          6.96
Activity Total Overhead Cost Driver Total Number Cost per Cost Driver
a b c d e = b/d
Machine Setup $   900,000 Setup Hours 2500 $           360 Per Setup Hour
Material Handling $   820,000 Material Moves 4000 $           205 Per Material Move
Machine Operation $   400,000 Machine Hours 20000 $             20 Per Machine Hour
$2,120,000

Related Solutions

Two-Stage ABC for Manufacturing Assume Sherwin-Williams Company, a large paint manufacturer, has determined the following activity...
Two-Stage ABC for Manufacturing Assume Sherwin-Williams Company, a large paint manufacturer, has determined the following activity cost pools and cost driver levels for the latest period: Activity Cost Pool Activity Cost Activity Cost Driver Machine setup $990,000     2,500 setup hours Material handling 860,000 5,000 material moves Machine operation 200,000   20,000 machine hours The following data are for the production of single batches of two products, Mirlite and Subdue: Mirlite Subdue Gallons produced 50,000 30,000 Direct labor hours 400 250...
Two-Stage ABC for Manufacturing Assume Sherwin-Williams Company, a large paint manufacturer, has determined the following activity...
Two-Stage ABC for Manufacturing Assume Sherwin-Williams Company, a large paint manufacturer, has determined the following activity cost pools and cost driver levels for the latest period: Activity cost pool Activity cost Activity cost driver Machine setup $950,000 2,500 setup hours Material handling 620,000 5,000 material moves Machine operation 200,000 20,000 machine hours The following data are for the production of single batches of two products, Mirlite and Subdue: Mirlite Subdue Gallons produced 60,000 10,000 Direct labor hours 500 350 Machine...
Two-Stage ABC for Manufacturing with Variances Montreat Manufacturing has developed the following activity cost pool information...
Two-Stage ABC for Manufacturing with Variances Montreat Manufacturing has developed the following activity cost pool information for its 2016 manufacturing activities: Budgeted Activity Cost Activity Cost Driver at Practical Capacity Purchasing and materials handling $2,700,000 900,000 kilograms Setup 2,800,000 1,120 setups Machine operations 3,816,000 12,000 hours First unit inspection 200,000 1,000 batches Packaging 1,000,000 312,500 units Actual 2016 production information is as follows: Standard Product A Standard Product B Specialty Products Units 150,000 100,000 50,000 Batches 100 80 600 Setups*...
Two-Stage ABC for Manufacturing Vollrath Manufacturing, a division of The Vollrath Company, manufactures restaurant equipment. Assume...
Two-Stage ABC for Manufacturing Vollrath Manufacturing, a division of The Vollrath Company, manufactures restaurant equipment. Assume the company has determined the following activity cost pools and cost driver levels for the year: Activity Cost Pool Activity Cost Activity Cost Driver Machine setup $ 750,000 18,750 setup hours Material handling 121,600 3,800 tons of materials Machine operation 552,500 16,250 machine hours The following data are for the production of single batches of two products, Equipment Stands and Charbroilers during the month...
Assume a company that uses activity-based costing (ABC) has only two products – A and B....
Assume a company that uses activity-based costing (ABC) has only two products – A and B. The company does not have any organization-sustaining activities or unused capacity costs. The company’s total manufacturing overhead cost of $56,000 has been allocated to the three activities shown below: Setups Machining Packing Orders Activity measure quantity: Product A 20 1,000 150 Activity measure quantity: Product B 20 ? 350 Overhead cost per activity cost pool ? ? $ 10,000 Activity rate    $ 150 per...
Traditional Product Costing versus Activity-Based Costing Assume that Panasonic Company has determined its estimated total manufacturing...
Traditional Product Costing versus Activity-Based Costing Assume that Panasonic Company has determined its estimated total manufacturing overhead cost for one of its plants to be $636,400 consisting of the following activity cost pools for the current month: Activity Centers Activity Costs Cost Drivers Activity Level Assembly setups $ 132,000 Setup hours 2,000 Materials handing 64,800 Number of moves 600 Assembly 360,000 Assembly hours 18,000 Maintenance 79,600 Maintenance hours 1,990 Total $636,400 Total direct labor hours used during the month were...
Traditional Product Costing Versus Activity-Based Costing Assume that Panasonic Company has determined its estimated total manufacturing...
Traditional Product Costing Versus Activity-Based Costing Assume that Panasonic Company has determined its estimated total manufacturing overhead cost for one of its plants to be $252,000, consisting of the following activity cost pools for the current month: Activity Centers Activity Costs Cost Drivers Activity Level Assembly setups $69,000 Setup hours 1,500 Materials handling 39,000 Number of moves 300 Assembly 120,000 Assembly hours 12,000 Maintenance 24,000 Maintenance hours 1,200 Total $252,000 Total direct labor hours used during the month were 8,000....
Traditional Product Costing Versus Activity-Based Costing Assume that Panasonic Company has determined its estimated total manufacturing...
Traditional Product Costing Versus Activity-Based Costing Assume that Panasonic Company has determined its estimated total manufacturing overhead cost for one of its plants to be $216,000, consisting of the following activity cost pools for the current month: Activity Centers Activity Costs Cost Drivers Activity Level Assembly setups $51,000 Setup hours 1,500 Materials handling 21,000 Number of moves 300 Assembly 120,000 Assembly hours 12,000 Maintenance 24,000 Maintenance hours 1,200 Total $216,000 Total direct labor hours used during the month were 8,000....
Traditional Product Costing Versus Activity-Based Costing Assume that Panasonic Company has determined its estimated total manufacturing...
Traditional Product Costing Versus Activity-Based Costing Assume that Panasonic Company has determined its estimated total manufacturing overhead cost for one of its plants to be $216,000, consisting of the following activity cost pools for the current month: Activity Centers Activity Costs Cost Drivers Activity Level Assembly setups $51,000 Setup hours 1,500 Materials handling 21,000 Number of moves 300 Assembly 120,000 Assembly hours 12,000 Maintenance 24,000 Maintenance hours 1,200 Total $216,000 Total direct labor hours used during the month were 8,000....
Traditional Product Costing versus Activity-Based Costing Assume that Panasonic Company has determined its estimated total manufacturing...
Traditional Product Costing versus Activity-Based Costing Assume that Panasonic Company has determined its estimated total manufacturing overhead cost for one of its plants to be $436,000 consisting of the following activity cost pools for the current month: Activity Centers Activity Costs Cost Drivers Activity Level Assembly setups $ 124,000 Setup hours 4,000 Materials handling 57,000 Number of moves 600 Assembly 225,000 Assembly hours 12,500 Maintenance 30,000 Maintenance hours 1,200 Total $436,000 Total direct labor hours used during the month were...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT