Question

In: Accounting

Two-Stage ABC for Manufacturing with Variances Montreat Manufacturing has developed the following activity cost pool information...

Two-Stage ABC for Manufacturing with Variances
Montreat Manufacturing has developed the following activity cost pool information for its 2016 manufacturing activities:

Budgeted Activity Cost

Activity Cost Driver at Practical Capacity

Purchasing and materials handling

$2,700,000

900,000 kilograms
Setup

2,800,000

1,120 setups

Machine operations

3,816,000

12,000 hours

First unit inspection

200,000

1,000 batches

Packaging

1,000,000

312,500 units

Actual 2016 production information is as follows:

Standard Product A

Standard Product B

Specialty Products

Units 150,000 100,000 50,000
Batches 100 80 600
Setups* 300 160 900
Machine operations (hours) 6,000 3,000 2,000
Kilograms of raw materials 400,000 300,000 200,000
Direct materials costs $900,000 $600,000 $820,000

*Some products require setups on two or more machines.



a. Determine the unit cost of each product for Montreat Manufacturing.
Round rates to two decimal places.
Activity-based overhead rates:

Purchasing & materials handling $Answer
Setup $Answer
Machine operations $Answer
First unit inspection $Answer
Packaging $Answer

Use rounded overhead rates calculated above for calculations below. Round cost answers to the nearest whole number, when needed.
Round cost per unit to two decimal places.

Standard Product A Standard Product B Specialty Products
Direct material $Answer $Answer $Answer
Overhead cost
Purchasing & handling Answer Answer Answer
Setup Answer Answer Answer
Machine operations Answer Answer Answer
First unit inspection Answer Answer Answer
Packaging Answer Answer Answer
Total costs $Answer $Answer $Answer
Units Answer Answer Answer
Cost per unit $Answer $Answer $Answer

Solutions

Expert Solution

ANSWER a

Activity-based overhead rates

b

NOTES------------------->


Related Solutions

Stage 2 ABC for Manufacturing: Reassigning Costs to Cost Objects Woodland Corporation has developed the following...
Stage 2 ABC for Manufacturing: Reassigning Costs to Cost Objects Woodland Corporation has developed the following activity cost information for its manufacturing activities: Activity Activity cost Machine setup $ 70.00 per batch Movement 12.00 per batch move 0.12 per pound Drilling 5.00 per hole Welding 3.00 per inch Shaping 20.00 per hour Assembly 16.00 per hour Inspection 1.50 per unit Filling an order for a batch of 100 fireplace inserts (each insert weighing 50 pounds) required the following: Three batch...
Compute the ABC rates based on the following information: Activity Cost Pool (a) Estimated Overhead Cost...
Compute the ABC rates based on the following information: Activity Cost Pool (a) Estimated Overhead Cost (b) Expected Activity Labor related........................... $ 5,200 800 DLHs Machine related....................... 1,500 2,000 MHs Machine setups........................ 4,200 100 setups Production orders..................... 1,800 50 orders Product testing........................ 4,800 200 tests Packaging............................... 7,000 500 packages General factory........................ 108,800 800 DLHs Compute the single overall predetermined overhead rate based entirely on direct labor-hours: Compute the cost for completing 100,000 widgets if the direct materials cost was $45,000...
Two-Stage ABC for Manufacturing Assume Sherwin-Williams Company, a large paint manufacturer, has determined the following activity...
Two-Stage ABC for Manufacturing Assume Sherwin-Williams Company, a large paint manufacturer, has determined the following activity cost pools and cost driver levels for the latest period: Activity Cost Pool Activity Cost Activity Cost Driver Machine setup $900,000 2,500 setup hours Material handling 820,000 4,000 material moves Machine operation 400,000 20,000 machine hours The following data are for the production of single batches of two products, Mirlite and Subdue: Mirlite Subdue Gallons produced 60,000 25,000 Direct labor hours 400 250 Machine...
Two-Stage ABC for Manufacturing Assume Sherwin-Williams Company, a large paint manufacturer, has determined the following activity...
Two-Stage ABC for Manufacturing Assume Sherwin-Williams Company, a large paint manufacturer, has determined the following activity cost pools and cost driver levels for the latest period: Activity Cost Pool Activity Cost Activity Cost Driver Machine setup $990,000     2,500 setup hours Material handling 860,000 5,000 material moves Machine operation 200,000   20,000 machine hours The following data are for the production of single batches of two products, Mirlite and Subdue: Mirlite Subdue Gallons produced 50,000 30,000 Direct labor hours 400 250...
Two-Stage ABC for Manufacturing Assume Sherwin-Williams Company, a large paint manufacturer, has determined the following activity...
Two-Stage ABC for Manufacturing Assume Sherwin-Williams Company, a large paint manufacturer, has determined the following activity cost pools and cost driver levels for the latest period: Activity cost pool Activity cost Activity cost driver Machine setup $950,000 2,500 setup hours Material handling 620,000 5,000 material moves Machine operation 200,000 20,000 machine hours The following data are for the production of single batches of two products, Mirlite and Subdue: Mirlite Subdue Gallons produced 60,000 10,000 Direct labor hours 500 350 Machine...
Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity...
Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity for Tyler Company for September: Standard cost per unit Direct materials 4 units of material A × $2.00 per unit 1 unit of material B × $3.00 per unit Direct labor 3 hours × $8.00 per hour Activity for September Materials purchased Material A 2,600 units × $2.05 per unit Material B 700 units × $3.10 per unit Materials used Material A 2,250 units...
Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity...
Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity for Repine Company for September: Standard cost per unit Direct materials 3 units of material A x $8.00 per unit 2 units of material B x $4.00 per unit Direct labor 2 hours x $15.00 per hour Activity for September Materials purchased Material A 7,000 units x $7.80 per unit Material B 4,800 units x $4.50 per unit Materials used Material A 6,430 units...
Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity...
Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity for Repine Company for September: Standard cost per unit Direct materials 4 units of material A x $ 6.00 per unit 1 unit of material B x $ 8.00 per unit Direct labor 3 hours x $ 18.00 per hour Activity for September Materials purchased Material A 6,750 units x $ 6.20 per unit Material B 1,650 units x $ 8.50 per unit Materials...
2) Gable Company uses three activity cost pools. Each pool has a cost driver. Information for...
2) Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Total Cost of Pool Cost Driver Estimated Cost Driver Machining $ 380,120 Number of machine hours 88,400 Designing costs 86,400 Number of design hours 9,000 Setup costs 74,672 Number of batches 525 Suppose that Gable Company manufactures three products, A, B, and C. Information about these products follows: Product A Product B Product C Number of machine hours...
Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable...
Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Total Cost of Pool Cost Driver Estimated Cost Driver Machining $ 259,000 Number of machine hours 85,600 Designing costs 59,000 Number of design hours 7,800 Setup costs 72,000 Number of batches 370 Required: 1. Compute the activity rate for each activity. (Round your answers to 2 decimal places.) Activity Activity Rate Machining per Machine Hrs Design Costs per Design...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT