Question

In: Accounting

Two-Stage ABC for Manufacturing Assume Sherwin-Williams Company, a large paint manufacturer, has determined the following activity...

Two-Stage ABC for Manufacturing
Assume Sherwin-Williams Company, a large paint manufacturer, has determined the following activity cost pools and cost driver levels for the latest period:

Activity Cost Pool Activity Cost

Activity Cost Driver

Machine setup $990,000

    2,500 setup hours

Material handling 860,000

5,000 material moves

Machine operation 200,000

  20,000 machine hours

The following data are for the production of single batches of two products, Mirlite and Subdue:

Mirlite Subdue
Gallons produced 50,000 30,000
Direct labor hours 400 250
Machine hours 800 250
Direct labor cost $10,500 $8,000
Direct materials cost $390,000 $190,000
Setup hours 15 12
Material moves 60 35

Determine the batch and unit costs per gallon of Mirlite and Subdue using ABC.
Round cost per gallon to two decimal places.

Product Costs

Mirlite

Subdue

Direct materials $Answer $Answer
Direct labor Answer Answer
Manufacturing overhead:
Machine setups Answer Answer
Material handling Answer Answer
Machine operation Answer Answer
Total cost per batch $Answer $Answer
Gallons produced Answer Answer
Cost per gallon $Answer $

Solutions

Expert Solution

  • All working forms part of the answer
  • Working #1: Calculation of activity rates

Activity Cost Pool

Activity Cost

Activity Cost Driver

Activity Rate per driver

Machine setup

$                        990,000.00

              2,500

$                                           396.00 per setup hrs

Material handling

$                        860,000.00

              5,000

$                                           172.00 per material move

Machine operation

$                        200,000.00

           20,000

$                                              10.00 per machine hour

  • Completion of table

Product Costs

Mirlite

Subdue

Direct materials

$                        390,000.00

$           190,000.00

Direct labor

$                          10,500.00

$               8,000.00

Manufacturing overhead:

Machine setups

$                           5,940.00

$               4,752.00

Material handling

$                          10,320.00

$               6,020.00

Machine operation

$                           8,000.00

$               2,500.00

Total cost per batch

$                        424,760.00

$           211,272.00

Gallons produced

                                 50,000

                    30,000

Cost per gallon

$                                  8.50

$                     7.04

  • Working for above

Product Costs

Mirlite

Subdue

Direct materials

390000

190000

Direct labor

10500

8000

Manufacturing overhead:

Machine setups

=15*396

=12*396

Material handling

=60*172

=35*172

Machine operation

=800*10

=250*10

Total cost per batch

Total (A)

Total (A)

Gallons produced

50000 (B)

30000 (B)

Cost per gallon

A / B

A / B


Related Solutions

Two-Stage ABC for Manufacturing Assume Sherwin-Williams Company, a large paint manufacturer, has determined the following activity...
Two-Stage ABC for Manufacturing Assume Sherwin-Williams Company, a large paint manufacturer, has determined the following activity cost pools and cost driver levels for the latest period: Activity Cost Pool Activity Cost Activity Cost Driver Machine setup $900,000 2,500 setup hours Material handling 820,000 4,000 material moves Machine operation 400,000 20,000 machine hours The following data are for the production of single batches of two products, Mirlite and Subdue: Mirlite Subdue Gallons produced 60,000 25,000 Direct labor hours 400 250 Machine...
Two-Stage ABC for Manufacturing Assume Sherwin-Williams Company, a large paint manufacturer, has determined the following activity...
Two-Stage ABC for Manufacturing Assume Sherwin-Williams Company, a large paint manufacturer, has determined the following activity cost pools and cost driver levels for the latest period: Activity cost pool Activity cost Activity cost driver Machine setup $950,000 2,500 setup hours Material handling 620,000 5,000 material moves Machine operation 200,000 20,000 machine hours The following data are for the production of single batches of two products, Mirlite and Subdue: Mirlite Subdue Gallons produced 60,000 10,000 Direct labor hours 500 350 Machine...
Two-Stage ABC for Manufacturing Detroit Foundry, a large manufacturer of heavy equipment components, has determined the...
Two-Stage ABC for Manufacturing Detroit Foundry, a large manufacturer of heavy equipment components, has determined the following activity cost pools and cost driver levels for the year: Activity Cost Pool Activity Cost Activity Cost Driver Machine setup $588,000 12,000 setup hours Material handling 108,000 2,000 material moves Machine operation 500,000 10,000 machine hours The following data are for the production of single batches of two products, C23 Cams and U2 Shafts during the month of August: C23 Cams U2 Shafts...
Two-Stage ABC for Manufacturing with Variances Montreat Manufacturing has developed the following activity cost pool information...
Two-Stage ABC for Manufacturing with Variances Montreat Manufacturing has developed the following activity cost pool information for its 2016 manufacturing activities: Budgeted Activity Cost Activity Cost Driver at Practical Capacity Purchasing and materials handling $2,700,000 900,000 kilograms Setup 2,800,000 1,120 setups Machine operations 3,816,000 12,000 hours First unit inspection 200,000 1,000 batches Packaging 1,000,000 312,500 units Actual 2016 production information is as follows: Standard Product A Standard Product B Specialty Products Units 150,000 100,000 50,000 Batches 100 80 600 Setups*...
Two-Stage ABC for Manufacturing Vollrath Manufacturing, a division of The Vollrath Company, manufactures restaurant equipment. Assume...
Two-Stage ABC for Manufacturing Vollrath Manufacturing, a division of The Vollrath Company, manufactures restaurant equipment. Assume the company has determined the following activity cost pools and cost driver levels for the year: Activity Cost Pool Activity Cost Activity Cost Driver Machine setup $ 750,000 18,750 setup hours Material handling 121,600 3,800 tons of materials Machine operation 552,500 16,250 machine hours The following data are for the production of single batches of two products, Equipment Stands and Charbroilers during the month...
Assume a company that uses activity-based costing (ABC) has only two products – A and B....
Assume a company that uses activity-based costing (ABC) has only two products – A and B. The company does not have any organization-sustaining activities or unused capacity costs. The company’s total manufacturing overhead cost of $56,000 has been allocated to the three activities shown below: Setups Machining Packing Orders Activity measure quantity: Product A 20 1,000 150 Activity measure quantity: Product B 20 ? 350 Overhead cost per activity cost pool ? ? $ 10,000 Activity rate    $ 150 per...
Traditional Product Costing versus Activity-Based Costing Assume that Panasonic Company has determined its estimated total manufacturing...
Traditional Product Costing versus Activity-Based Costing Assume that Panasonic Company has determined its estimated total manufacturing overhead cost for one of its plants to be $636,400 consisting of the following activity cost pools for the current month: Activity Centers Activity Costs Cost Drivers Activity Level Assembly setups $ 132,000 Setup hours 2,000 Materials handing 64,800 Number of moves 600 Assembly 360,000 Assembly hours 18,000 Maintenance 79,600 Maintenance hours 1,990 Total $636,400 Total direct labor hours used during the month were...
Traditional Product Costing Versus Activity-Based Costing Assume that Panasonic Company has determined its estimated total manufacturing...
Traditional Product Costing Versus Activity-Based Costing Assume that Panasonic Company has determined its estimated total manufacturing overhead cost for one of its plants to be $252,000, consisting of the following activity cost pools for the current month: Activity Centers Activity Costs Cost Drivers Activity Level Assembly setups $69,000 Setup hours 1,500 Materials handling 39,000 Number of moves 300 Assembly 120,000 Assembly hours 12,000 Maintenance 24,000 Maintenance hours 1,200 Total $252,000 Total direct labor hours used during the month were 8,000....
Traditional Product Costing Versus Activity-Based Costing Assume that Panasonic Company has determined its estimated total manufacturing...
Traditional Product Costing Versus Activity-Based Costing Assume that Panasonic Company has determined its estimated total manufacturing overhead cost for one of its plants to be $216,000, consisting of the following activity cost pools for the current month: Activity Centers Activity Costs Cost Drivers Activity Level Assembly setups $51,000 Setup hours 1,500 Materials handling 21,000 Number of moves 300 Assembly 120,000 Assembly hours 12,000 Maintenance 24,000 Maintenance hours 1,200 Total $216,000 Total direct labor hours used during the month were 8,000....
Traditional Product Costing Versus Activity-Based Costing Assume that Panasonic Company has determined its estimated total manufacturing...
Traditional Product Costing Versus Activity-Based Costing Assume that Panasonic Company has determined its estimated total manufacturing overhead cost for one of its plants to be $216,000, consisting of the following activity cost pools for the current month: Activity Centers Activity Costs Cost Drivers Activity Level Assembly setups $51,000 Setup hours 1,500 Materials handling 21,000 Number of moves 300 Assembly 120,000 Assembly hours 12,000 Maintenance 24,000 Maintenance hours 1,200 Total $216,000 Total direct labor hours used during the month were 8,000....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT