In: Accounting
Two-Stage ABC for Manufacturing
Assume Sherwin-Williams Company, a large paint manufacturer, has
determined the following activity cost pools and cost driver levels
for the latest period:
Activity Cost Pool | Activity Cost |
Activity Cost Driver |
---|---|---|
Machine setup | $990,000 |
2,500 setup hours |
Material handling | 860,000 |
5,000 material moves |
Machine operation | 200,000 |
20,000 machine hours |
The following data are for the production of single batches of two products, Mirlite and Subdue:
Mirlite | Subdue | |
---|---|---|
Gallons produced | 50,000 | 30,000 |
Direct labor hours | 400 | 250 |
Machine hours | 800 | 250 |
Direct labor cost | $10,500 | $8,000 |
Direct materials cost | $390,000 | $190,000 |
Setup hours | 15 | 12 |
Material moves | 60 | 35 |
Determine the batch and unit costs per gallon of Mirlite and
Subdue using ABC.
Round cost per gallon to two decimal places.
Product Costs | ||
---|---|---|
Mirlite |
Subdue |
|
Direct materials | $Answer | $Answer |
Direct labor | Answer | Answer |
Manufacturing overhead: | ||
Machine setups | Answer | Answer |
Material handling | Answer | Answer |
Machine operation | Answer | Answer |
Total cost per batch | $Answer | $Answer |
Gallons produced | Answer | Answer |
Cost per gallon | $Answer | $ |
Activity Cost Pool |
Activity Cost |
Activity Cost Driver |
Activity Rate per driver |
Machine setup |
$ 990,000.00 |
2,500 |
$ 396.00 per setup hrs |
Material handling |
$ 860,000.00 |
5,000 |
$ 172.00 per material move |
Machine operation |
$ 200,000.00 |
20,000 |
$ 10.00 per machine hour |
Product Costs |
||
Mirlite |
Subdue |
|
Direct materials |
$ 390,000.00 |
$ 190,000.00 |
Direct labor |
$ 10,500.00 |
$ 8,000.00 |
Manufacturing overhead: |
||
Machine setups |
$ 5,940.00 |
$ 4,752.00 |
Material handling |
$ 10,320.00 |
$ 6,020.00 |
Machine operation |
$ 8,000.00 |
$ 2,500.00 |
Total cost per batch |
$ 424,760.00 |
$ 211,272.00 |
Gallons produced |
50,000 |
30,000 |
Cost per gallon |
$ 8.50 |
$ 7.04 |
Product Costs |
||
Mirlite |
Subdue |
|
Direct materials |
390000 |
190000 |
Direct labor |
10500 |
8000 |
Manufacturing overhead: |
||
Machine setups |
=15*396 |
=12*396 |
Material handling |
=60*172 |
=35*172 |
Machine operation |
=800*10 |
=250*10 |
Total cost per batch |
Total (A) |
Total (A) |
Gallons produced |
50000 (B) |
30000 (B) |
Cost per gallon |
A / B |
A / B |