Question

In: Operations Management

1.The following time estimates are given for an activity: optimistic time = 16 days, most likely...

1.The following time estimates are given for an activity: optimistic time = 16 days, most likely time = 24 days and pessimistic time = 40 days.

What is the variance of this activity?

Group of answer choices

A. 9

B. 16

C. 20

D. 24

E. None of these answers are correct

2.The expected waiting time in line is equal to the expected number of customers in line divided by the arrival rate

Group of answer choices

True

False

3. Activities C and D are the immediate predecessors of activity E. The early finish time (EF) of activity C is 35; and the early finish time (EF) of activity D is 42. What is the early start (ES) time of activity E?

Group of answer choices

A. 35

B. 42

C. 77

D. 38.5

E. None of these answers are correct

4. The goal of queueing analysis is to minimize:

Group of answer choices :

A.the sum of customer waiting costs and service costs.

B. the sum of customer waiting time and service time.

C.service costs.

D. customer waiting time.

E. None of the answer choices is correct.

5. All preceding activities have to be completed before work can start on a follower activity.

Group of answer choices

True

False

Solutions

Expert Solution

1.The following time estimates are given for an activity: optimistic time = 16 days, most likely time = 24 days and pessimistic time = 40 days.

What is the variance of this activity?

Given that

Optimistic Time = 16 Days

Most Likely time = 24 Days

Pessimistic Time = 40 Days

Variance = ((pessimistic time - optimistic time)/6)^2=((40-16)/6)^2 =4^2=16

hence, correct answer is 16

2.The expected waiting time in line is equal to the expected number of customers in line divided by the arrival rate

True

3. Activities C and D are the immediate predecessors of activity E. The early finish time (EF) of activity C is 35; and the early finish time (EF) of activity D is 42. What is the early start (ES) time of activity E?

Since C and D are both predecessors of E, then E can start only when both C and D has completed.

So E can start later of 35 and 42. The correct answer is 42

4. The goal of queueing analysis is to minimize:

A. the sum of customer waiting costs and capacity costs


Related Solutions

1. The following time estimates are given for an activity: optimistic time = 16 days, most...
1. The following time estimates are given for an activity: optimistic time = 16 days, most likely time = 24 days and pessimistic time = 38 days. What is the expected time to complete this activity? Group of answer choices A. 16 B. 24 C. 38 D. 25 E. None of these answers are correct 2. The project duration is equal to the sum of the durations of all activities in a network. Group of answer choices True False 3.The...
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC...
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC TIME (days) A - 5 10 15 B - 10 12 14 C - 10 10 10 D B,C 2 4 6 E A 4 8 12 F A 4 8 12 G D,E 10 12 14 I F 4 8 12 J G 2 4 6 The total slack for activity C is __________
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC...
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC TIME (days) A - 5 10 15 B - 10 12 14 C - 10 10 10 D B,C 2 4 6 E A 4 8 12 F A 4 8 12 G D,E 10 12 14 I F 4 8 12 J G 2 4 6 The total slack for activity C is __________ a. 0 b. 2 c. 8 d. 4
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC...
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC TIME (days) A - 5 10 15 B - 10 12 14 C - 10 10 10 D B,C 2 4 6 E A 4 8 12 F A 4 8 12 G D,E 10 12 14 I F 4 8 12 J G 2 4 6 The total slack for activity F is __________ a. 8 b. 4 c. 2 d. 0
Use the following project information: Activity Optimistic Time Estimate(weeks) Most Likely Time Estimates (weeks) Pessimistic Time...
Use the following project information: Activity Optimistic Time Estimate(weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s) A 2 7 11 none B 2 5 9 A C 4 6 12 A D 5 6 10 B E 6 10 17 C F 3 4 6 D,E G 3 6 10 D,E H 5 7 10 F I 5 8 11 G J 3 3 3 H,I (a) Calculate the expected completion time for this project. (Round...
Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s)...
Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s) A 3 6 9 none B 3 5 7 A C 4 7 12 A D 4 8 10 B E 5 10 16 C F 3 4 5 D, E G 3 6 8 D, E H 5 6 10 F I 5 8 11 G J 3 3 3 H, I A.)Using the information given, construct a network diagram using AON notation....
Consider the following project. Times (days) Activity Optimistic Most Likely Pessimistic Preceding Tasks 1 8 10...
Consider the following project. Times (days) Activity Optimistic Most Likely Pessimistic Preceding Tasks 1 8 10 13 - 2 5 6 8 - 3 13 15 21 2 4 10 12 14 1,3 5 11 20 30 4 6 4 5 8 5 7 2 3 4 5 8 4 6 10 7 9 2 3 4 8,6 Draw the AON Network Diagram Compute the expected activity time Using the expected activity times, compute the early start, early finish, late...
QUESTION 7    [18 MARKS) In the following table, optimistic, most likely and pessimistic time estimates have...
QUESTION 7    [18 MARKS) In the following table, optimistic, most likely and pessimistic time estimates have been given for each activity for a project. Task Immediate Predecessor(s) Time (days) Optimistic (a) Most Likely (m) Pessimistic (b) A None 5 7 12 B None 8 8 8 C A 2 6 10 D A,B 12 14 19 E C,D 6 6 12 F B,E 3 12 18 G F 6 8 10 Construct an activity on node network diagram for this...
Use the following table to answer questions. Activity a (Optimistic Time Estimate) m (Most Likely Estimate)...
Use the following table to answer questions. Activity a (Optimistic Time Estimate) m (Most Likely Estimate) b (Pessimistic Time Estimate) A 3 8 13 B 3 6 9 C 4 6 8 D 7 9 11 E 5 7 12 What is the expected time for activity c? 5.167 3 4.28 6 What is the variance for activity A? 3.33 2.77 5.31 .674 Assume there is one critical path of (A, B, C, E) what is the project variance? 5.583...
Times (days) Activity Optimistic Most Likely Pessimistic Preceding Tasks 1 8 10 13 - 2 5...
Times (days) Activity Optimistic Most Likely Pessimistic Preceding Tasks 1 8 10 13 - 2 5 6 8 - 3 13 15 21 2 4 10 12 14 1,3 5 11 20 30 4 6 4 5 8 5 7 2 3 4 5 8 4 6 10 7 9 2 3 4 8,6 Draw the AON Network Diagram Compute the expected activity time Using the expected activity times, compute the early start, early finish, late start, late finish, and...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT