Create a network diagram (graphical diagram) that shows the sequence and dependent relationships identified in the Astin Martin project activity list and activity duration schedule.
Provide a project objective associated with the Astin Martin Graphics project. Include a list of assumptions about the project. What is a work breakdown structure? What is a responsibility matrix? Using the Astin Martin project activity list and activity duration schedule, create a WBS and RAM.
STATEMENT OF WORK SUMMARY
RFP awarded for specific web services which will be incorporated into a web graphics company (Astin Martin Graphics LLC). Topical level requirements for the software were provided. Deliverable products include:
⦁ Systems Engineering to provide appropriate requirements decomposition
⦁ Software Engineering to provide design/development/unit test of software
⦁ System Test Engineering to provide component and enterprise level testing
⦁ Quality Engineering to provide quality control through the entire development life cycle
⦁ Management functions to include all primary functions (project management, finance, planning & scheduling, Overhead support (contracts, engineering matrix, etc.)
Award date of May 15 and required completion date (deliverables provided) of November 15.
Astin Martin Graphics request of planned deliverables, acceptance criteria, quality plan, and work breakdown structure. These items need to be provided in an acceptable time for Astin Martin to review and approve.
Astin Martin Graphics further requests other deliverables to include final software (source and binary) which meets all approved acceptance criteria, associated design documents (system and development level)
All project questions or request for project scope changes should be directed to the Astin Martin Graphic designee (course instructor).
There is no requirement relative to project tools used to generate the required data.
Topical requirements include:
⦁ System Engineering: UML design appropriate graphic widgets to display aeronautical expanse gauges within the technical specs guidelines for twenty-five different visual aspects. Include appropriate level of peer review. Design should include graphical mock-up of gauges.
⦁ System Engineering: Derive component level requirements for Software Engineering to design, code, and unit test and System Test can provide System and Enterprise level testing
⦁ Software Engineering: Provide appropriate level design artifacts from System Engineering UML design artifacts. Include appropriate level of peer review.
⦁ Software Engineering: Code and Unit Test software modules that execute the software which meets all topical and derived requirements
⦁ System Test Engineering: Derive sell-off acceptance criteria. Include appropriate peer review (including System Engineering) and customer approval.
⦁ System Test Engineering: Derive System and Enterprise Level Test Cases. Include appropriate level of peer review.
⦁ System Test Engineering: Execute test cases as software modules become available
⦁ Quality Engineering: Provide quality checks during the processes described for System Engineering, Software Engineering, and System Test Engineering as appropriate
⦁ Include the following customer related reviews: Design Review (after System Engineering completes design artifacts), Pre-Ship Review (provided prior to Astin Martin Graphics acceptance of software), and Final Acceptance Test (software demonstration at customer facility showing software meets all requirements as installed)
Approved labor rates as follows:
⦁ System Engineer I: 43.15
⦁ System Engineer II: 48.37
⦁ System Engineer III: 51.17
⦁ Lead System Engineer: 58.91
⦁ Software Engineer I: 41.38
⦁ Software Engineer II: 47.62
⦁ Software Engineer III: 51.01
⦁ Lead Software Engineer: 59.83
⦁ System Test Engineer I: 40.78
⦁ System Test Engineer II: 43.79
⦁ System Test Engineer III: 49.25
⦁ Lead System Test Engineer: 51.25
⦁ Quality Engineer I: 40.38
⦁ Quality Engineer II: 47.55
⦁ Quality Engineer III: 51.01
⦁ Lead Quality Engineer: 59.83
⦁ Project Manager: 91.22 (LOE – Level of Effort)
⦁ Chief Engineer: 72.41 (LOE – Level of Effort)
Approved overhead rates as follows:
⦁ Finance: 7.6% of total hours
⦁ Planning & Scheduling: 6.2% of total hours
⦁ Management (Contracts/Senior Management): 2.1% of total hours
⦁ Facility: 1.3% of total hours
⦁ HR/Staffing: 0.54% of total hours
ACTIVITY / TASK LIST BY LOWEST WBS LEVEL LEG
2.1 Select Layout
System Engineering: Create outline of UML design.
Software Engineering: Assist system engineering.
Quality Engineering: Provide quality checks
2.2 Design Graphics
System Engineering: Design appropriate graphic widgets to display aeronautical expanse gauges within the technical specs guidelines for twenty-five different visual aspects. Include appropriate level of peer review.
Software Engineering: Assist system engineering.
Quality Engineering: Provide quality checks.
2.3 Approve design
System Engineering: Derive component level requirements for Software Engineering to design, code, and unit test and System Test can provide System and Enterprise level testing.
Software Engineering: Assist system engineering
System Test Engineering: Derive sell-off acceptance criteria. Include appropriate peer review (including System Engineering) and customer approval.
Quality Engineering: Provide quality checks.
3.1 Write content
System Engineering: Assist software engineering
Software Engineering: Code and Unit Test software modules that execute the software which meets all topical and derived requirements.
Quality Engineering: Provide quality checks.
3.2 Approve content
System Engineering: Assist software engineering
Software Engineering: Provide appropriate level design artifacts from System Engineering UML design artifacts. Include appropriate level of peer review.
System Test Engineering: Derive sell-off acceptance criteria. Include appropriate peer review (including System Engineering) and customer approval.
Quality Engineering: Provide quality checks.
3.3 Insert content in pages
System Engineering: Assist software engineering
Software Engineering: Check the function
Quality Engineering: Provide quality checks.
4.1 Set up web service on test
System Engineering: Corporate with other engineers for opinion
Software Engineering: Corporate with other engineers for opinion
System Test Engineering: Derive System and Enterprise Level Test Cases. Include appropriate level of peer review.
Quality Engineering: Provide quality checks.
4.2 Perform tests
System Engineering: Corporate with other engineers for opinion
Software Engineering: Corporate with other engineers for opinion
System Test Engineering: Execute test cases as software modules become available
Quality Engineering: Provide quality checks.
4.3 Approve web service
System Test Engineering: Assist Quality Engineering
Quality Engineering: Quality checks during the processes described for System Engineering, Software Engineering, and System Test Engineering as appropriate
Include the following customer related reviews: Design Review (after System Engineering completes design artifacts), Pre-Ship Review (provided prior to Astin Martin Graphics acceptance of software).
4.4 Set up web service on live environment
System Test Engineering: Assist Quality engineering
Quality Engineering: quality checks, and Final Acceptance Test (software demonstration at customer facility showing software meets all requirements as installed) installed)
NOTIONAL ACTIVITY DURATION SCHEDULE
Notional Activity estimated Duration
The estimated total elapsed time for how long an activity will take from starts to finish, including associated waiting time. Also referred to as activity resource estimated or estimated activity resources.
First Let me write the WORK BREAK DOWN STRUCTURE, where All WBS Code has Activity Description Below
WBS with WBS Code
As described in the Question Putting the Activity Description against Activity Code
Project Start Date – 15 May
Project Completion date- 15 November
Now let s make Responsibility Assignment Matrix/Structure where they will alloted with the activity as mentioned in case study with Labor Rate
The departments with the Overhead list with Cost consumption as in the Case study
Finance: 7.6% of total hours
⦁ Planning & Scheduling: 6.2% of total hours
⦁ Management (Contracts/Senior Management): 2.1% of total hours
⦁ Facility: 1.3% of total hours
⦁ HR/Staffing: 0.54% of total hours
Requirement List
Task |
Topical Requirements |
System Engineering: |
UML design appropriate graphic widgets to display aeronautical expanse gauges within the technical specs guidelines for twenty-five different visual aspects. Include appropriate level of peer review. Design should include graphical mock-up of gauges. |
System Engineering: |
Derive component level requirements for Software Engineering to design, code, and unit test and System Test can provide System and Enterprise level testing |
Software Engineering: |
Provide appropriate level design artifacts from System Engineering UML design artifacts. Include appropriate level of peer review. |
Software Engineering: |
Code and Unit Test software modules that execute the software which meets all topical and derived requirements |
System Test Engineering: |
Derive sell-off acceptance criteria. Include appropriate peer review (including System Engineering) and customer approval. |
System Test Engineering: |
Derive System and Enterprise Level Test Cases. Include appropriate level of peer review. |
System Test Engineering: |
Execute test cases as software modules become available |
Quality Engineering: |
Provide quality checks during the processes described for System Engineering, Software Engineering, and System Test Engineering as appropriate |
customer related reviews: |
Design Review (after System Engineering completes design artifacts), Pre-Ship Review (provided prior to Astin Martin Graphics acceptance of software), and Final Acceptance Test (software demonstration at customer facility showing software meets all requirements as installed) |
Assumption :
Following are the Assumption to be Included in the furnishing Project Charter
Systems Engineering to provide appropriate requirements decomposition
⦁ Software Engineering to provide design/development/unit test of software
⦁ System Test Engineering to provide component and enterprise level testing
⦁ Quality Engineering to provide quality control through the entire development life cycle
⦁ Management functions to include all primary functions (project management, finance, planning & scheduling, Overhead support (contracts, engineering matrix, etc.)
Astin Martin Graphics request of planned deliverables, acceptance criteria, quality plan, and work breakdown structure. These items need to be provided in an acceptable time for Astin Martin to review and approve.
Astin Martin Graphics further requests other deliverables to include final software (source and binary) which meets all approved acceptance criteria, associated design documents (system and development level)
All project questions or request for project scope changes should be directed to the Astin Martin Graphic designee (course instructor).
There is no requirement relative to project tools used to generate the required data.
Network Diagram:
The Network diagram can be furnished from the WBS Prepared but Activity Duration and no details of Activity Relation ship available in The Case Study