Question

In: Operations Management

Create a network diagram (graphical diagram) that shows thesequence and dependent relationships identified in the...

Create a network diagram (graphical diagram) that shows the sequence and dependent relationships identified in the Astin Martin project activity list and activity duration schedule.

Provide a project objective associated with the Astin Martin Graphics project. Include a list of assumptions about the project. What is a work breakdown structure? What is a responsibility matrix? Using the Astin Martin project activity list and activity duration schedule, create a WBS and RAM.

STATEMENT OF WORK SUMMARY  

RFP awarded for specific web services which will be incorporated into a web graphics company (Astin Martin Graphics LLC). Topical level requirements for the software were provided. Deliverable products include:

⦁   Systems Engineering to provide appropriate requirements decomposition

⦁   Software Engineering to provide design/development/unit test of software

⦁   System Test Engineering to provide component and enterprise level testing

⦁   Quality Engineering to provide quality control through the entire development life cycle

⦁   Management functions to include all primary functions (project management, finance, planning & scheduling, Overhead support (contracts, engineering matrix, etc.)

Award date of May 15 and required completion date (deliverables provided) of November 15.

Astin Martin Graphics request of planned deliverables, acceptance criteria, quality plan, and work breakdown structure. These items need to be provided in an acceptable time for Astin Martin to review and approve.

Astin Martin Graphics further requests other deliverables to include final software (source and binary) which meets all approved acceptance criteria, associated design documents (system and development level)

All project questions or request for project scope changes should be directed to the Astin Martin Graphic designee (course instructor).

There is no requirement relative to project tools used to generate the required data.

Topical requirements include:

⦁   System Engineering: UML design appropriate graphic widgets to display aeronautical expanse gauges within the technical specs guidelines for twenty-five different visual aspects. Include appropriate level of peer review. Design should include graphical mock-up of gauges.

⦁   System Engineering: Derive component level requirements for Software Engineering to design, code, and unit test and System Test can provide System and Enterprise level testing

⦁   Software Engineering: Provide appropriate level design artifacts from System Engineering UML design artifacts. Include appropriate level of peer review.

⦁   Software Engineering: Code and Unit Test software modules that execute the software which meets all topical and derived requirements

⦁   System Test Engineering: Derive sell-off acceptance criteria. Include appropriate peer review (including System Engineering) and customer approval.

⦁   System Test Engineering: Derive System and Enterprise Level Test Cases. Include appropriate level of peer review.

⦁   System Test Engineering: Execute test cases as software modules become available

⦁   Quality Engineering: Provide quality checks during the processes described for System Engineering, Software Engineering, and System Test Engineering as appropriate

⦁   Include the following customer related reviews: Design Review (after System Engineering completes design artifacts), Pre-Ship Review (provided prior to Astin Martin Graphics acceptance of software), and Final Acceptance Test (software demonstration at customer facility showing software meets all requirements as installed)

Approved labor rates as follows:

⦁   System Engineer I: 43.15

⦁   System Engineer II: 48.37

⦁   System Engineer III: 51.17

⦁   Lead System Engineer: 58.91

⦁   Software Engineer I: 41.38

⦁   Software Engineer II: 47.62

⦁   Software Engineer III: 51.01

⦁   Lead Software Engineer: 59.83

⦁   System Test Engineer I: 40.78

⦁   System Test Engineer II: 43.79

⦁   System Test Engineer III: 49.25

⦁   Lead System Test Engineer: 51.25

⦁   Quality Engineer I: 40.38

⦁   Quality Engineer II: 47.55

⦁   Quality Engineer III: 51.01

⦁   Lead Quality Engineer: 59.83

⦁   Project Manager: 91.22 (LOE – Level of Effort)

⦁   Chief Engineer: 72.41 (LOE – Level of Effort)

Approved overhead rates as follows:

⦁   Finance: 7.6% of total hours

⦁   Planning & Scheduling: 6.2% of total hours

⦁   Management (Contracts/Senior Management): 2.1% of total hours

⦁   Facility: 1.3% of total hours

⦁   HR/Staffing: 0.54% of total hours

ACTIVITY / TASK LIST BY LOWEST WBS LEVEL LEG  

2.1 Select Layout

System Engineering: Create outline of UML design.

Software Engineering: Assist system engineering.

Quality Engineering: Provide quality checks

2.2 Design Graphics

System Engineering: Design appropriate graphic widgets to display aeronautical expanse gauges within the technical specs guidelines for twenty-five different visual aspects. Include appropriate level of peer review.

Software Engineering: Assist system engineering.

Quality Engineering: Provide quality checks.

2.3 Approve design

System Engineering: Derive component level requirements for Software Engineering to design, code, and unit test and System Test can provide System and Enterprise level testing.

Software Engineering: Assist system engineering

System Test Engineering: Derive sell-off acceptance criteria. Include appropriate peer review (including System Engineering) and customer approval.

Quality Engineering: Provide quality checks.

3.1 Write content

System Engineering: Assist software engineering

Software Engineering: Code and Unit Test software modules that execute the software which meets all topical and derived requirements.

Quality Engineering: Provide quality checks.

3.2 Approve content

System Engineering: Assist software engineering

Software Engineering: Provide appropriate level design artifacts from System Engineering UML design artifacts. Include appropriate level of peer review.

System Test Engineering: Derive sell-off acceptance criteria. Include appropriate peer review (including System Engineering) and customer approval.

Quality Engineering: Provide quality checks.

3.3 Insert content in pages

System Engineering: Assist software engineering

Software Engineering: Check the function

Quality Engineering: Provide quality checks.

4.1 Set up web service on test

System Engineering: Corporate with other engineers for opinion

Software Engineering: Corporate with other engineers for opinion

System Test Engineering: Derive System and Enterprise Level Test Cases. Include appropriate level of peer review.

Quality Engineering: Provide quality checks.

4.2 Perform tests

System Engineering: Corporate with other engineers for opinion

Software Engineering: Corporate with other engineers for opinion

System Test Engineering: Execute test cases as software modules become available

Quality Engineering: Provide quality checks.

4.3 Approve web service

System Test Engineering: Assist Quality Engineering

Quality Engineering: Quality checks during the processes described for System Engineering, Software Engineering, and System Test Engineering as appropriate

Include the following customer related reviews: Design Review (after System Engineering completes design artifacts), Pre-Ship Review (provided prior to Astin Martin Graphics acceptance of software).

4.4 Set up web service on live environment

System Test Engineering: Assist Quality engineering

Quality Engineering: quality checks, and Final Acceptance Test (software demonstration at customer facility showing software meets all requirements as installed) installed)

NOTIONAL ACTIVITY DURATION SCHEDULE  

Notional Activity estimated Duration

The estimated total elapsed time for how long an activity will take from starts to finish, including associated waiting time. Also referred to as activity resource estimated or estimated activity resources.

Solutions

Expert Solution

First Let me write the WORK BREAK DOWN STRUCTURE, where All WBS Code has Activity Description Below

WBS with WBS Code

As described in the Question Putting the Activity Description against Activity Code

  1. Astin Martin project
  2. Design Works
    1. Select Layout
      1. System Engineering: Create outline of UML design.
      2. Software Engineering: Assist system engineering.
      3. Quality Engineering: Provide quality checks
    2. Design Graphics
      1. System Engineering: Design appropriate graphic widgets to display aeronautical expanse gauges within the technical specs guidelines for twenty-five different visual aspects. Include appropriate level of peer review.
      2. Software Engineering: Assist system engineering.
      3. Quality Engineering: Provide quality checks.
    3. Approve design
      1. System Engineering: Derive component level requirements for Software Engineering to design, code, and unit test and System Test can provide System and Enterprise level testing.
      2. Software Engineering: Assist system engineering
      3. System Test Engineering: Derive sell-off acceptance criteria. Include appropriate peer review (including System Engineering) and customer approval.
      4. Quality Engineering: Provide quality checks.
  3. Content Work
    1. Write content
      1. System Engineering: Assist software engineering
      2. Software Engineering: Code and Unit Test software modules that execute the software which meets all topical and derived requirements.
      3. Quality Engineering: Provide quality checks.
    2. Approve content
      1. System Engineering: Assist software engineering
      2. Software Engineering: Provide appropriate level design artifacts from System Engineering UML design artifacts. Include appropriate level of peer review.
      3. System Test Engineering: Derive sell-off acceptance criteria. Include appropriate peer review (including System Engineering) and customer approval.
      4. Quality Engineering: Provide quality checks.
    3. Insert content in pages
      1. System Engineering: Assist software engineering
      2. Software Engineering: Check the function
      3. Quality Engineering: Provide quality checks.
  4. Web Service Work
    1. Set up web service on test
      1. System Engineering: Corporate with other engineers for opinion
      2. Software Engineering: Corporate with other engineers for opinion
      3. System Test Engineering: Derive System and Enterprise Level Test Cases. Include appropriate level of peer review.
      4. Quality Engineering: Provide quality checks.
    2. Perform tests
      1. System Engineering: Corporate with other engineers for opinion
      2. Software Engineering: Corporate with other engineers for opinion
      3. System Test Engineering: Execute test cases as software modules become available
      4. Quality Engineering: Provide quality checks.
    3. Approve web service
      1. System Test Engineering: Assist Quality Engineering
      2. Quality Engineering: Quality checks during the processes described for System Engineering, Software Engineering, and System Test Engineering as appropriate
      3. Include the following customer related reviews: Design Review (after System Engineering completes design artifacts), Pre-Ship Review (provided prior to Astin Martin Graphics acceptance of software).
    4. Set up web service on live environment
      1. System Test Engineering: Assist Quality engineering
      2. Quality Engineering: quality checks, and Final Acceptance Test (software demonstration at customer facility showing software meets all requirements as installed) installed)

Project Start Date – 15 May

Project Completion date- 15 November

Now let s make Responsibility Assignment Matrix/Structure where they will alloted with the activity as mentioned in case study ​ with Labor Rate

The departments with the Overhead list with Cost consumption as in the Case study

Finance: 7.6% of total hours

⦁   Planning & Scheduling: 6.2% of total hours

⦁   Management (Contracts/Senior Management): 2.1% of total hours

⦁   Facility: 1.3% of total hours

⦁   HR/Staffing: 0.54% of total hours

Requirement List

Task

Topical Requirements

System Engineering:

UML design appropriate graphic widgets to display aeronautical expanse gauges within the technical specs guidelines for twenty-five different visual aspects. Include appropriate level of peer review. Design should include graphical mock-up of gauges.

System Engineering:

Derive component level requirements for Software Engineering to design, code, and unit test and System Test can provide System and Enterprise level testing

Software Engineering:

Provide appropriate level design artifacts from System Engineering UML design artifacts. Include appropriate level of peer review.

Software Engineering:

Code and Unit Test software modules that execute the software which meets all topical and derived requirements

System Test Engineering:

Derive sell-off acceptance criteria. Include appropriate peer review (including System Engineering) and customer approval.

System Test Engineering:

Derive System and Enterprise Level Test Cases. Include appropriate level of peer review.

System Test Engineering:

Execute test cases as software modules become available

Quality Engineering:

Provide quality checks during the processes described for System Engineering, Software Engineering, and System Test Engineering as appropriate

customer related reviews:

Design Review (after System Engineering completes design artifacts), Pre-Ship Review (provided prior to Astin Martin Graphics acceptance of software), and Final Acceptance Test (software demonstration at customer facility showing software meets all requirements as installed)

Assumption :

Following are the Assumption to be Included in the furnishing Project Charter

Systems Engineering to provide appropriate requirements decomposition

⦁   Software Engineering to provide design/development/unit test of software

⦁   System Test Engineering to provide component and enterprise level testing

⦁   Quality Engineering to provide quality control through the entire development life cycle

⦁   Management functions to include all primary functions (project management, finance, planning & scheduling, Overhead support (contracts, engineering matrix, etc.)

Astin Martin Graphics request of planned deliverables, acceptance criteria, quality plan, and work breakdown structure. These items need to be provided in an acceptable time for Astin Martin to review and approve.

Astin Martin Graphics further requests other deliverables to include final software (source and binary) which meets all approved acceptance criteria, associated design documents (system and development level)

All project questions or request for project scope changes should be directed to the Astin Martin Graphic designee (course instructor).

There is no requirement relative to project tools used to generate the required data.

Network Diagram:

The Network diagram can be furnished from the WBS Prepared but Activity Duration and no details of Activity Relation ship available in The Case Study


Related Solutions

Create a diagram of a Small/Medium size Business network Using Computer Network Defense and Defense in...
Create a diagram of a Small/Medium size Business network Using Computer Network Defense and Defense in Depth, Define what a secure network should look like on a modest budget. (Describe your diagram and why you placed your appliances where you chose to place them).
By using the WBS for contruscting a house, students will create a Network Diagram and Critical...
By using the WBS for contruscting a house, students will create a Network Diagram and Critical Path Analysis for the project. A network diagram is essentially a flow chart that includes all of the project elements and how they relate to one another. It depicts the sequence of activities in the project and also shows parallel activities and the links between each activity (PMBOK Guide). When outlined on a network diagram, the critical path is the longest path through the...
Create a table that shows the relationships between monomers, polymers, and types of bonds, for sugars,...
Create a table that shows the relationships between monomers, polymers, and types of bonds, for sugars, proteins, nucleic acids, and lipids. Write two well-composed, logical sentences for each of the four molecules above. Write one sentence for dehydration reactions, and one sentence for hydrolysis reactions.
Create Gantt Chart and network Diagram Task Precedes Optimistic MostLikely Pessimistic Norm$ CrashTime Crash$ A D...
Create Gantt Chart and network Diagram Task Precedes Optimistic MostLikely Pessimistic Norm$ CrashTime Crash$ A D 4 4 4 1000 3 1301 B E 2 3 28 1391 4 2000 C F 2 4 12 2000 4 2713 D G 2 3 22 1198 5 1400 E G 1 4 7 899 3 1100 F H 7 10 19 2500 6 3765 G H 1 3 11 792 3 1450 H none 2 2 8 300 1 504
Please design the network and draw the network diagram. You have the freedom to assume the...
Please design the network and draw the network diagram. You have the freedom to assume the internal network structure. In the diagram, in addition to the 2 servers, you should also include a few desktop computers and a printer. Please explain the rationale on why you put a computer or a printer in its designated location, 1 example for each location. A subnet (or a segment) is regarded as the same location. (hint: a firewall or a few firewalls, depending...
Briefly assess the relationships between Biological and Artificial Neural Network
Briefly assess the relationships between Biological and Artificial Neural Network
Hardware and Network Plan Create a network for a company that sells shoes. Describe the hardware...
Hardware and Network Plan Create a network for a company that sells shoes. Describe the hardware needed and the size of the network (PAN, LAN, WAN) and make a flow chart or mind map of the network. The description should be at least 500 words. The flow chart or mind map should have at least 12 boxes, each box should be labeled and the flow noted. The main thing I need help with is the flow chart or the mind...
Explain the shape of the network good demand curve and illustrate with a diagram
Explain the shape of the network good demand curve and illustrate with a diagram
You are studying a density-dependent elephant population that has the following relationships for the birth rate...
You are studying a density-dependent elephant population that has the following relationships for the birth rate (b) and the death rate (d), as functions of N. b=0.10+0.03N-0.0005N^2 d=0.20+0.01N Plot these functions on the same graph (on a separate page). Using Excel can help you with this: plug into the equation a range of numbers for N from 1 to 60 or so elephants. How many equilibrium points are shown by your graph? You do not have to calculate the values...
Consider the following proposed relationships between an independent and a dependent variable. In each case, would...
Consider the following proposed relationships between an independent and a dependent variable. In each case, would it be realistic for a researcher to perform an experiment to test the theory? If yes, briefly describe what would be randomly assigned in the experiment; if no, briefly explain why not. (a)​An individual’s level of religiosity (X) and his or her preferences for different political candidates (Y). (b)​Exposure to negative political news (X) and political apathy (Y).  (c)​Military service (X) and attitudes...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT