Question

In: Operations Management

Use the following activities and their three duration estimates (in days) to do the following Calculate...

Use the following activities and their three duration estimates (in days) to do the following

  1. Calculate the probability that the project will take at least 19 days - use 2 decimals when determining the duration
  1. determining the duration

Path

Activity

Optimistic

Most Likely

Pessimistic

a-b-c

A

4

5

6

B

7

8

10

C

3

5

9

d-e-f

D

7

8

11

E

2

3

4

f

1

4

6

Solutions

Expert Solution

Expected Duration of Activity = (Optimistic Time + 4*Most Likely Time + Pessimistic Time)/6

Expected Duration of Activity A = (4+4*5+6)/6 = 5 days

Expected Duration of Activity B = (7+4*8+10)/6 = 8.17 days

Expected Duration of Activity C = (3+4*5+9)/6 = 5.33 days

Expected Duration of Path A-B-C = 5+8.17+5.33 = 18.50 days

Expected Duration of Activity D = (7+4*8+11)/6 = 8.33 days

Expected Duration of Activity E = (2+4*3+4)/6 = 3 days

Expected Duration of Activity F = (1+4*4+6)/6 = 3.83 days

Expected Duration of Path D-E-F = 8.33+3+3.83 = 15.16 days

From above,

Critical Path = A-B-C

Variance = ((Pessimistic Time - Optimistic Time)/6)^2

Varince of A = ((6-4)/6)^2 = 0.11

Varince of B = ((10-7)/6)^2 = 0.25

Varince of C = ((9-3)/6)^2 = 1.00

Total Variance = 1.36

SD = Variance^(1/2)

SD = (1.36)^(1/2) = 1.166 = 1.17

Expected Duration = 18.50

Z = (X-Mean)/SD

Z = (19-18.50)/1.17

Z = 0.4274

Probability = NORM.S.DIST(0.4274,1)

Probability = 0.6655 = 66.55%


Related Solutions

Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A Clear Site and mobilize labour and equipment None 5 B Excavate foundation A 15 C Procure materials (sand, cement, chippings etc.) A 10 D Pour foundation concrete B, C 5 E Mould sandcrete blocks (substructure) C 5 F Construct substructure block work D, E 15 G Construct superstructure block work F, H 30 H Make doors and window frames I 10 I Procure and...
QUESTION 5 A project has the following activities: Activity Duration, days Predecessor activity A 8 None...
QUESTION 5 A project has the following activities: Activity Duration, days Predecessor activity A 8 None B 7 A C 4 None D 11 C E 7 B & D The project started on Day 1. Assume 7 working days a week. For example, activity A start on Day 1 and finish on the end of day 8. John is responsible for both activities B and D. However, he CAN'T work on both of them on the same period. By...
The formula is: Te = (o + 4m + p) / 6 Calculate duration estimates for...
The formula is: Te = (o + 4m + p) / 6 Calculate duration estimates for the following situation: The operations manager was in the process of upgrading the IT network and preparing estimates from the technology installers in regards to how long the existing network would be down during the upgrade. The technologists believed that it could be done within 8 days if everything went according to plan. There is the possibility it could take up to 16 days...
Forty-minute workouts of one of the following activities three days a week will lead to a...
Forty-minute workouts of one of the following activities three days a week will lead to a loss of weight. Suppose the following sample data show the number of calories burned during 40-minute workouts for three different activities. Swimming Tennis Cycling 413 420 390 385 490 245 430 450 295 400 415 397 422 525 273 Do these data indicate differences in the amount of calories burned for the three activities? Use a 0.05 level of significance. Find the value of...
Forty-minute workouts of one of the following activities three days a week will lead to a...
Forty-minute workouts of one of the following activities three days a week will lead to a loss of weight. Suppose the following sample data show the number of calories burned during 40-minute workouts for three different activities. Swimming Tennis Cycling 403 410 385 375 490 250 430 450 290 400 415 397 432 535 263 Do these data indicate differences in the amount of calories burned for the three activities? Use a 0.05 level of significance. Find the value of...
Forty-minute workouts of one of the following activities three days a week will lead to a...
Forty-minute workouts of one of the following activities three days a week will lead to a loss of weight. Suppose the following sample data show the number of calories burned during 40-minute workouts for three different activities. Swimming Tennis Cycling 403 415 390 385 485 255 420 450 295 395 425 402 422 530 268 Do these data indicate differences in the amount of calories burned for the three activities? Use a 0.05 level of significance. Find the value of...
Forty-minute workouts of one of the following activities three days a week will lead to a...
Forty-minute workouts of one of the following activities three days a week will lead to a loss of weight. The following sample data show the number of calories burned during -minute workouts for three different activities. Swimming Tennis Cycling 415 385 408 380 485 250 425 450 295 400 420 402 427 530 268 Use a .05 level of significance. Use Table 1 of Appendix B. a. What is the sum of the ranks for Swimming, Tennis and Cycling (to...
a) Calculate mean duration and standard deviation for all the activities using the beta distribution. [4pts]...
a) Calculate mean duration and standard deviation for all the activities using the beta distribution. [4pts]    b) Construct a network diagram for this problem using the mean durations calculated in part (a), calculate the LS(Foll.), ES(Prec.) and total float for all the activities, and hence identify the critical path . What is the mean completion time for the project? What is the standard deviation of the critical path? [30 pts ]    c) What is the 92% confidence interval...
Krusskal – Wallis Test Forty-minute workouts of one if the following activities three days a week...
Krusskal – Wallis Test Forty-minute workouts of one if the following activities three days a week will lead to a loss weight. The following sample data show the number of calories burned during 40-minute workouts for three different activities. Swimming Tennis Cycling 408 415 385 380 485 250 425 450 295 400 420 402 427 530 268 a. At the 0.05 level of significance, is there evidence of a significant difference in the median amount of calories burned among the...
Calculate the duration, given the following (use 2 decimals) Face value = $1,000 Coupon rate =...
Calculate the duration, given the following (use 2 decimals) Face value = $1,000 Coupon rate = 7.75% Yield = 8.25% Remaining years = 4 Redemption = 100 Frequency = 2
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT