Question

In: Operations Management

Case 9.4 The Ventron Engineering Company has just been awarded a $2 million development contract by...

Case 9.4

The Ventron Engineering Company has just been awarded a $2 million development contract by the U.S. Army Aviation Systems Command to develop a blade spar for its Heavy Lift Helicopter program. The blade spar is a metal tube that runs the length of and provides strength to the helicopter blade. Due to the unusual length and size of the Heavy Lift Helicopter blade, Ventron is unable to produce a single-piece blade spar of the required dimensions using existing extrusion equipment and material. The engineering department has prepared two alternatives for developing the blade spar:

  • (1)

    sectioning or

  • (2)

    an improved extrusion process.

Ventron must decide which process to use. (Backing out of the contract at any point is not an option.) The risk report has been prepared by the engineering department. The information from this report is explained next.

The sectioning option involves joining several shorter lengths of extruded metal into a blade spar of sufficient length. This work will require extensive testing and rework over a 12-month period at a total cost of $1.8 million. Although this process will definitely produce an adequate blade spar, it merely represents an extension of existing technology.

To improve the extrusion process, on the other hand, it will be necessary to perform two steps:

  • (1)

    improve the material used, at a cost of $300,000, and

  • (2)

    modify the extrusion press, at a cost of $960,000.

The first step will require six months of work, and if this first step is successful, the second step will require another six months of work. If both steps are successful, the blade spar will be available at that time, that is, a year from now. The engineers estimate that the probabilities of succeeding in steps 1 and 2 are 0.9 and 0.75, respectively. However, if either step is unsuccessful (which will be known only in six months for step 1 and in a year for step 2), Ventron will have no alternative but to switch to the sectioning process—and incur the sectioning cost on top of any costs already incurred.

Development of the blade spar must be completed within 18 months to avoid holding up the rest of the contract. If necessary, the sectioning work can be done on an accelerated basis in a six-month period, but the cost of sectioning will then increase from $1.8 million to $2.4 million. The director of engineering, Dr. Smith, wants to try developing the improved extrusion process. He reasons that this is not only cheaper (if successful) for the current project, but its expected side benefits for future projects could be sizable. Although these side benefits are difficult to gauge, Dr. Smith’s best guess is an additional $2 million. (These side benefits are obtained only if both steps of the modified extrusion process are completed successfully.)

  1. Develop a decision tree to maximize Ventron’s EMV. This includes the revenue from this project, the side benefits (if applicable) from an improved extrusion process, and relevant costs. You don’t need to worry about the time value of money; that is, no discounting or net present values are required. Summarize your findings in words in the spreadsheet.

Solutions

Expert Solution

The decision tree looks like this

Total Revenue = $ 2 Mn

  • Sectioning :
    • Cost = $ 1.8 Mn
    • Profit = $ 0.2 Mn
  • Improvement :
    • Step 1 cost = 0.3 Mn, P(Success) = 0.9
    • Step 2 cost = 0.96 Mn P(Success) = 0.75
      • Step 1 Failure --> Sectioning -1
        • Cost = $1.8 Mn + $0.3 Mn = $ 2.1 Mn
        • Revenue = $ 2 Mn
        • Profit = $(0.1) Mn
      • Step 1 Success
        • Step 2 Success
          • Cost = $0.3 Mn + $0.96 Mn
          • Revenue = $ 2 Mn
          • Side benefits = $ 2 Mn
          • Profit = $ 2.74 Mn
        • Step 2 Failure --> Accelerated Sectioning
          • Cost = $2.4 Mn + $0.3 Mn + $0.96 Mn
          • Revenue = $ 2 Mn
          • Profit = $(1.66) Mn
  1. EMV (Sectioning ) = P(Success) * Profit = 1 * $0.2 Mn = $ 0.2 Mn
  2. EMV ( Improvement) =    (P(Success) * Profit) = (0.9 *0.75 *2.74 )+ (0.1 * {-0.1}) +( 0.9 * 0.25 * {-1.66})

= $ 1.8495 Mn + ( - .01) + (-0.3735 Mn)

= $ 1.466 Mn

Thus, Ventron should go with the improvement plan as it has higher EMV of $1.466 Mn as against $200K for the standard sectioning process.

Thanks

Harshal


Related Solutions

Construction Engineering question: Produce a environmental management plan Company has been awarded the contract for a...
Construction Engineering question: Produce a environmental management plan Company has been awarded the contract for a bridge replacement, including 2km approach resurfacing on each side and has placed you and your team in charge. Produce a environmental management plan. Thanks!!
Mr. Phiri has been awarded a contract of supplying coarse aggregates to Junxi Engineering company who...
Mr. Phiri has been awarded a contract of supplying coarse aggregates to Junxi Engineering company who are working on Lusaka-Ndola dual carriage way. One of the condition for Mr. Phiri to supply the coarse aggregates is having his own quarry site and to employ a material’s Engineer for quality control purpose and technical advice. The material’s Engineer will give guidance on site selection for coarse aggregates which will be presented to the main contractor Junxi Engineering Company. You have been...
case study: A leading maintenance management company has been awarded the contract for sole long- term...
case study: A leading maintenance management company has been awarded the contract for sole long- term maintenance of an airport including its hangars, control tower, parking and hotel facilities. Being a maintenance manager working for the company, suggest the most suitable ideas for the following situations. questions: 1. List five resources in this project which can have an MTBF or MTTF associated with them. Explain one benefit for each resource. 2. Explain any six benefits this project will experience by...
The Scenario: A construction company has been awarded the contract to build a pipeline in Alaska....
The Scenario: A construction company has been awarded the contract to build a pipeline in Alaska. The project timeline is of the highest priority because work can only be completed during summer months due to adverse weather conditions. One of the suppliers of a key component has longer lead time than is required to complete the pipeline, but may be able to deliver if the construction company will pay fees to expedite. There are other suppliers, but these suppliers are...
A building company has been awarded the contract to undertake the construction works for a multi-storey...
A building company has been awarded the contract to undertake the construction works for a multi-storey office project in a city centre location. A deep basement is to be installed under one half of the building, within a layer of dense gravel. The site is surrounded by public roads and buildings on all sides and it is expected that the water table is extremely close to the ground surface on a year-round basis. You have been asked by the contractor...
Your company has been awarded a contract for 5-story addition on top of an existing 10-story...
Your company has been awarded a contract for 5-story addition on top of an existing 10-story hospital tower at a Cancer Center located in one of the most populated areas of Dallas, Texas. The existing hospital building is beyond 100% occupancy. The company was hired under a design-build contract to complete the $220 million project. Wind-load testing will be conducted. The wind-resisting system will be modified to redistribute loads on the mat foundation. High-strength concrete will be utilized for the...
CAT Construction has been awarded a contract with the City of Newberg to replace and repair...
CAT Construction has been awarded a contract with the City of Newberg to replace and repair all of the sidewalks in the older residential areas. Based on experience with previous​ projects, CAT feels the project completion time follows a normal distribution with a mean of 60 days and a standard deviation of 10 days. CAT anticipates the net profit for completing the project is​ $100,000. If the company completes the project is less than 40​ days, it will receive an...
Your company has just been awarded a project to renovate part of an existing occupied building....
Your company has just been awarded a project to renovate part of an existing occupied building. Your customer has stated that prior to starting work, all existing conditions are to be reviewed and a plan is to be developed off what you discover for how the work will be conducted so as to not interrupt/disrupt any of the existing occupants and their on-going activities. You decide to look to technology to help accomplish and expedite this task. Identify a technological...
Industrial Designs has been awarded a contract to design a label for a new wine produced...
Industrial Designs has been awarded a contract to design a label for a new wine produced by Lake View Winery. The company estimates that 150 hours will be required to complete the project. The firm’s three graphic designers available for assignment to this project are Lisa, a senior designer and team leader; David, a senior designer; and Sarah, a junior designer. Because Lisa has worked on several projects for Lake View Winery, management specified that Lisa must be assigned at...
Industrial design has been awarded a contract to design a label for a new wine produced...
Industrial design has been awarded a contract to design a label for a new wine produced by Lake View Winery.The company estimates that150 hours will be required to complete the project.The firm's three graphic designers available for to this project are Lisa,a senior designer and team leader; David , a senior designer; and Sarah, a junior designer. Because Lisa has worked on several projects for Lake View Winery, management has specified that Lisa must be assigned at least 40%of the...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT