Question

In: Operations Management

The following jobs are waiting to be processed at the same machine center. Jobs are logged...

The following jobs are waiting to be processed at the same machine center. Jobs are logged as they​ arrive:

Job   Date Received   Due Date   Duration (days)
A             275                    312                  16
B             275                    325                  40
C      275                     314                   5
D            275                     315                   3
E            275                      313                  8

All dates are specified as manufacturing planning calendar days. Assume that all jobs arrive on day 275. Assume each job starts at the beginning of the day and finishes at the end of the day​ (a job that begins on day 275 and takes 8 days will finish on day​ 282, and the next job begins in the morning of day​ 283). Compute all times based on initiating work on day 275.

​a) Using the FCFS​ (first come, first served​ ) decision rule for sequencing the​ jobs, the order is​ (assume that jobs came in the order in which they are listed in the​ table):

Sequence                    Job

1                    ?

2                    ?

3                    ?

4                    ?

5                    ?

the average tardiness for the sequence developed using the EDD rule= ?? days

The percentage utilization for the sequence developed using the EDD rule =??% round 2 dec

using the SPT decision rule for sequencing the jobs, the order is a,e,b,c,d

the average tardiness for the sequence developed using the SPT rule = ?? days

the percentage utilization for the sequence developed using the SPT rule = ??% round 2 dec.

using the LPT decision rule for sequencing the jobs, the order is d,c,b,e,a

the average tardiness for the sequence developed using the LPT rule = ?? days . round 2 dec.

the percentage utilization for the sequence developed using the LPT rule = ??% round 2 dec

Solutions

Expert Solution

(a)

As it is FCFS, the sequence will be A – B – C – D – E.

===============================================================

For EDD, the earliest due date job is taken first. So sequence will be A – E – C – D – B.

EDD

Job

Date received

Due date

Duration

Flow time

Duration of existing job + flow time of previous job

Date of completion

Date received + Duration – 1

Lateness Maximum of 0 and (Date of completion – Due date)

A

275

312

16

16

275 + 16 - 1 = 290

290 – 312 = -22 = 0

E

275

313

8

16 + 8 = 24

298

0

C

275

314

5

24 + 5 = 29

303

0

D

275

315

3

32

306

0

B

275

325

40

72

346

21

Total

72

173

1543

21

Average tardiness = Total tardiness/number of jobs = 21/5 = 4.20

% utilization = Total Duration/Total flow time = 72/173 * 100 = 41.618 = 41.62%

=============================================================

SPT stands for Shortest Processing time. The sequence will be D – C – E – A – B

SPT

Job

Date received

Due date

Duration

Flow time

Date of completion

Lateness

D

275

315

3

3

277

0

C

275

314

5

8

282

0

E

275

313

8

16

290

0

A

275

312

16

32

306

0

B

275

325

40

72

346

21

Total

72

131

1501

21

Average tardiness = 21/5 = 4.2

% utilization = 72/131 * 100 = 54.96%

===============================================================

LPT stands for longest processing time. Here, the sequence is done based on the longest to shortest duration of work. Sequence will be B -A – E – C – D

LPT

Job

Date received

Due date

Duration

Flow Time

Date of completion

Lateness

B

275

325

40

40

314

0

A

275

312

16

56

330

18

E

275

313

8

64

338

25

C

275

314

5

69

343

29

D

275

315

3

72

346

31

Total

72

301

1671

103

Average tardiness = 103/5 = 20.6

% utilization = 72/301 * 100 = 23.92%

Hope the answer will help. In the case of doubt, please comment. I have tried my best to explain.


Related Solutions

The following jobs are waiting to be processed at the same machine center. Jobs are logged...
The following jobs are waiting to be processed at the same machine center. Jobs are logged as they arrive: A 313 8 B 312 16 C 325 40 D 314 5 E 314 3 In what sequence would the jobs be ranked according to the following decision rules: (a) FCFS, (b) EDD, (c) SPT, and (d) LPT? Which decision is best and why? All dates are specified as manufacturing planning calendar days. Assume that all jobs arrive on day 275.
The following jobs are waiting to be processed at the same machine center. Jobs are logged...
The following jobs are waiting to be processed at the same machine center. Jobs are logged as they​ arrive:     Job Due Date Duration​ (days) A 315 3 B 313 8 C 312 16 D 325 40 E 314 5 All dates are specified as manufacturing planning calendar days. Assume that all jobs arrive on day 275. Assume each job starts at the beginning of the day and finishes at the end of the day​ (a job that begins on...
The following jobs are waiting to be processed at Rick Solano's machine center. Solano's machine center...
The following jobs are waiting to be processed at Rick Solano's machine center. Solano's machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled today, which is day 241(day 241 is a work day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241. Job Date Job Received Due Date Duration (days)...
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center...
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center has a relatively long backlog and sets a fresh schedule every 2? weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled? today, which is day 241 ?(day 241 is a work? day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241. (Job) (Date Job Received) (Due Date Duration...
The following jobs are waiting to be processed at Jeremy​ LaMontagne's machine center. Today is day...
The following jobs are waiting to be processed at Jeremy​ LaMontagne's machine center. Today is day 240. Job Date job received Due date Duration (days) 1 210 270 25 2 215 280 35 3 220 295 45 4 235 315 40 5 240 340 15 Calculate the Critical Ratios​ (CR): ​(Enter all responses rounded to two decimal​ places.) JOB     CR 1         ? 2         ? 3         ? 4         ? 5         ? Using the Critical Ratio (CR) scheduling rule for sequencing the...
The table below contains information about five jobs waiting to be processed at work center. Job...
The table below contains information about five jobs waiting to be processed at work center. Job Processing Time (Days.) Days Until Due a 14 15 b 10 20 c 18 18 d 2 16 e 4 21 a. The sequence that would result using the FCFS rule is: e-b-c-d-a c-a-b-e-d a-b-c-d-e d-e-b-a-c e-d-b-a-c       b. The sequence that would result using the SPT rule is: e-b-c-d-a c-a-b-e-d a-d-c-e-b d-e-b-a-c e-d-b-a-c        c. The average flow time (completion time) using the...
Evan Schwartz has six jobs waiting to be processed through his machine. Processing time (in days)...
Evan Schwartz has six jobs waiting to be processed through his machine. Processing time (in days) and due date information for each job are as follows: Job Processing Time Due Date A B C D E F 2 1 5 3 4 7 3 2 12 4 8 11 Sequence the jobs by FCFS, SPT, SLACK, and DDATE. Calculate the mean flow time and mean tardiness of the six jobs under each sequencing rule. Which rule would you recommend?
The following set of seven jobs is to be processed through two work centers at George?...
The following set of seven jobs is to be processed through two work centers at George? Heinrich's printing company. The sequence is first? printing, then binding. Processing time at each of the work centers is shown in the following? table: Job Printing (hours) Binding(hours) T 12 4 U 8 11 V 5 14 W 6 2 X 9 10 Y 3 1 Z 7 13 a-b) Using? Johnson's rule for? 2-machine scheduling, the sequence? is: Scheduled Order Job 1.____ 2....
Which of the following will increase the waiting time in a call center in which the...
Which of the following will increase the waiting time in a call center in which the incoming call gets assigned to the first available server? A. Add more servers B. Implement the shortest processing time first priority rule C. Decrease the variability in servers D. Increase the average service/processing time E. Decrease the interarrival time Both C and D Both D and E C, D, and E
Q4   (a)   A manufacturer has the following jobs waiting on a single work centre. The firm...
Q4   (a)   A manufacturer has the following jobs waiting on a single work centre. The firm has not decided which dispatching rule to apply in order to prioritize the jobs and fix them into the schedule. Processing time and due date for each job are in the Table 4 below. Recommend the best job sequence to the manufacturer using THREE (3) dispatching rules scenario analysis. Table 4: Jobs Information Jobs Information Processing Time (days) Due Date (days) Job 1 3.25...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT