Question

In: Statistics and Probability

Evan Schwartz has six jobs waiting to be processed through his machine. Processing time (in days)...

Evan Schwartz has six jobs waiting to be processed through his machine. Processing time (in days) and due date information for each job are as follows:

Job

Processing Time

Due Date

A

B

C

D

E

F

2

1

5

3

4

7

3

2

12

4

8

11

Sequence the jobs by FCFS, SPT, SLACK, and DDATE. Calculate the mean flow time and mean tardiness of the six jobs under each sequencing rule. Which rule would you recommend?

Solutions

Expert Solution

ANSWER

FCFS: Process the jobs in order of their arrival, A, B, C, D, E.

Job

Processing time

Flow time

Due date

Tardiness

a

2

2

3

0

b

1

3

2

1

c

4

7

12

0

d

3

10

4

6

e

4

14

8

6

f

5

19

11

8

55

21

Mean flow time = total flow time/ no. of jobs

                                   = 55/6 = 9.17

Mean Tardiness = total tardiness/ no. of jobs

                                = 21/6 = 3.50

SPT: Sequence the jobs by smallest processing time.

Job

Processing time

Flow time

Due date

Tardiness

b

1

1

2

0

a

2

3

3

0

d

3

6

4

2

c

4

10

12

0

e

4

14

8

6

f

5

19

11

8

53

16

Mean flow time = 53/6 = 8.83

Mean Tardiness = 16/6 = 2.67

SLACK: Sequence the jobs by minimum slack. The slack for each job is calculated as: (due date - today's date) - remaining processing time.

Job

Processing time

Due date

Slack

a

2

3

0

b

1

2

0

c

4

12

7

d

3

4

0

e

4

8

3

f

5

11

5

Job

Processing time

Flow time

Due date

Tardiness

a

2

2

3

0

b

1

3

2

1

d

3

6

4

2

e

4

10

8

2

f

5

15

11

4

c

4

19

12

7

55

16

Mean flow time = 55/6 = 9.17

Mean Tardiness = 16/6 = 2.67

DDATE: Sequence the jobs by earliest due date

Job

Processing time

Flow time

Due date

Tardiness

b

1

1

2

0

a

2

3

3

0

d

3

6

4

2

e

4

10

8

2

f

5

15

11

4

c

4

19

12

7

54

15

Mean flow time = 54/6 = 9

Mean Tardiness = 15/6 = 2.50

Process DDate method is recommended as it has the lowest Mean tardiness.

------------------------------------------------------------------------

DEAR STUDENT,..IF YOU HAVE ANY QUERY ASK ME IN THE COMMENT BOX,I AM HERE TO HELPS YOU.PLEASE GIVE ME POSITIVE RATINGS

*****************THANK YOU*****************


Related Solutions

Five jobs are waiting for processing through two work centers. Their processing time? (in minutes) at...
Five jobs are waiting for processing through two work centers. Their processing time? (in minutes) at each work center is contained in the table below. Each job requires work center Alpha before work center Beta. According to? Johnson's rule, which job should be scheduled first in the? sequence? job Alpha beta r 20 10 s 25 35 t 50 20 u 15 35 v 55 75
The following jobs are waiting to be processed at Rick Solano's machine center. Solano's machine center...
The following jobs are waiting to be processed at Rick Solano's machine center. Solano's machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled today, which is day 241(day 241 is a work day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241. Job Date Job Received Due Date Duration (days)...
Six jobs are to be processed through a two-step operation. The first operation involves sanding, and...
Six jobs are to be processed through a two-step operation. The first operation involves sanding, and the second involves painting. Processing times are as following table. Job Operation 1 (Hours) Operation 2 (Hours) A 10 5 B 7 4 C 5 7 D 3 8 E 2 6 F 4 3 Determine the sequence that will minimize the total completion time for the jobs using Johnson’s rule. Illustrate graphically the throughput time and idle time at the two operations by...
Six jobs are to be processed through a? two-step operation. The first operation involves? sanding, and...
Six jobs are to be processed through a? two-step operation. The first operation involves? sanding, and the second involves painting. Processing times are as? follows: Job Operation 1 (hours) Operation 2 (hours) A 4 8 B 10 5 C 3 11 D 14 14 E 6 1 F 7 12 A) Using? Johnson's rule for? 2-machine scheduling, the sequence? is: b) For the schedule developed using? Johnson's rule, the total length of time taken to complete the six jobs? (including...
The following set of seven jobs is to be processed through two work centers at George?...
The following set of seven jobs is to be processed through two work centers at George? Heinrich's printing company. The sequence is first? printing, then binding. Processing time at each of the work centers is shown in the following? table: Job Printing (hours) Binding(hours) T 12 4 U 8 11 V 5 14 W 6 2 X 9 10 Y 3 1 Z 7 13 a-b) Using? Johnson's rule for? 2-machine scheduling, the sequence? is: Scheduled Order Job 1.____ 2....
Assume that you have a set of jobs where each has only a processing time that...
Assume that you have a set of jobs where each has only a processing time that you need to schedule on a single machine. Explain how you should schedule the jobs to minimize the sum of completion (finish) times. Write a proof that your schedule is optimal.
A batch production operation has a machine setup time of 4.0 hr and a processing time...
A batch production operation has a machine setup time of 4.0 hr and a processing time of 1.50 min per cycle. Three parts are produced each cycle. No tool handling time is included in the cycle. Part handling time each cycle is 30 sec. It consists of the worker obtaining three starting work units from a parts tray, loading them into the machine, and then after processing, unloading the completed units and placing them into the same tray. Each tray...
A company is currently waiting for 4 days to collect money. Through a lock box arrangement,...
A company is currently waiting for 4 days to collect money. Through a lock box arrangement, the funds could be collected the next day (1 day float). The company is considering using 4 lock boxes strategically located in areas where it has clusters of customers. The company expects to have 5,000 checks processed per day, per lockbox, and the average amount of each check is $520. The lockbox arrangement has a fee of $0.463 per check. There is additional charge...
The mean waiting time at the drive-through of a fast-food restaurant from the time an order...
The mean waiting time at the drive-through of a fast-food restaurant from the time an order is placed to the time the order is received is 84.3 seconds. A manager devises a new drive-through system that he believes will decrease wait time. He initiates the new system at his restaurant and measures the wait time for eleven randomly selected orders. The wait times are provided in the table below. Based on the given data, is the new system effective? Use...
The mean waiting time at the drive-through of a fast-food restaurant from the time an order...
The mean waiting time at the drive-through of a fast-food restaurant from the time an order is placed to the time the order is received is 84.3 seconds. A manager devises a new drive-through system that he believes will decrease wait time. He initiates the new system at his restaurant and measures the wait time for ten randomly selected orders. The wait times are provided in the table below. Based on the given data, is the new system effective? Use...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT