Question

In: Operations Management

The following set of seven jobs is to be processed through two work centers at George?...

The following set of seven jobs is to be processed through two work centers at George? Heinrich's printing company. The sequence is first? printing, then binding. Processing time at each of the work centers is shown in the following? table:

Job Printing (hours) Binding(hours)
T 12 4
U 8 11
V 5 14
W 6 2
X 9 10
Y 3 1
Z 7 13

a-b) Using? Johnson's rule for? 2-machine scheduling, the sequence? is:

Scheduled Order

Job

1.____

2. ____

3. ____

4.____

5.____

6.____

7.____



?c) For the schedule developed using? Johnson's rule, the total length of time taken to complete the seven printing and binding jobs? (including binding)? = ______ hours ?(enter your response as a whole? number).

?d) The idle time in the binding shop based on the sequence developed using ?Johnson's rule = ______ hours (enter your response as a whole? number).

?

e) By splitting Job V in? half, the binding? machine's idle time would be cut by ______ hour(s)?
??(enter your response rounded to one decimal? place).

Solutions

Expert Solution

As per Johnson’s Rule of sequencing; if there are two step operations for any job then select the one with the shortest processing time from both operations. If the shortest time is from the first operation then this job will schedule first and if it is from second operation then it will schedule last. This process we have to repeat again and again till any job left at any operation center.

Therefore apply this rule on the above operations

Job

Printing (Hours) (operation 1)

Binding (Hours)

(operation 2)

T

12

4

U

8

11

V

5

14

W

6

2

X

9

10

Y

3

1

Z

7

13

Shortest processing time

Shortest processing time (time)

Job

Operation (1 Or 2)

Sequence

1

Y

Operation 2

Last

2

W

Operation 2

       Second from last

4

T

Operation 2

         Third from Last

5

V

Operation 1

First

7

Z

Operation 1

Second

8

U

Operation 1

Third

9

X

Operation 1

Fourth

Therefore the sequence is V-Z-U-X-T-W-Y

a-b.

Scheduled order

Job

1

V

2

Z

3

U

4

X

5

T

6

W

7

Y

c. Total length calculation:

Scheduled order

Job

Cumulative time Required at Printing (hours)

Cumulative time Required at Binding (hours)

1

V

5

5+14=19

2

Z

5+7=12

19+13=32

3

U

12+8=20

32+11=43

4

X

20+9=29

43+10=53

5

T

29+12=41

53+4=57

6

W

41+6=47

57+2=59

7

Y

47+3=50

59+1=60

Therefore total length of time taken to complete the seven printing and binding jobs is 60 hours. (The longest time at binding)

d. The idle time at binding shop = total length of time taken to complete the seven printing and binding – total time required to do only binding job

= 60 hours – (4+11+14+2+10+1+13) hours = 60 hours – 55 hours = 5 hours

Therefore the idle time at binding shop is 5 hours.

e. The idle time for binding machine is 5 hours which is basically the processing time of printing job at first job V; by splitting Job V in half, it will take only 2.5 hours

Therefore the idle time at binding shop will be 2.5 hours.


Related Solutions

Five jobs are waiting for processing through two work centers. Their processing time? (in minutes) at...
Five jobs are waiting for processing through two work centers. Their processing time? (in minutes) at each work center is contained in the table below. Each job requires work center Alpha before work center Beta. According to? Johnson's rule, which job should be scheduled first in the? sequence? job Alpha beta r 20 10 s 25 35 t 50 20 u 15 35 v 55 75
Six jobs are to be processed through a two-step operation. The first operation involves sanding, and...
Six jobs are to be processed through a two-step operation. The first operation involves sanding, and the second involves painting. Processing times are as following table. Job Operation 1 (Hours) Operation 2 (Hours) A 10 5 B 7 4 C 5 7 D 3 8 E 2 6 F 4 3 Determine the sequence that will minimize the total completion time for the jobs using Johnson’s rule. Illustrate graphically the throughput time and idle time at the two operations by...
Six jobs are to be processed through a? two-step operation. The first operation involves? sanding, and...
Six jobs are to be processed through a? two-step operation. The first operation involves? sanding, and the second involves painting. Processing times are as? follows: Job Operation 1 (hours) Operation 2 (hours) A 4 8 B 10 5 C 3 11 D 14 14 E 6 1 F 7 12 A) Using? Johnson's rule for? 2-machine scheduling, the sequence? is: b) For the schedule developed using? Johnson's rule, the total length of time taken to complete the six jobs? (including...
6.9. An order for 250 bell ringers is processed on work centers 10 and 20. The...
6.9. An order for 250 bell ringers is processed on work centers 10 and 20. The setup and run times are as follows. It is decided to overlap the lot on the two work centers and to split the lot into two lots of 100 and 150. Move time between operations is 30 minutes. Work center 20 cannot be set up until the first lot arrives. Calculate the saving in manufacturing lead time. Setup on A = 50 minutes Run...
The following jobs are waiting to be processed at the same machine center. Jobs are logged...
The following jobs are waiting to be processed at the same machine center. Jobs are logged as they arrive: A 313 8 B 312 16 C 325 40 D 314 5 E 314 3 In what sequence would the jobs be ranked according to the following decision rules: (a) FCFS, (b) EDD, (c) SPT, and (d) LPT? Which decision is best and why? All dates are specified as manufacturing planning calendar days. Assume that all jobs arrive on day 275.
Evan Schwartz has six jobs waiting to be processed through his machine. Processing time (in days)...
Evan Schwartz has six jobs waiting to be processed through his machine. Processing time (in days) and due date information for each job are as follows: Job Processing Time Due Date A B C D E F 2 1 5 3 4 7 3 2 12 4 8 11 Sequence the jobs by FCFS, SPT, SLACK, and DDATE. Calculate the mean flow time and mean tardiness of the six jobs under each sequencing rule. Which rule would you recommend?
Through a published schedule and set of guidelines, the Centers for Disease Control and Prevention (CDC)...
Through a published schedule and set of guidelines, the Centers for Disease Control and Prevention (CDC) and public health officials recommend that every child receive certain vaccinations by age 6. What are the benefits of this recommendation to public health officials, to the community and to other children? Some parents and health care professionals question the CDC’s recommendations and decide not to vaccinate their children, while others, like Jennifer Margulis, choose to vaccinate their children along an alternative schedule. How...
The following jobs are waiting to be processed at Rick Solano's machine center. Solano's machine center...
The following jobs are waiting to be processed at Rick Solano's machine center. Solano's machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled today, which is day 241(day 241 is a work day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241. Job Date Job Received Due Date Duration (days)...
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center...
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center has a relatively long backlog and sets a fresh schedule every 2? weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled? today, which is day 241 ?(day 241 is a work? day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241. (Job) (Date Job Received) (Due Date Duration...
Please explain and work through the following genetics problem: An organization of the data set given...
Please explain and work through the following genetics problem: An organization of the data set given below in a table. The determination of recombinant classes. The determination of the double recombinant class. All calculations and determinations of individual map distances. A final map with the correct placement of genes relative to one another and their map distances. Calculations of the coefficient of coincidence (with actual and expected DCOs) and calculation of interference. Analyze this data set: +++ - 1340 abc...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT