Question

In: Operations Management

The table below contains information about five jobs waiting to be processed at work center. Job...

The table below contains information about five jobs waiting to be processed at work center.

Job

Processing

Time (Days.)

Days Until

Due

a

14

15

b

10

20

c

18

18

d

2

16

e

4

21

a. The sequence that would result using the FCFS rule is:

  1. e-b-c-d-a
  2. c-a-b-e-d
  3. a-b-c-d-e
  4. d-e-b-a-c
  5. e-d-b-a-c

     

b. The sequence that would result using the SPT rule is:

  1. e-b-c-d-a
  2. c-a-b-e-d
  3. a-d-c-e-b
  4. d-e-b-a-c
  5. e-d-b-a-c

      

c. The average flow time (completion time) using the SPT rule is

A. 9.6

B. 14

C.16.6

D.18

E. None of the above

d. The average days late using the SPT rule is

A. 9.6

B. 18

C.16.6

D.31.6

E. None of the above

e. The average flow time using the EDD rule is

A. 9.6

B. 18

C.16.6

D.31.2

E. None of the above

f. The average days late using the EDD rule is

A. 9.6

B. 18

C.16.6

D.31.6

E. 13.4

Solutions

Expert Solution

1. C. A-B-C-D-E

2. D. D-E-B-A-C

3. E. NONE OF THE ABOVE(ANSWER IS 20.4)

4. E. NONE OF THE ABOVE(ANSWER IS 9)

5. D. 31.2

6. E. 13.4



FCFS

JOB

PROCESSING TIME

DUE TIME

FLOW TIME

JOB LATENESS

A

14

15

0 + 14 = 14

B

10

20

14 + 10 = 24

4

C

18

18

24 + 18 = 42

24

D

2

16

42 + 2 = 44

28

E

4

21

44 + 4 = 48

27

TOTAL FLOW TIME = 14 + 24 + 42 + 44 + 48 = 172

AVERAGE COMPLETION TIME = FLOW TIME / N = 172 / 5 = 34.4

AVERAGE JOB LATENESS = TOTAL JOB LATENESS / N = 83 / 5 = 16.6



SPT


JOB

PROCESSING TIME

DUE TIME

FLOW TIME

JOB LATENESS

D

2

16

0 + 2 = 2

E

4

21

2 + 4 = 6

B

10

20

6 + 10 = 16

A

14

15

16 + 14 = 30

15

C

18

18

30 + 18 = 48

30

TOTAL FLOW TIME = 2 + 6 + 16 + 30 + 48 = 102

AVERAGE COMPLETION TIME = FLOW TIME / N = 102 / 5 = 20.4

AVERAGE JOB LATENESS = TOTAL JOB LATENESS / N = 45 / 5 = 9


EDD


JOB

PROCESSING TIME

DUE TIME

FLOW TIME

JOB LATENESS

A

14

15

0 + 14 = 14

D

2

16

14 + 2 = 16

0

C

18

18

16 + 18 = 34

16

B

10

20

34 + 10 = 44

24

E

4

21

44 + 4 = 48

27

TOTAL FLOW TIME = 14 + 16 + 34 + 44 + 48 = 156

AVERAGE COMPLETION TIME = FLOW TIME / N = 156 / 5 = 31.2

AVERAGE JOB LATENESS = TOTAL JOB LATENESS / N = 67 / 5 = 13.4

A Thumbs Up! would be really helpful for me. If you have any questions, please leave a comment and I will get back to you as soon as possible.


Related Solutions

The following jobs are waiting to be processed at the same machine center. Jobs are logged...
The following jobs are waiting to be processed at the same machine center. Jobs are logged as they arrive: A 313 8 B 312 16 C 325 40 D 314 5 E 314 3 In what sequence would the jobs be ranked according to the following decision rules: (a) FCFS, (b) EDD, (c) SPT, and (d) LPT? Which decision is best and why? All dates are specified as manufacturing planning calendar days. Assume that all jobs arrive on day 275.
The following jobs are waiting to be processed at the same machine center. Jobs are logged...
The following jobs are waiting to be processed at the same machine center. Jobs are logged as they​ arrive: Job   Date Received   Due Date   Duration (days) A             275                    312                  16 B             275                    325                  40 C      275                     314                   5 D            275                     315                   3 E            275                      313                  8 All dates are specified as manufacturing planning calendar days. Assume that all jobs arrive on day 275. Assume each...
The following jobs are waiting to be processed at the same machine center. Jobs are logged...
The following jobs are waiting to be processed at the same machine center. Jobs are logged as they​ arrive:     Job Due Date Duration​ (days) A 315 3 B 313 8 C 312 16 D 325 40 E 314 5 All dates are specified as manufacturing planning calendar days. Assume that all jobs arrive on day 275. Assume each job starts at the beginning of the day and finishes at the end of the day​ (a job that begins on...
The following jobs are waiting to be processed at Rick Solano's machine center. Solano's machine center...
The following jobs are waiting to be processed at Rick Solano's machine center. Solano's machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled today, which is day 241(day 241 is a work day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241. Job Date Job Received Due Date Duration (days)...
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center...
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center has a relatively long backlog and sets a fresh schedule every 2? weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled? today, which is day 241 ?(day 241 is a work? day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241. (Job) (Date Job Received) (Due Date Duration...
The following jobs are waiting to be processed at Jeremy​ LaMontagne's machine center. Today is day...
The following jobs are waiting to be processed at Jeremy​ LaMontagne's machine center. Today is day 240. Job Date job received Due date Duration (days) 1 210 270 25 2 215 280 35 3 220 295 45 4 235 315 40 5 240 340 15 Calculate the Critical Ratios​ (CR): ​(Enter all responses rounded to two decimal​ places.) JOB     CR 1         ? 2         ? 3         ? 4         ? 5         ? Using the Critical Ratio (CR) scheduling rule for sequencing the...
Five jobs are waiting for processing through two work centers. Their processing time? (in minutes) at...
Five jobs are waiting for processing through two work centers. Their processing time? (in minutes) at each work center is contained in the table below. Each job requires work center Alpha before work center Beta. According to? Johnson's rule, which job should be scheduled first in the? sequence? job Alpha beta r 20 10 s 25 35 t 50 20 u 15 35 v 55 75
The table below contains information about the production, costs and profits of a firm. The price...
The table below contains information about the production, costs and profits of a firm. The price faced by the firm is $40 per unit. There are 50 empty cells in the table. (a) Fill in all the empty cells. Output Total Fixed Costs Total Variable Costs Marginal Costs Average Variable Costs Average Fixed Costs Average Total Costs Price per unit Profits 0 12 1 12 50 50.0 50.0 -22.0 2 12 75 25.0 37.5 43.5 3 10.0 28.3 4 20.0...
Evan Schwartz has six jobs waiting to be processed through his machine. Processing time (in days)...
Evan Schwartz has six jobs waiting to be processed through his machine. Processing time (in days) and due date information for each job are as follows: Job Processing Time Due Date A B C D E F 2 1 5 3 4 7 3 2 12 4 8 11 Sequence the jobs by FCFS, SPT, SLACK, and DDATE. Calculate the mean flow time and mean tardiness of the six jobs under each sequencing rule. Which rule would you recommend?
Given the following information concerning jobs awaiting processing at a single work center, what is the...
Given the following information concerning jobs awaiting processing at a single work center, what is the processing sequence using the critical ratio (CR) rule? JOB Processing time at this operation (hrs) at this operation (hrs.) Processing time remaining at other operations (hrs.) Final due date ( hrs.) D 4 4 9 A 8 6 38 O 6 10 24 I 3 8 20 N 5 14 32