In: Operations Management
A |
313 |
8 |
B |
312 |
16 |
C |
325 |
40 |
D |
314 |
5 |
E |
314 |
3 |
In what sequence would the jobs be ranked according to the following decision rules: (a) FCFS, (b) EDD, (c) SPT, and (d) LPT? Which decision is best and why?
All dates are specified as manufacturing planning calendar days. Assume that all jobs arrive on day 275.