Question

In: Operations Management

Q4   (a)   A manufacturer has the following jobs waiting on a single work centre. The firm...

Q4   (a)   A manufacturer has the following jobs waiting on a single work centre. The firm has not decided which dispatching rule to apply in order to prioritize the jobs and fix them into the schedule. Processing time and due date for each job are in the Table 4 below. Recommend the best job sequence to the manufacturer using THREE (3) dispatching rules scenario analysis.

Table 4: Jobs Information

Jobs Information

Processing Time (days)

Due Date (days)

Job 1

3.25

8

Job 2

4.75

7

Job 3

4.5

9

Job 4

5

8

Job 5

4.5

7

Job 6

3.75

10

Job 7

4.25

9

Job 8

4

7

  1. Nuqman established TT Flash Sdn Bhd, to manufacture Automatic Hand-Cleaner Dispenser Station to help curb the spread of Covid-19 in the country. The company received 5 orders with different design specification (Design F, G, H, I & J) that must be completed not more than 29 days. With the TT Flash Sdn Bhd manufacturing capability, the company estimated 40 days to deliver all the stations. To overcome this issue, Nuqman have call others company to build the Automatic Hand-Cleaner Dispenser Station and ask each company their estimation time to manufacture each design. The estimated time information of each design shown in Table 5.
  1. Suggest to the company with justification the best alternative available for this order.

Table 5: Hand-Cleaner Dispenser Station Manufacturing Time Information

Design (days)

Company

F

G

H

I

J

TT Flash

9

5

12

6

8

P00

7

4

7

7

10

Q12

8

7

5

6

11

R34

6

7

11

10

9

S56

8

6

10

5

7

  1. Ranjit, the industrial engineer in the company have recommend to Nuqman for implementing concurrent process for this orders with establishing two workstation to manufacture the Automatic Hand-Cleaner Dispenser Station, namely fabrication and assembly as shown in Table 6.

Evaluate the above proposal by Ranjit whether the company able to meet the order demand not more than 29 days.

Table 6: Station Processing Time Information for each workstation

Design

Fabrication (days)

Assembly (days)

F

5

4

G

2

3

H

6

6

I

4

2

J

5

3

Solutions

Expert Solution

Scheduling as per three dispatching rules is following:

Of the three rules, SPT gives the best results (lowest values) in terms of average flow time, average tardiness and average number of jobs in system

Therefore, jobs should be scheduled as per SPT rule as shown below:

Sequence Job
1 Job 1
2 Job 6
3 Job 8
4 Job 7
5 Job 3
6 Job 5
7 Job 2
8 Job 4

Related Solutions

The following jobs are waiting to be processed at the same machine center. Jobs are logged...
The following jobs are waiting to be processed at the same machine center. Jobs are logged as they arrive: A 313 8 B 312 16 C 325 40 D 314 5 E 314 3 In what sequence would the jobs be ranked according to the following decision rules: (a) FCFS, (b) EDD, (c) SPT, and (d) LPT? Which decision is best and why? All dates are specified as manufacturing planning calendar days. Assume that all jobs arrive on day 275.
The 4M company has a work center with a single turret lathe. Jobs arrive at this...
The 4M company has a work center with a single turret lathe. Jobs arrive at this work center according to a Poisson process at a mean rate of 2 jobs per day, The lathe processing time has an exponential distribution with a mean of 0.25 day per job. a) On average, how many jobs are waiting.in the work center? b) On average, how long will a job stay in the center? c).Since each job takes a big space, the waiting...
Five jobs are waiting for processing through two work centers. Their processing time? (in minutes) at...
Five jobs are waiting for processing through two work centers. Their processing time? (in minutes) at each work center is contained in the table below. Each job requires work center Alpha before work center Beta. According to? Johnson's rule, which job should be scheduled first in the? sequence? job Alpha beta r 20 10 s 25 35 t 50 20 u 15 35 v 55 75
Given the following information concerning jobs awaiting processing at a single work center, what is the...
Given the following information concerning jobs awaiting processing at a single work center, what is the processing sequence using the critical ratio (CR) rule? JOB Processing time at this operation (hrs) at this operation (hrs.) Processing time remaining at other operations (hrs.) Final due date ( hrs.) D 4 4 9 A 8 6 38 O 6 10 24 I 3 8 20 N 5 14 32
Duke Company is a furniture manufacturer. At the end of November two jobs are in work-in-process....
Duke Company is a furniture manufacturer. At the end of November two jobs are in work-in-process. The following table provides the information about Jobs 401 and 402. Job 401 Job 402 Direct labor $20,000 $25,000 Direct materials $ 35,000 $ 20,000 Direct labor hours 2,000 2,500 Machine hours 1,500 3,000 The predetermined overhead rate for Duke is based on budgeted direct labor hours, 100,000, and the budgeted overhead cost, $750,000. The actual data for November are: Direct Labor Hours 15,000...
The following jobs are waiting to be processed at Rick Solano's machine center. Solano's machine center...
The following jobs are waiting to be processed at Rick Solano's machine center. Solano's machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled today, which is day 241(day 241 is a work day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241. Job Date Job Received Due Date Duration (days)...
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center...
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center has a relatively long backlog and sets a fresh schedule every 2? weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled? today, which is day 241 ?(day 241 is a work? day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241. (Job) (Date Job Received) (Due Date Duration...
Evan Schwartz has six jobs waiting to be processed through his machine. Processing time (in days)...
Evan Schwartz has six jobs waiting to be processed through his machine. Processing time (in days) and due date information for each job are as follows: Job Processing Time Due Date A B C D E F 2 1 5 3 4 7 3 2 12 4 8 11 Sequence the jobs by FCFS, SPT, SLACK, and DDATE. Calculate the mean flow time and mean tardiness of the six jobs under each sequencing rule. Which rule would you recommend?
WAITING LINES The Peachtree Airport in Atlanta serves light aircraft. It has a single runway and...
WAITING LINES The Peachtree Airport in Atlanta serves light aircraft. It has a single runway and one air traffic controller to land planes. It takes an airplane 10 minutes to land and clear the runway, but planes arrive at the rate of 4 per hour. Set up the waiting lines problem and be prepared to answer questions from the output WAITINGLINES(Airport) __________8a. What is the average number of planes that will stack up waiting to land? __________8b. What is the...
Consider the following set of jobs to be scheduled for execution on a single CPU system....
Consider the following set of jobs to be scheduled for execution on a single CPU system. Job Arrival Time Burst (msec) Priority A 0 6 3 (Silver) B 1 2 1 (Diamond) C 3 5 3 (Silver) D 5 3 4 (Bronze) E 7 2 2 (Gold)    (a)     Draw a Gantt chart showing First-Come-First-Served (FCFS) scheduling for these jobs. (b)     Draw a Gantt chart showing preemptive PRIORITY scheduling. (c)    Draw a Gantt chart showing Highest Response Ratio Next (HRRN) scheduling. (d)     Draw a...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT