In: Operations Management
The following jobs are waiting to be processed at Jeremy LaMontagne's machine center. Today is day 240.
Job |
Date job received |
Due date |
Duration (days) |
1 |
210 |
270 |
25 |
2 |
215 |
280 |
35 |
3 |
220 |
295 |
45 |
4 |
235 |
315 |
40 |
5 |
240 |
340 |
15 |
Calculate the Critical Ratios (CR): (Enter all responses rounded to two decimal places.)
JOB CR
1 ?
2 ?
3 ?
4 ?
5 ?
Using the Critical Ratio (CR) scheduling rule for sequencing the jobs, the order is:
Sequence Job
1 ?
2 ?
3 ?
4 ?
5 ?
Answer (i)
Critical ratio is defined as the ratio obtained by dividing the
time remaining for due date by the total machine time left for that
job.
Critical ratio (CR)= Time remaining before due date/Remaining
processing time
Therefore for the given data, the CR will be:
Job | Date job received | Due date | Duration (Days) | Days left to due date (Due date-240) | CR (Days left to due/Duration) |
1 | 210 | 270 | 25 | 30 | 1.20 |
2 | 215 | 280 | 35 | 40 | 1.14 |
3 | 220 | 295 | 45 | 55 | 1.22 |
4 | 235 | 315 | 40 | 75 | 1.88 |
5 | 240 | 340 | 15 | 100 | 6.67 |
Answer (ii)
For scheduling the jobs, just arrange the jobs in the increasing order of their CR.
Job | Date job received | Due date | Duration (Days) | Days left to due date (Due date-240) | CR (Days left to due/Duration) | correct Order for scheduling |
1 | 210 | 270 | 25 | 30 | 1.20 | 2 |
2 | 215 | 280 | 35 | 40 | 1.14 | 1 |
3 | 220 | 295 | 45 | 55 | 1.22 | 3 |
4 | 235 | 315 | 40 | 75 | 1.88 | 4 |
5 | 240 | 340 | 15 | 100 | 6.67 | 5 |
Therefore, the correct order will be
2 -> 1 -> 3 -> 4 -> 5