Question

In: Operations Management

For the project with the activates and costs given below Probability that the project could finish...

  1. For the project with the activates and costs given below
  1. Probability that the project could finish in 31 days
  2. 95% confidence for project completion time

Activity

Predecessor

Optimistic Duration

Normal Duration

Pesimistic Duration

Normal Cost

Crash time

Crash Cost

A

NA

4

5

6

$ 300.00

5

$ 300.00

B

A

5

8

9

$ 250.00

5

$ 400.00

C

A

2

2

3

$ 100.00

2

$ 100.00

D

A

3

6

7

$ 300.00

3

$ 600.00

E

B,C

2

3

5

$ 150.00

2

$ 300.00

F

C,D

3

4

6

$ 275.00

3

$ 300.00

G

E,F

8

9

12

$ 700.00

8

$ 900.00

Solutions

Expert Solution

Based on the given data, we find expected completion of each activity as shown below:

The formula for the Expected activity duration and variance is shown in the table.

Based on precedence relationships and expected duration, we prepare a project network diagram as shown below:

The above network diagram in the form of formulas is shown below for better understanding and reference

The above project diagram is prepared as per the legend shown in the top-left corner.

EST = Early start time

LST = Late start time

EFT = Early finish time

LFT = Late finish time

SLK = Slack = LST - EST or Slack = LFT - EFT

The EST of an activity = EFT of previous activity

EFT of an activity = EST + Duration

Similarly LFT & LST are calculated during backward pass.

There are multiple paths in the diagram:

A-B-E-G

A-C-E-G

A-C-F-G

A-D-F-G

Out of the above paths, path A-B-E-G is the longest path and has 0 slack. Hence, this is the critical path

As seen from the above network diagram, the project completion time expected is 25.17 days

We find the probability of calculating the probability of completion in 31 days

We first find the total of variance over the critical path as shown below:

Variance over critical path = Variance for activity A + Variance for activity B + Variance for activity E + Variance for activity G = 0.111 + 0.444 + 0.25 + 0.444 = 1.25

We find z value using the formula below:

z = = =   5.21

Form Z table, for z = 5.21, Probability = 1 = 100% Hence,

Probability that the project could finish in 31 days = 100%

For a 95% confidence level,

Z = 1.96

We find the required duration as:

z =

1.96 = = 27.38 = 27.38 weeks

95% confidence for project completion time = 27.38 weeks

_______________________________________________________________________________________

In case of any doubt, please ask through the comment section before Upvote/downvote.


Related Solutions

2. Given the project information below, what is the probability of completing the National Holiday Toy...
2. Given the project information below, what is the probability of completing the National Holiday Toy project in 93 time units? Note 1: The Critical Path activities are: 1, 2, 4, 5, 6, 7. Note 2: Using the examples in Appendix 7.1 as a guide, calculate the weighted average activity time of each task (te). Determine the project duration. Calculate the variance. Use the Z-score formula, in Appendix 7.1 to calculate the Z-score. Note that non-critical path activities are not...
Given below is a list of costs: Direct labor                                   &
Given below is a list of costs: Direct labor                                                                 35,500 Accounting Dept. salaries                                          70,000 Indirect materials                                                        32,700 Depreciation, factory                                                  15,000 Direct materials                                                          66,000 Sales commission                                                       36,000 Indirect labor                                                              20,200 Advertising                                                                 5,800 Water and electricity of the office                              12,000 Required, From the above costs calculate the following costs (show your calculation): Total product costs Total period costs Total prime costs Total conversion costs
8. To analyze whether a putative transcriptional enhancer activates transcription, one could use which of the...
8. To analyze whether a putative transcriptional enhancer activates transcription, one could use which of the following approaches?     
It is known from past information that the probability of failing to finish an Ironman (called...
It is known from past information that the probability of failing to finish an Ironman (called a DNF) is 15%. Suppose we take a sample of 100 Ironman races over the past few years and find that the DNF percentage is 12%. We are interested in seeing if there has been a significant decrease in the number of DNFs. Use alpha=0.05. Find the 95% confidence interval for the percentage of DNFs. a. (0.0665, 0.1735) b. (0.0555, 0.1845) c. (0.1179, 0.1221)...
The probability distribution of returns for Stocks A and B are given in the table below....
The probability distribution of returns for Stocks A and B are given in the table below. If you invest $1,200,000 in Stock A and $800,000 in Stock B, calculate the expected return of your portfolio. State of Economy Probability of state Stock A's Return Stock B's Return Boom 0.20 40% 28% Normal 0.40 25% 12% Slow Down 0.30 0% 7% Recession 0.10 -20% 0% a.16.00% b.15.2% c.12.8% d.14.6% Group of answer choices
For the project with the five activities given below, you are required to crash the project...
For the project with the five activities given below, you are required to crash the project duration from its original duration to a final duration of 14 days. Assuming a daily indirect cost of $100, what is the total cost of the project with a duration of 14 days. For the project with the five activities given below, you are required to crash the project duration from its original duration to a final duration of 14 days. Assuming a daily...
Using the information provided in the table below, find the probability of completing the project in...
Using the information provided in the table below, find the probability of completing the project in 46 weeks? Activity Immediate Predecessor(s) Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) A none 3 6 9 B A 3 5 7 C A 4 7 12 D B, C 4 8 10 E B, C 9 12 18 F D 5 10 13 G E 3 6 8 H F 1 5 12 I G 7 8...
Given the data in the spreadsheet below, what is the probability of completing the critical path...
Given the data in the spreadsheet below, what is the probability of completing the critical path of the project in 34 or more time units? Activity Preceded By Optimistic Time Most Likely Time Pessimistic Time A None 12.89 15.25 18.21 B None 14.17 15.61 18.13 C A and B 12.33 14.2 17.98 D A and B 14.84 17.64 20.53
old Corporation is considering a project. The data for the 3 year project are given below....
old Corporation is considering a project. The data for the 3 year project are given below. Should the manager of Gold Corporation accept this project? Use the NPV criteria to make your decision. Sales revenue, each year: $50,000 Variable costs, each year: $12,000 Fixed costs, each year: $0 Sunk costs: $30,000 Initial outlay: $45,000 Depreciation, each year: $15,000 Tax rate: 20% WACC: 12% The project should not be accepted because it has an NPV of -$15,179 The project should be...
The cost formulas for Swan Company's manufacturing overhead costs are given below. The costs cover a...
The cost formulas for Swan Company's manufacturing overhead costs are given below. The costs cover a range of 20,000 to 40,000 machine-hours. Overhead Costs Cost Formula utilities $20,600 plus $0.10 per machine-hour maintenance $40,000 plus $1.60 per machine-hour supplies $0.30 per machine-hour indirect labor $130,000 plus $0.70 per machine-hour depreciation $70,000 Required: Prepare a flexable manufacturing overhead budget assuming a budgeted level of activity of 30,000 machine-hours. Include all costs in your flexable budget. Per Unit Total Variable Costs: _________...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT