In: Operations Management
Activity |
Predecessor |
Optimistic Duration |
Normal Duration |
Pesimistic Duration |
Normal Cost |
Crash time |
Crash Cost |
A |
NA |
4 |
5 |
6 |
$ 300.00 |
5 |
$ 300.00 |
B |
A |
5 |
8 |
9 |
$ 250.00 |
5 |
$ 400.00 |
C |
A |
2 |
2 |
3 |
$ 100.00 |
2 |
$ 100.00 |
D |
A |
3 |
6 |
7 |
$ 300.00 |
3 |
$ 600.00 |
E |
B,C |
2 |
3 |
5 |
$ 150.00 |
2 |
$ 300.00 |
F |
C,D |
3 |
4 |
6 |
$ 275.00 |
3 |
$ 300.00 |
G |
E,F |
8 |
9 |
12 |
$ 700.00 |
8 |
$ 900.00 |
Based on the given data, we find expected completion of each activity as shown below:
The formula for the Expected activity duration and variance is shown in the table.
Based on precedence relationships and expected duration, we prepare a project network diagram as shown below:
The above network diagram in the form of formulas is shown below for better understanding and reference
The above project diagram is prepared as per the legend shown in the top-left corner.
EST = Early start time
LST = Late start time
EFT = Early finish time
LFT = Late finish time
SLK = Slack = LST - EST or Slack = LFT - EFT
The EST of an activity = EFT of previous activity
EFT of an activity = EST + Duration
Similarly LFT & LST are calculated during backward pass.
There are multiple paths in the diagram:
A-B-E-G
A-C-E-G
A-C-F-G
A-D-F-G
Out of the above paths, path A-B-E-G is the longest path and has 0 slack. Hence, this is the critical path
As seen from the above network diagram, the project completion time expected is 25.17 days
We find the probability of calculating the probability of completion in 31 days
We first find the total of variance over the critical path as shown below:
Variance over critical path = Variance for activity A + Variance for activity B + Variance for activity E + Variance for activity G = 0.111 + 0.444 + 0.25 + 0.444 = 1.25
We find z value using the formula below:
z =
=
= 5.21
Form Z table, for z = 5.21, Probability = 1 = 100% Hence,
Probability that the project could finish in 31 days = 100%
For a 95% confidence level,
Z = 1.96
We find the required duration as:
z =
1.96 =
= 27.38 = 27.38 weeks
95% confidence for project completion time = 27.38 weeks
_______________________________________________________________________________________
In case of any doubt, please ask through the comment section before Upvote/downvote.