Question

In: Operations Management

2. Given the project information below, what is the probability of completing the National Holiday Toy...

2. Given the project information below, what is the probability of completing the National Holiday Toy project in 93 time units?

Note 1: The Critical Path activities are: 1, 2, 4, 5, 6, 7. Note 2: Using the examples in Appendix 7.1 as a guide, calculate the weighted average activity time of each task (te). Determine the project duration. Calculate the variance. Use the Z-score formula, in Appendix 7.1 to calculate the Z-score. Note that non-critical path activities are not included in Z-score calculations. Also be aware that a critical path activity may not need to be included, if it occurs parallel with another critical path activity and has the same te. Then use the statistical table A7.2 (or look for a Z-score table on the Internet, because the one is the text is abbreviated) and find the probability of completing the project in 93 time units.  

ID Description Predecessor (a) (m) (b) te Variance
1 Design package none 6 12 24
2 Design product 1 16 19 28
3 Build package 1 4 7 10
4 Secure patent 2 21 30 39
5 Build product 2 17 29 47
6 Paint 3, 4, 5 4 7 10
7 Test market 6 13 16 19

Solutions

Expert Solution

Here we have 2 critical paths which are parallel to each other 1-2-4-6-7 and 1-2-5-6-7

Project duration = duration of the longest path (Critical path) = 86 time units

We know, z = (x-expected project completion time)/project standard deviation

When x = 93,

Z = (93-86)/sqrt(24) = 1.428869017

So, probability of completing the project within 93 time units = norm.s.dist(1.428869017,TRUE) = 0.923479058

Formula


Related Solutions

Using the information provided in the table below, find the probability of completing the project in...
Using the information provided in the table below, find the probability of completing the project in 46 weeks? Activity Immediate Predecessor(s) Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) A none 3 6 9 B A 3 5 7 C A 4 7 12 D B, C 4 8 10 E B, C 9 12 18 F D 5 10 13 G E 3 6 8 H F 1 5 12 I G 7 8...
Given the data in the spreadsheet below, what is the probability of completing the critical path...
Given the data in the spreadsheet below, what is the probability of completing the critical path of the project in 34 or more time units? Activity Preceded By Optimistic Time Most Likely Time Pessimistic Time A None 12.89 15.25 18.21 B None 14.17 15.61 18.13 C A and B 12.33 14.2 17.98 D A and B 14.84 17.64 20.53
A project manager wants to calculate the probability of completing his project in 30 days. If...
A project manager wants to calculate the probability of completing his project in 30 days. If the variance of the critical path is 1.33 and the critical path is completed in 32 days, what is the probability of completing the project in 30 days? 41.8% 32% 4.18% 0 45.82%
Using the Program Evaluation Review Technique, what is the probability of completing the project on or before 60 days?
Using the Program Evaluation Review Technique, what is the probability of completing the project on or before 60 days?
Given that the data below was randomly selected from a lognormal distribution. What is the probability...
Given that the data below was randomly selected from a lognormal distribution. What is the probability of a randomly selected item having a value greater than 3.9? Give your answer to 3 decimal places. Data 1.72, 124.2, 1.04, 0.84, 12.82, 11.76, 51.2, 0.11
Given that the data below was randomly selected from a lognormal distribution. What is the probability...
Given that the data below was randomly selected from a lognormal distribution. What is the probability of a randomly selected item having a value greater than 3.9? Give your answer to 3 decimal places. Data 1.72, 124.2, 1.04, 0.84, 12.82, 11.76, 51.2, 0.11 answer - 0.846 was wrong  
Part 1: Information to use in completing is below and the requirements follow where you will...
Part 1: Information to use in completing is below and the requirements follow where you will answer the questions. Glass Company makes glass orders based on the customer specifications, so the company uses job costing to track costs. 1. The company uses direct labor hours as the cost driver for manufacturing overhead application. The company estimated the following manufacturing overhead costs for the year:   $600,000 The company estimated the following usage of direct-labor hours for the year: 200,000 2. Beginning...
Assignment OverviewUnit 2 - Individual Project ASSIGNMENT DESCRIPTIONDeliverable Length: 5–7 pages OBJECTIVES Additional Information After completing...
Assignment OverviewUnit 2 - Individual Project ASSIGNMENT DESCRIPTIONDeliverable Length: 5–7 pages OBJECTIVES Additional Information After completing your stakeholder analysis and developing your stakeholder register, you started working on your next project, which will be to develop a project charter. You started to gather information from various stakeholders via interviews and e-mails. The latest e-mail you sent caused quite a response. Several meetings were centered on the project charter, statement of work (SOW), work breakdown structure (WBS), and enterprise environmental factors...
Below information is for Question 1 & 2: You are analyzing a project and have gathered...
Below information is for Question 1 & 2: You are analyzing a project and have gathered the following data: Year Cash Flow o -$175,000 1 $56,000 2 $61,800 3 $72,000 4 $75,000 Required payback period of 2.5 year Required return 14.5% 1. Based on the net present value of__________, you should_________the project. (please show work). A. $12,995.84; accept B. -$15,030.75; reject C. -$12,995.84; reject D. $9,283.60; accept 2. Based on the payback period of ______ years for this project, you...
Miss Maple is considering 2 securities, A and B, and the relevant information is given below:...
Miss Maple is considering 2 securities, A and B, and the relevant information is given below: State of Economy Prob. Return on A Return on B Bear 0.4 0.03 0.065 Bull 0.6 0.15 0.065 (a). Calculate the expected returns and standard deviations of the two securities. b) Suppose Miss Maple invested $2,500 in security A and $3,500 in security B. Calculate the expected return and standard deviation of her portfolio. (c). Suppose Miss Maple borrowed from her friend 40 shares...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT