| Using the information provided in the table below, find the probability of completing the project in 46 weeks? | ||||
| Activity | Immediate Predecessor(s) | Optimistic Time Estimate (weeks) | Most Likely Time Estimates (weeks) | Pessimistic Time Estimates (weeks) |
| A | none | 3 | 6 | 9 |
| B | A | 3 | 5 | 7 |
| C | A | 4 | 7 | 12 |
| D | B, C | 4 | 8 | 10 |
| E | B, C | 9 | 12 | 18 |
| F | D | 5 | 10 | 13 |
| G | E | 3 | 6 | 8 |
| H | F | 1 | 5 | 12 |
| I | G | 7 | 8 | 9 |
| J | H, I | 3 | 3 | 3 |