Question

In: Operations Management

Using the information provided in the table below, find the probability of completing the project in...

Using the information provided in the table below, find the probability of completing the project in 46 weeks?
Activity Immediate Predecessor(s) Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks)
A none 3 6 9
B A 3 5 7
C A 4 7 12
D B, C 4 8 10
E B, C 9 12 18
F D 5 10 13
G E 3 6 8
H F 1 5 12
I G 7 8 9
J H, I 3 3 3

Solutions

Expert Solution


Related Solutions

2. Given the project information below, what is the probability of completing the National Holiday Toy...
2. Given the project information below, what is the probability of completing the National Holiday Toy project in 93 time units? Note 1: The Critical Path activities are: 1, 2, 4, 5, 6, 7. Note 2: Using the examples in Appendix 7.1 as a guide, calculate the weighted average activity time of each task (te). Determine the project duration. Calculate the variance. Use the Z-score formula, in Appendix 7.1 to calculate the Z-score. Note that non-critical path activities are not...
Valuation of assets   Using the information provided in the following​ table, find the value of each​...
Valuation of assets   Using the information provided in the following​ table, find the value of each​ asset: Asset End of Year Amount A 1 3000 18% 2 3000 3 3000 B 1 through &inf; 300 15% C 1 0 16% 2 0 3 0 4 0 5 30000 D 1 through 5 1900 13% 6 8600 E 1 2000 13% 2 3000 3 5000 4 7000 5 4000 6 1000
Using the information provided in the following​ table, find the value of each​ asset: The value...
Using the information provided in the following​ table, find the value of each​ asset: The value of Asset A is ​ The value of Asset B The value of Asset C The value of Asset D The value of Asset E Asset End of Year Amount Appropriate required return A 1 ​$ 7,000 8​% 2 7,000 3 7,000 B 1 through∞ ​$ 500 4​% C 1 ​$ 0 5​% 2 0 3 0 4 0 5 48,000 D 1 through...
Using the table below, find the Probability of Ordering as a decimal and percent. Please show...
Using the table below, find the Probability of Ordering as a decimal and percent. Please show your work and formulas you would use in excel. # of pizzas ordered # of customers who ordered Probability of ordering (decimal value) Probability of ordering (as a percent) 1 8 2 9 3 6 4 1 5 0 6 0 7 0 8 0 Sum total 24
Using the information provided in the following table, find the value of each asset. Cash flow...
Using the information provided in the following table, find the value of each asset. Cash flow Asset end of year Amount Appropriate required return A 1 $6,000 13% 2 6,000 3 6,000 B 1 through ∞ $200 10% C 1 $0 12% 2 $0 3 $0 4 $0 5 35,000 D 1 through 5 $2,500 12% 6 8,500 E 1 $3,000 19% 2 2,000 3 8,000 4 7,000 5 4,000 6 1,000
Consider the information provided in the following table. Using the additional information provided at the bottom,...
Consider the information provided in the following table. Using the additional information provided at the bottom, calculate the value of the firm using FCFF method.                                                           [15] Year 2019 2020 2021 2022 2023 2024 2025 Total Assets 10000 Fixed Assets 8000 Current assets 2000 Debt 4000 Equity 5000 Current liabilities 1000 Sales 15000 Operating expenses 12000 EBIT 3000 Int 400 PBT 2600 Tax(25%) 650 PAT 1950 For first five years, growth rate is sales in 5% and from sixth year...
the table below provides information for a probability distribution. use the table below to answer the...
the table below provides information for a probability distribution. use the table below to answer the following questions. X p(X) 0 .10 1 .60 2 .30 a. calculate the variance. b. calculate the standard deviation
Using the Program Evaluation Review Technique, what is the probability of completing the project on or before 60 days?
Using the Program Evaluation Review Technique, what is the probability of completing the project on or before 60 days?
A project manager wants to calculate the probability of completing his project in 30 days. If...
A project manager wants to calculate the probability of completing his project in 30 days. If the variance of the critical path is 1.33 and the critical path is completed in 32 days, what is the probability of completing the project in 30 days? 41.8% 32% 4.18% 0 45.82%
arah provided you with the following information in the table and you are required to find...
arah provided you with the following information in the table and you are required to find the value of the below bond to assist her with her investment decision: Cash Flow Appropriate required return End of year Amount (N$) 1 750.00 15% 2 750.00 3 750.00 4 750.00 until infinity 750.00
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT