In: Finance
Task:
Senior management asks you to recommend a decision on which project(s) to accept based on the cash flow forecasts provided.
Relevant information:
The cash flows for projects A, B and C are provided below.
Project A |
Project B |
Project C |
|
Year 0 |
-30,000 |
-20,000 |
-50,000 |
Year 1 |
0 |
4,000 |
20,000 |
Year 2 |
7,000 |
5,000 |
20,000 |
Year 3 |
20,000 |
6,000 |
20,000 |
Year 4 |
20,000 |
7,000 |
5,000 |
Year 5 |
10,000 |
8,000 |
5,000 |
Year 6 |
5,000 |
9,000 |
5,000 |
Which projects would you accept based on the NPV criterion?