Question

In: Finance

Compute the Discounted Payback statistic for Project X and recommend whether the firm should accept or...

Compute the Discounted Payback statistic for Project X and recommend whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 14 percent and the maximum allowable discounted payback is 3 years.

Time: 0 1 2 3 4 5
Cash flow: -960 460 520 440 340 190

Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 11 percent.

Time: 0 1 2 3 4 5
Cash flow: -83 -83 0 108 83 58

Solutions

Expert Solution

First:

Year Investment Net annual cash flow Cumulative net cash flow Balance to be recovered
0                  (960)                             -                       960.00
1                    460                         460                     500.00
2                    520                         980                              -  
3                    440                      1,420                              -  
4                    340                      1,760                              -  
5                    190                      1,950                              -  
Capital is recovered fully in year 2
Pay back period is= 1 + 500/520 1.96

Accept as payback is less than 3 years

Second:

Year Cash flow × factor@ 11.00% Present value
0 $              (83.00) 1.0000 $                    (83.00)
1 $              (83.00) 0.9009 $                    (74.77)
2 $             108.00 0.8116 $                     87.66
3 $                      -   0.7312 $                            -  
4 $               83.00 0.6587 $                     54.67
5 $               58.00 0.5935 $                     34.42
NPV 3.6959 $                     18.98

PI = (87.66+54.67+34.42)/(83+74.77) = 1.12

Accept project


Related Solutions

Compute the Discounted Payback statistic for Project X and recommend whether the firm should accept or...
Compute the Discounted Payback statistic for Project X and recommend whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 12 percent and the maximum allowable discounted payback is 3 years.   Time: 0 1 2 3 4 5   Cash flow: -980 380 600 520 420 270 Multiple Choice 2.78 years, accept 3.44 years, reject 2.44 years, accept 4.78 years, reject
Compute the payback statistics (Not discounted) for Project X and recommend whether the firm should accept...
Compute the payback statistics (Not discounted) for Project X and recommend whether the firm should accept or reject the project with the cash flows shown as follows if the appropriare cost of capital is 10 percent and the maximum allowable payback is five years. Time:                  0        1      2        3         4       5 Cash flow:        -75   -75     0     100     75     50 a. 3.67 years, accept b. 4.67 years, accept c. 3.67 years, reject d. 4.67 years, reject
Compute the PI statistic for Project X and note whether the firm should accept or reject...
Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown as follows if the appropriate cost of capital is 10%. Time 0 1 2 3 4 5 Cash Flow -250 75 0 100 75 50 a) 2.41, accept b) 0.023, reject c) 0.90, reject d) 1.97, accept
Compute the PI statistic for Project X and note whether the firm should accept or reject...
Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 8 percent. Time: 0, 1, 2, 3, 4, 5 Cash Flow: -82, -82, 0, 117, 92, 67 Time: 0 1 2 3 4 5 Cash flow: -82 -82 0 117 92 67 Multiple Choice 48.17 percent, reject 8.00 percent, accept 58.74 percent, accept 47.21 percent, reject All information is...
Compute the PI statistic for Project X and note whether the firm should accept or reject...
Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 10 percent.   Time: 0 1 2 3 4 5   Cash flow: -75 -75 0 100 75 50
Compute the PI statistic for Project X and note whether the firm should accept or reject...
Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 10 percent.   Time: 0 1 2 3 4 5   Cash flow: -80 -80 0 115 90 65   
Compute the PI statistic for Project X and note whether the firm should accept or reject...
Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 6 percent. Time: 0 1 2 3 4 5 Cash flow:-84 -84 0 109 84 59
1.      Compute the IRR for Project X and note whether the firm should accept or reject...
1.      Compute the IRR for Project X and note whether the firm should accept or reject the project with the cash flows shown as follows if the appropriate cost of capital is 9 percent. Time: 0 1 2 3 4 5 Cash flow: ?1,000 ?75 100 100 0 2,000 A.      9 PERCENT, ACCEPT B.       9 PERCENT, REJECT C.       16.61 PERCENT, ACCEPT D.      16.61 PERCENT, REJECT
Problem 13-8 Discounted Payback (LG13-2) Compute the discounted payback statistic for Project D if the appropriate...
Problem 13-8 Discounted Payback (LG13-2) Compute the discounted payback statistic for Project D if the appropriate cost of capital is 11 percent and the maximum allowable discounted payback is four years. (Do not round intermediate calculations and round your final answer to 2 decimal places. If the project does not pay back, then enter a "0" (zero).) Project D Time: 0 1 2 3 4 5 Cash flow: –$12,800 $3,530 $4,540 $1,880 $0 $1,360 Problem 13-8 Discounted Payback (LG13-2) Compute...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 6...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 6 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations. Round your final answer to 2 decimal places.) Project C Time: 0 1 2 3 4 5 Cash flow –$2,900 $1,240 $1,050 $1,090 $680 $480 Discounted payback period years Should the project be accepted or rejected? Rejected Accepted
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT