In: Finance
Compute the Discounted Payback statistic for Project X and
recommend whether the firm should accept or reject the project with
the cash flows shown below if the appropriate cost of capital is 14
percent and the maximum allowable discounted payback is 3
years.
Time: | 0 | 1 | 2 | 3 | 4 | 5 |
Cash flow: | -960 | 460 | 520 | 440 | 340 | 190 |
Compute the PI statistic for Project X and note whether the firm
should accept or reject the project with the cash flows shown below
if the appropriate cost of capital is 11 percent.
Time: | 0 | 1 | 2 | 3 | 4 | 5 |
Cash flow: | -83 | -83 | 0 | 108 | 83 | 58 |
First:
Year | Investment | Net annual cash flow | Cumulative net cash flow | Balance to be recovered |
0 | (960) | - | 960.00 | |
1 | 460 | 460 | 500.00 | |
2 | 520 | 980 | - | |
3 | 440 | 1,420 | - | |
4 | 340 | 1,760 | - | |
5 | 190 | 1,950 | - | |
Capital is recovered fully in year | 2 | |||
Pay back period is= | 1 + 500/520 | 1.96 |
Accept as payback is less than 3 years
Second:
Year | Cash flow | × factor@ 11.00% | Present value |
0 | $ (83.00) | 1.0000 | $ (83.00) |
1 | $ (83.00) | 0.9009 | $ (74.77) |
2 | $ 108.00 | 0.8116 | $ 87.66 |
3 | $ - | 0.7312 | $ - |
4 | $ 83.00 | 0.6587 | $ 54.67 |
5 | $ 58.00 | 0.5935 | $ 34.42 |
NPV | 3.6959 | $ 18.98 |
PI = (87.66+54.67+34.42)/(83+74.77) = 1.12
Accept project