Question

In: Finance

Compute the Discounted Payback statistic for Project X and recommend whether the firm should accept or...

Compute the Discounted Payback statistic for Project X and recommend whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 12 percent and the maximum allowable discounted payback is 3 years.


  Time: 0 1 2 3 4 5
  Cash flow: -980 380 600 520 420 270

Multiple Choice

  • 2.78 years, accept

  • 3.44 years, reject

  • 2.44 years, accept

  • 4.78 years, reject

Solutions

Expert Solution

Given cash flow about a project X,

Cost of capital for the project Kc = 12%

Its discounted cash flow and cumulative discounted cash flows are also calculated as below:

discounted cash flow = cash flow/(1+Kc)^year

cumulative discounted cash flow = previous year cumulative discounted cash flow + current year discounted cash flow

Year Cash flow Discounted Cash flow Cumulative discounted cash flow
0 $     -980.00 $                          -980.00 $                                                   -980.00
1 $       380.00 $                            339.29 $                                                   -640.71
2 $       600.00 $                            478.32 $                                                   -162.40
3 $       520.00 $                            370.13 $                                                     207.73
4 $       420.00 $                            266.92 $                                                     474.65
5 $       270.00 $                            153.21 $                                                     627.85

Discounted Payback period of a project = year before the cumulative discounted cash flow turns positive + (discounted cumulative cash flow of period before recovery/discounted cash flow of recovery period)

So, here Payback period = 2 + 162.40/370.13 = 2.44 years

Since maximum allowable discounted payback period is 3 years and projects discounted payback period is 2.44 years, Project should be accepted.

Option C is correct.


Related Solutions

Compute the Discounted Payback statistic for Project X and recommend whether the firm should accept or...
Compute the Discounted Payback statistic for Project X and recommend whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 14 percent and the maximum allowable discounted payback is 3 years. Time: 0 1 2 3 4 5 Cash flow: -960 460 520 440 340 190 Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows...
Compute the payback statistics (Not discounted) for Project X and recommend whether the firm should accept...
Compute the payback statistics (Not discounted) for Project X and recommend whether the firm should accept or reject the project with the cash flows shown as follows if the appropriare cost of capital is 10 percent and the maximum allowable payback is five years. Time:                  0        1      2        3         4       5 Cash flow:        -75   -75     0     100     75     50 a. 3.67 years, accept b. 4.67 years, accept c. 3.67 years, reject d. 4.67 years, reject
Compute the PI statistic for Project X and note whether the firm should accept or reject...
Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown as follows if the appropriate cost of capital is 10%. Time 0 1 2 3 4 5 Cash Flow -250 75 0 100 75 50 a) 2.41, accept b) 0.023, reject c) 0.90, reject d) 1.97, accept
Compute the PI statistic for Project X and note whether the firm should accept or reject...
Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 8 percent. Time: 0, 1, 2, 3, 4, 5 Cash Flow: -82, -82, 0, 117, 92, 67 Time: 0 1 2 3 4 5 Cash flow: -82 -82 0 117 92 67 Multiple Choice 48.17 percent, reject 8.00 percent, accept 58.74 percent, accept 47.21 percent, reject All information is...
Compute the PI statistic for Project X and note whether the firm should accept or reject...
Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 10 percent.   Time: 0 1 2 3 4 5   Cash flow: -75 -75 0 100 75 50
Compute the PI statistic for Project X and note whether the firm should accept or reject...
Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 10 percent.   Time: 0 1 2 3 4 5   Cash flow: -80 -80 0 115 90 65   
Compute the PI statistic for Project X and note whether the firm should accept or reject...
Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 6 percent. Time: 0 1 2 3 4 5 Cash flow:-84 -84 0 109 84 59
1.      Compute the IRR for Project X and note whether the firm should accept or reject...
1.      Compute the IRR for Project X and note whether the firm should accept or reject the project with the cash flows shown as follows if the appropriate cost of capital is 9 percent. Time: 0 1 2 3 4 5 Cash flow: ?1,000 ?75 100 100 0 2,000 A.      9 PERCENT, ACCEPT B.       9 PERCENT, REJECT C.       16.61 PERCENT, ACCEPT D.      16.61 PERCENT, REJECT
Problem 13-8 Discounted Payback (LG13-2) Compute the discounted payback statistic for Project D if the appropriate...
Problem 13-8 Discounted Payback (LG13-2) Compute the discounted payback statistic for Project D if the appropriate cost of capital is 11 percent and the maximum allowable discounted payback is four years. (Do not round intermediate calculations and round your final answer to 2 decimal places. If the project does not pay back, then enter a "0" (zero).) Project D Time: 0 1 2 3 4 5 Cash flow: –$12,800 $3,530 $4,540 $1,880 $0 $1,360 Problem 13-8 Discounted Payback (LG13-2) Compute...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 6...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 6 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations. Round your final answer to 2 decimal places.) Project C Time: 0 1 2 3 4 5 Cash flow –$2,900 $1,240 $1,050 $1,090 $680 $480 Discounted payback period years Should the project be accepted or rejected? Rejected Accepted
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT