Question

In: Finance

19. What is the NPV of the project? Which you accept the project?

19. What is the NPV of the project? Which you accept the project?


Solutions

Expert Solution

Net Present Value (NPV) of a project is sum of all cash flows of the project discounted at the required rate of return. Required rate of return is rate of return we can generate by investing the money in alternative assets.

For example, if our initial investment(Cash outflow at year 0) is $100,000, yearly cash inflow from the project is $30,000 for 5 years and required rate of return is 12%. Then NPV is calculated as follows-

0 1 2 3 4 5
Cash Outflow (Given in negative since it is outflow)     (100,000)
Cash inflow       30,000     30,000     30,000     30,000        30,000
Discounting Factor at Required Rate of return@12%                  1      0.8929     0.7972     0.7118     0.6355        0.5674
[1/{(1+0.12)^n}]
Where, n is the number of year
Discounted Cash Flows (Cash flows*disounting factor)     (100,000)       26,786     23,916     21,353     19,066        17,023

Hence NPV = (100,000) + 26,786 +23,916+21,353+21,353+19,066+17,023 = 8,143

When a NPV of a project is positive, we should accept the project since we are getting more than the investment (cash inflow is more than Cash outflow ).

In the example, we have positive cash flow, we should accept the project.

If NPV of a project is negative, we should reject the project.


Related Solutions

Calculate the NPV for Project A and accept or reject the project with the cash flows...
Calculate the NPV for Project A and accept or reject the project with the cash flows shown below if the appropriate cost of capital is 7% Project A Time 0 1 2 3 4 5 Cash Flow -990 350 480 500 630 120 2) Calculate the NPV for project L and recommend whether the company should accept or reject the project. Cost of Capital is 6% Project L Time 0 1 2 3 4 5 Cash Flow -         8,600          ...
Norman Inc. wishes to accept a new project which has a NPV of US$98,000. A sum...
Norman Inc. wishes to accept a new project which has a NPV of US$98,000. A sum of US$10,000,000 will be needed to invest in it. The net earnings for the current year are US$1,000,000 and the accumulated retained earnings to date are US$7,000,000. The current amount of long term debt carried on Norman Inc.’s balance sheet is US$5,333,333.33. Norman Inc. wishes to finance the new investments in line with its existing capital structure. i. Will Norman Inc. be in a...
What is the payback period, NPV, IRR of A. Using this information, should we accept Project...
What is the payback period, NPV, IRR of A. Using this information, should we accept Project A. Why or why not. Given the following information answer the question above. The discount rate is 10 percent.      PROJECT A       t           Cash Flow       0          (150,000)        1          40,000           2          40,000              3          40,000          4           40,000           5            40,000               ROUND TO NEAREST DOLLAR OR TEN %
20. What is the PI (Profitability Index) ratio for the project? Will you accept the project...
20. What is the PI (Profitability Index) ratio for the project? Will you accept the project based on the PI ratio?
If these two projects are mutually exclusive, which project should the company accept based on the NPV, IRR, MIRR, payback, and discounted payback period for each project?
Considering the following projects.ProjectYear01234ACash flows-$100$35$35$35$35BCash flows-$100$60$50$40$30Project A has WACC = 6.00% while project B has WACC = 8.50%.If these two projects are mutually exclusive, which project should the company accept based on the NPV, IRR, MIRR, payback, and discounted payback period for each project?Would your decision (Your answer from part A) change if these two projects were independent?
Calculate the IRR, the NPV, and the MIRR for each project, and indicate the correct accept/reject decision for each.
11.  Problem 10-08 (NPVs, IRRs, and MIRRs for Independent Projects)NPVs, IRRs, and MIRRs for Independent ProjectsEdelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system, in this year's capital budget. The projects are independent. The cash outlay for the truck is $18,000, and that for the pulley system is $22,000. The firm's cost of capital is 14%. After-tax cash flows, including depreciation, are as follows:YearTruckPulley1$5,100$7,50025,1007,50035,1007,50045,1007,50055,1007,500Calculate the IRR, the NPV, and the MIRR for each project,...
Senior management asks you to recommend a decision on which project(s) to accept based on the...
Senior management asks you to recommend a decision on which project(s) to accept based on the cash flow forecasts provided.The firm uses a 3-year cutoff when using the payback method. The hurdle rate used to evaluate capital budgeting projects is 15%. Assume the projects are independent and answer the following: Calculate the payback period for each project. Which project(s) would you accept based on the payback criterion? Calculate the internal rate of return (IRR) for each project. Which projects would...
You are trying to decide whether to accept or reject a project. The project will generate...
You are trying to decide whether to accept or reject a project. The project will generate a cash flow of $15,000 in year one; $25,000 in year two; $20,000 in year three; and $4,000 in year four. The project costs $40,000 initially. The firm has a weighted average cost of capital of 8%. Your firm generally accepts projects that payback in three years or less. What is the discounted payback of the project? Should you accept or reject the project?
Calculate the NPV for each project and determine which project should be accepted. Project A Project...
Calculate the NPV for each project and determine which project should be accepted. Project A Project B Project C Project D Inital Outlay (105,000.000) (99,000.00) (110,000.00) (85,000.00) Inflow year 1 53,000.00 51,000.00 25,000.00 45,000.00 Inflow year 2 50,000.00 47,000.00 55,000.00 50,000.00 Inflow year 3 48,000.00 41,000.00 15,000.00 30,000.00 Inflow year 4 30,000.00 52,000.00 21,000.00 62,000.00 Inflow year 5 35,000.00 40,000.00 35,000.00 68,000.00 Rate 7% 10% 13% 18% Your company is considering three independent projects. Given the following cash flow information,...
Calculate the NPV for each project and determine which project should be accepted. Project A Project...
Calculate the NPV for each project and determine which project should be accepted. Project A Project B Project C Project D Initial Outlay (105,000.00) (99,000.00) (110,000.00) (85,000.00) Inflow year 1 53,000.00 51,000.00 25,000.00 45,000.00 Inflow year 2 50,000.00 47,000.00 55,000.00 50,000.00 Inflow year 3 48,000.00 41,000.00 15,000.00 30,000.00 Inflow year 4 30,000.00 52,000.00 21,000.00 62,000.00 Inflow year 5 35,000.00 40,000.00 35,000.00 68,000.00 Rate 7% 10% 13% 18% NPV = $75,228.32 $77,364.07 -$2,531.00 $69,006.08 Answer: Project B How to show work...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT