A rectangular beam has a width of 300 mm and an effective depth of 510 mm....

A rectangular beam has a width of 300 mm and an effective depth of 510 mm. It carries Vu = 200 KN and Mu = 55 KN-m and is reinforced with 2650 mm2. Use f’c = 21 MPa and fy = 345 MPa. Normal concrete. Express your answer in two decimal places.

a. Compute the shear strength in KN provided by concrete using the less conservative formula as shown. Express your answer in two decimal places.

b. Calculate the required area of compression reinforcement in mm2 due to the factored moment, Mu.

c. Compute the shear force in KN to be carried by the transverse reinforcements.

d. What is the e spacing of stirrups in mm?

In: Civil Engineering

1. Managing material cost, worker productivity, and subcontractor requests for extra compensation are all project risks....

1. Managing material cost, worker productivity, and subcontractor requests for extra compensation are all project risks. Discuss how the tools or activities listed below can help manage these risks.

a. Weekly job cost analysis

b. Pre-award subcontractor proposal analysis for completeness and feasibility

c. Hard bids on material unit costs

d. Contracts for material purchase

e. Firm contract procedures for claims for additional costs f. Assigning risk to those best able to manage it

In: Civil Engineering

. Discuss the use and types of estimate you can use for: a. project planning b....

. Discuss the use and types of estimate you can use for:

a. project planning

b. establishing contract costs

c. managing the costs in the field

d. change order pricing.

In: Civil Engineering

The concept of slab panels are designed as in a single unit, however each consisting of...

The concept of slab panels are designed as in a single unit, however each consisting of one or more slab items (slab panels). When it comes to design you then need to conceptualize the slab as a series of design panels. Each design panel will have its own results. Different reinforcement can be selected in different panels. More often than not, pattern loading (some panels loaded and others not). In reference to the afore mentioned; produce and explain five types panel used for slab construction. Annotated sketches can be made to support the answers.

In: Civil Engineering

1. A contractor is planning to use a crawler tractor with power shift transmission to push...

1. A contractor is planning to use a crawler tractor with power shift transmission to push 1,500 LCY. The tractor must haul the loose material up a 12% slope where it will be stockpiled for later removal. The contractor has measured the tractor blade load measurement: the pile length 12.6 ft, the pile width 8.1 ft, and the pile height 4 ft. The tractor weighs 44,400 pounds, and the coefficient of traction is estimated to be 0.7. The average haul distance is estimated to be 300 ft. The job efficiency is 50 minutes per hour. Performance characteristics of the tractor are shown in the lecture slides. (Note: 1 mi/hr = 88 ft/min).

1) What is the estimated productivity of the tractor? (First gear for dozing; Third gear for return.)

2) Estimate the total hours to complete the work.

3) Determine if the tractor can perform the work in the given condition above.

In: Civil Engineering

4. What are the three most frequently and widely assigned rock mechanics property measurement tests? Explain...

4. What are the three most frequently and widely assigned rock mechanics property measurement tests? Explain them. How are they each used in rock mechanics property measurement test?

In: Civil Engineering

Prepare an earned value schedule for a public construction project improving the drainage system of a...

Prepare an earned value schedule for a public construction project improving the drainage system of a neighborhood street.

In: Civil Engineering

Related to subject of ( Reinforcement Concrete ) Answer the following in very short answers:- Please...

Related to subject of ( Reinforcement Concrete )
Answer the following in very short answers:-
Please use typing only.

1- What is the difference between a Type A and Type B splice?

2- Why is it conservative to assume that the moment capacity and area of steel vary linearly instead of using the quadratic relationship?

3- Why is this helpful to speed up the moment design?

In: Civil Engineering

Conduct a web search for a news article of a large-scale soils/foundation issue, problem, or failure...

Conduct a web search for a news article of a large-scale soils/foundation issue, problem, or failure problem. Prepare a 3-page document on analysis and interpretation of any soils/foundation related current news article following the format below. 1. Summarize Article in ½ page 2. What Aspect or Topic in EGR 354 is it related to? Be specific. List all that Apply 3. Define Problem Statement and its Causes. Use Technical Language based on lessons from EGR 354. 4. What proposed solutions would you have suggested differently? 5. Determine any social and environmental effects of your solutions. Have to include the references.

In: Civil Engineering

What is the difference between a prescriptive specification and a performance standard for the production of...

What is the difference between a prescriptive specification and a performance standard

for the production of wood structural panels?

In: Civil Engineering

Briefly describe the span rating found in the grade-trademark of sheathing grades and APA Rated Strud-I-Floor

Briefly describe the span rating found in the grade-trademark of sheathing grades and APA Rated Strud-I-Floor

In: Civil Engineering

A contractor must choose between buying or renting a crane for the duration of a 5...

A contractor must choose between buying or renting a crane for the duration of a 5 year construction project. The contractor uses an MARR of 8%. At the end of the project, the crane can be sold for 26% of its initial cost. The cost to operate and maintain the crane is $210,000 per year. Renting the crane costs $330,000 per year including all operating and maintenance costs. Determine the maximum amount the contractor should pay to purchase the crane (i.e. the breakeven initial cost of the crane). Express your answer in $ to the nearest $1,000

In: Civil Engineering

The settlement of a structure has the normally distributed probability density function with a mean of...

The settlement of a structure has the normally distributed probability density function with a mean of 26mm and a coefficient of a variation of 20%.

1) What is the probability that the settlement is less than 22mm?

2) What is the probability that the settlement is between 24mm and 29mm?

3) What is the probability that the settlement exceeds 31mm?

In: Civil Engineering

flow chart and description for water and wastewater treatment facility.

flow chart and description for water and wastewater treatment facility.

In: Civil Engineering

Imagine that you are a traveler from Mongol-ruled China who has traveled to Western Europe in...

Imagine that you are a traveler from Mongol-ruled China who has traveled to Western Europe in the 1200s. Describe the customs and lifeways of medieval Europe in a way that would be familiar to a reader from medieval China.

Remember that your answer needs to be at least two paragraphs long. When you reply to a fellow student, write as though you are a medieval Central Asian Turk or Chinese person trying to understand the lifeways and customs of the medieval Europeans.

In: Civil Engineering