Questions
Write a 2 to 3 page literature review on how is hazardous waste controlled in developing...

Write a 2 to 3 page literature review on how is hazardous waste controlled in developing countries like India , China, Mexico, Uganda?

In: Civil Engineering

Potentially, which models would be used for traffic flow ? provide one example with an mathematical...

Potentially, which models would be used for traffic flow ? provide one example with an mathematical explanation

In: Civil Engineering

Problem 1: Assume the mix is made with Type I cement, with no pozzolans or admixtures,...

Problem 1:
Assume the mix is made with Type I cement, with no pozzolans or admixtures, and that the temperature of concrete at placing is 75°F. The unit weight of concrete is 150 pcf with a slump of 3.75 inches.
Design forms for 13’-8” high wall to be concreted at the rate of 6 ft per hour, internally vibrated.
The forms will be used only once, so short-term loading stresses will apply.
Use form grade plywood sheathing 7/8 in. thick in 5×10-ft sheets, and 5,250-lb coil ties are on hand.
Framing lumber of No. 2 Douglas Fir-Larch is to be purchased as required
Problem 2:
Draw the pressure diagram for a wall form 15 feet tall in which concrete will be placed at a rate R = 10 feet per hour when the temperature is 60oF. Draw the diagram if the wall were only 6 feet tall.

In: Civil Engineering

14.15 Aconcrete-linedtrapezoidalchannelhastobeconstructedtocarryadischargeof500cfs. Design the channel. Assume that the following values were fixed based on the site...

  1. 14.15 Aconcrete-linedtrapezoidalchannelhastobeconstructedtocarryadischargeof500cfs. Design the channel. Assume that the following values were fixed based on the site conditions:

    1. Bed slope = 0.002
    2. n=0.015
    3. Side slope, z = 1 (vertical):1.5 (horizontal) 4. b/y ratio = 2.0

  2. 14.16 DesignthechannelofProblem14.15asamost-hydraulic-efficientchannel(ofsemicircu- lar section).

  3. 14.17 DesignthechannelofProblem14.15asabest-hydraulicrectangularsection.

In: Civil Engineering

A two-lane rural highway, four-leg intersection will have its stop control replaced by a signal control....

A two-lane rural highway, four-leg intersection will have its stop control replaced by a signal control. Compute the expected average total crash frequency (all types, all severities) after the change for the following conditions: 


Expected average crash frequency before change: 23 total crashes/yr
AADT on minor road: 1500 veh/day

AADT on major road: 5000 veh/day 


Please show all work and formulas used. Thanks! Submitting this again this the last person didn't even answer the question at all. Not sure what they were reading.

In: Civil Engineering

The composition of "ordinary" Portland cement is 63.82% CaO, 20.56% SiO 2, 5.50%Al 2O 3, 0.76%K...

The composition of "ordinary" Portland cement is 63.82% CaO, 20.56% SiO 2, 5.50%Al 2O 3, 0.76%K 2O, 0.32% Na 2O, 0.95% other, and 0.52% insoluble. When mixed with water the resulting cement slurry is basic. Identify three bases of Portland cement and the compounds they form when mixed with water.

In: Civil Engineering

What new technologies were important in the history of bridges? Why did the Romans use elevated...

What new technologies were important in the history of bridges?

Why did the Romans use elevated aqueducts instead of pipes to convey their water?

Which of the Grand Challenges for the 21st century do you believe is most important? why? which challenge do you believe to be the least important? why? what challenges do you believe should be added to the list why?

In: Civil Engineering

For the project with the five activities given below, you are required to crash the project...

For the project with the five activities given below, you are required to crash the project duration from its original duration to a final duration of 14 days. Assuming a daily indirect cost of $100, what is the total cost of the project with a duration of 14 days.

For the project with the five activities given below, you are required to crash the project

duration from its original duration to a final duration of 14 days. Assuming a daily

indirect cost of $100,

what is the total cost of the project with a duration of 14 days

.

Duration (days)

Cost ($)

Cost slope

Activity

IPA

Normal

Crash

Normal

Crash

A

-

3

1

2,000

5,000

B

A

5

2

3,000

6,000

C

A

3

2

3,000

5,000

D

A

8

3

3,000

8,000

E

B,C,D

5

3

1,000

2,000

Total Direct Cost before Crashing

Draw a Network Diagram (with the Crashing shown) below:

Compression

Cycle

Activity

Compression

days

Amount

Project

Duration

Direct

Cost

Indirect

Cost

Total

Cost

0

-

-

-

1

In: Civil Engineering

I need case studies for case Asbestos encapsulation please

I need case studies for case Asbestos encapsulation please

In: Civil Engineering

Differences and similarities between Chemical and Mineral Admixtures. (CONCRETE)

Differences and similarities between Chemical and Mineral Admixtures. (CONCRETE)

In: Civil Engineering

How have concrete admixtures impacted the concrete construction industry? WRITE IN PARAGRAPHS PLEASE

How have concrete admixtures impacted the concrete construction industry?

WRITE IN PARAGRAPHS PLEASE

In: Civil Engineering

For each of the following, situations, indicate whether Kanban or MRP would be more effective. An...

For each of the following, situations, indicate whether Kanban or MRP would be more effective.

  1. An automobile plant producing three styles of vehicles (0.8 point)
  2. A custom job shop (0.8 point)
  3. A circuit board plant with 40,000 active part numbers (0.8 point)
  4. A circuit board with 12 active part numbers (0.8 point)
  5. A plant with one assembly line where all parts are purchased (0.8 point)

In: Civil Engineering

1. Describe 5 factors affecting the selection of A/Es by owners? (In detail)

1. Describe 5 factors affecting the selection of A/Es by owners? (In detail)

In: Civil Engineering

Engineering Failure Research Paper Write a 2000 word research paper over the Takata Airbag failures. Please...

Engineering Failure Research Paper

  • Write a 2000 word research paper over the Takata Airbag failures. Please make sure to add as much detail as possible.
  • Must be in narrative form (not an outline); use 3rd person
  • Double-spaced, 12 pt. Times New Roman font, with 1” margins
  • Use of figures is highly recommended; provide proper citations
  • Minimum of five different references cited with at least two from non-web based sources.
  • Follow the Publication Manual of the American Psychological Association (APA); see: http://citationmachine.net/

Please type the paper at the following link below:

https://docs.google.com/document/d/1mBBmQ80ZK3zwvPr33qylILwcB3-islvVpoHTEjeaur8/edit?usp=sharing

In: Civil Engineering

Hurricane Harvey caused a net loss of $127 Billion. Let us assume that in any given...

Hurricane Harvey caused a net loss of $127 Billion. Let us assume that in any given year the net loss would be the same for the next 10 years (Jan 1, 2020 to Dec 31, 2029) if a Harvey like hurricane were to recur in Houston and adjoining areas. However, if certain investments are made in 2019 to mitigate risks and enhance resilience in the region, the expected loss can be reduced significantly. Let us assume that scientists, engineers and policy experts have worked together to estimate that if the investments are indeed made in 2019 the net loss would reduce to 10% (i.e., $12.7 Billion expected net loss per year over the period from 2020 to 2029 if a hurricane like Harvey were to recur) but additional investments of $ 6.35 Billion would be needed each year to maintain the investments. At the end of 2029 the salvage value of the investments would be 20% of the cost of the original investment. Other than this salvage value there would be no other costs or gains expected after the 10-year period. According to a Presidential tweet at the time, Harvey was a 500-year event. Assuming this probability assessment to be accurate, what present (2019) investment would be justified from a net present worth perspective? Please feel free to make any appropriate assumptions but try to state them clearly.

In: Civil Engineering