An electrostatic precipitator is to be designed to collect dust from a pulverized coal boiler with an actual flow of 100 m3/s. The effective migration velocity for the flyash is anticipated to be 0.08 m/s. The design gas flow velocity is 1.2 m/s, the plate height is 10 m, and the plate-toplate spacing (2s) is 0.25 m.
a. Determine the number of ducts required to accommodate the flow [-].
b. For an efficiency of 99%, determine the required plate length [m
In: Civil Engineering
Q a) What are the factors to be considered, while making choice between coffer dam and caisson?
b) Describe pile driving by drop hammer method . State and explain dynamic formula for determining load carrying capacity of piles.
In: Civil Engineering
I want to write a paper
Paper is about to introduce a steel building
There is requirements such as
Abstract
Keywords
Engineering background
architecture design
Structure design
conclusion
Reference
Please give me description to each topic what should I include. According to my topic, what kind of information should I input to my paper.
In: Civil Engineering
compare on-site cast and precast concrete framing systems. Specify the advantages and disadvantages of each method.
In: Civil Engineering
In: Civil Engineering
Moisture movement in concrete is one of the factor that influencing shrinkage and creep. Elaborate this effect and how to differentiate between these properties. please i need full answer about how the moisture is a factor of shrinkage and creep . and what is the different between them...in detail
In: Civil Engineering
What is the Terrain Category in the Middle of Brisbane, QLD Australia and Port Headland, WA, Australia? Is it Terrain Category 1, 2, 3 or 4? I need it for my reference in getting the Wind Speed Vsit.
In: Civil Engineering
Thirty-six piles, 0.6 m in diameter, are spread at 2.4 m centres in a 6 x 6 group. The piles extend between depths of 3 m and 18 m in a layer of stiff clay 28 m thick, overlying rock. The undrained shear strength of the clay at a depth of 18 m is 145 KN/m2 and the average value over the pile length is 105 KN/m2. The following parameters have also been determined for the clay: α = 0.4, A = 0.28, Eu = 65 MN/m2 and mv = 0.08 m2/MN. If the pile group carries a load of 21 MN, determine the load factor and the total settlement.
In: Civil Engineering
In: Civil Engineering
Consider a double-pane window of size 48.56×73.55 cm. The window is framed in aluminum. If the maximum and minimum outside temperatures are 30.28 and -32.21 °C, respectively, how much gap do you need to allow between the glass panes and the frame?
In: Civil Engineering
what is the advantage and disadvantage of MR-24 BUTLER ,EPOM, TPO,AND BUR roofing system ?
In: Civil Engineering
In: Civil Engineering
Describe the measurements of discharge at weirs and its potential errors associated with indirect methods weir in real-world application setting
In: Civil Engineering
Q1) The following are four examples of technical engineering knowledge areas that are required to be mastered by an engineer involved in the design of steel bridges: 1……………………………………
2 ……………………… 3 …………………………… 4……………………
a) The degree to which a person is able to achieve objectives is referred to as …………………
b) Accomplishing tasks with optimizing the use of resources is referred to as ………………….
c) . ………………….. may be defined as a mental position with regard to a fact or state; a feeling or emotion towards a fact or state. This represents one category of competencies.
In: Civil Engineering
Use the Hazen-Williams equation and the Manning equation to calculate the flow rate for problem 3.5.7on chapter 3 Hydraulic Engineering Systems Fourth Edition by Robert J. Houghtalen which was solved using the Darcy-Weisbach equation and yielded Q = 78.8 m^3/sec. Compare the results and discuss the differences. Assume minor losses are negligible and verify your results with computer software.
In: Civil Engineering