An oceanic Oil Tanker weighing 63,000 tons with no fuel has 13 separate tanks with dimensions of 110’ x 107’ x 32’. The waterline on the ship has a cross sectional area of 280,000 ft2. The ship can submerge a maximum of 15 feet due to the weight in the tanks, and the cross sectional area of the waterline will remain the same area. What is the maximum number of gallons of Kerosene (S.G. = .87) that the ship can hold, without going over the restriction? a. 20 Million Gallons b. 48 Million Gallons c. 36 Million Gallons d. 62 Million Gallons

In: Civil Engineering

TRP 631: HIGHWAY TRAFFIC OPERATIONS An existing six-lane divided multilane highway with a field-measured free-flow speed...

TRP 631: HIGHWAY TRAFFIC OPERATIONS

An existing six-lane divided multilane highway with a field-measured free-flow speed of 45 mi/h serves a peak-hour volume of 4,000 veh/h with 10% trucks (50% SUT, 50% TT). The PHF is 0.88. The highway has generally rolling terrain. What is the likely level of service of this segment? Good weather, no incidents, no work zones, and regular drivers may be assumed.

In: Civil Engineering

What does the cam shaft and crank shaft position sensor do? And explain how you can...

What does the cam shaft and crank shaft position sensor do? And explain how you can determine if there is failure in these sensors.

In: Civil Engineering

please answer my question in word software not in a Handwritten Question 1 Discuss the ways...

please answer my question in word software not in a Handwritten

Question 1
Discuss the ways in which BIM can facilitate structural analysis.


Compare question (1) using other design software such as Esteem.


In: Civil Engineering

please answer my question in word software writing Question 1 Discuss the ways in which BIM...

please answer my question in word software writing
Question 1
Discuss the ways in which BIM can facilitate structural analysis.



Compare question (1) using other design software such as Esteem.


In: Civil Engineering

What is liquefaction of sand? how can it prevented

What is liquefaction of sand? how can it prevented

In: Civil Engineering

Unlined trapezoidal channel to be excavated in fine sand soil to convey 350 ft3/s. The slope...

Unlined trapezoidal channel to be excavated in fine sand soil to convey 350 ft3/s. The slope is 0.0025. Determine the width of the bottom and the depth of water of the cross section of the channel b and y.

In: Civil Engineering

A 200-acre catchment area contains 50 acres paved surfaces (C = 0.8), 100 acres buildings (C...

A 200-acre catchment area contains 50 acres paved surfaces (C = 0.8), 100 acres buildings (C = 0.7), 40 acres open lawn space (C = 0.15). Determine the peak discharge Qp (cfs) by the Rational Method if the duration of the storm is 50 minutes. Assume 100-year return period storm. Use formulas/graphs from Houston City Manual.

In: Civil Engineering

TRP 631: HIGHWAY TRAFFIC OPERATIONS An older four-lane freeway has the following characteristics: 11 ft lanes...

TRP 631: HIGHWAY TRAFFIC OPERATIONS

An older four-lane freeway has the following characteristics:

  • 11 ft lanes
  • No lateral clearance
  • 4.5 ramps/mile
  • 5% truck( standard mix)
  • Peak-hour factor = 0.90
  • Rolling Terrain

The present peak-hour demand on the facility is 2,100 veh/h, and anticipated growth is expected to be 3% per year. What is the present LOS? What is the expected LOS in 5 years? 10 years? 20 years?. To avoid breakdown (LOS F), when will substantial improvements be needed to this facility, and/or alternative routes created? Good weather, no incidents, no work zones, and regular drivers may be assumed.

In: Civil Engineering

For steel member is subjected to cyclic loads, The experimental results indicated failure at a number...

For steel member is subjected to cyclic loads,

The experimental results indicated failure at a number of cycles of 52 when the maximum stress is 1071 MPa. Also, failure at a number of cycles of 380,000 when the applied maximum stress is 506 MPA.

  1. Find the fatigue equations for stress vs number of cycles using

σ = A NB And σ = A (2N)b

2) Plot on the same diagram both functions

3) Discuss the results of the two plots.

4) Find the number of cycles to failure when the maximum stress is 950 MPa in both functions

In: Civil Engineering

I need a full explanation of - Types of Road maintenance and tools Please include at...

I need a full explanation of - Types of Road maintenance and tools

Please include at least 2 references,thanks.

In: Civil Engineering

2 There are two (2) laboratory tests can be conducted to determine the coefficient of soil...

2 There are two (2) laboratory tests can be conducted to determine the coefficient of soil permeability which is falling head test(for fine grained soil) and constant head test(for coarse grained soil). Based on your understanding about soil permeability, justify the difference of these two tests in details by using your own word. Provide the justification with references and the answers are limited to three pages only.

In: Civil Engineering

1) why is the difference between an avoidable delay and an unavoidable delay important to a...

1) why is the difference between an avoidable delay and an unavoidable delay important to a contractor? 2) What is the difference between a calender day and a working day? 3) Why would it be necessary and desirable to perform resource leveling for a construction schedule? 4) In which parts of a schedule should a contractor share the most detail with an owner? 5) As a contractor, what concern would you have regard cost and productivity if an owner directed you to use overtime to catch up on a scehdule?

In: Civil Engineering

complete research paper (12 pages) with references about application of remote sensing and GIS in groundwater...

complete research paper (12 pages) with references about application of remote sensing and GIS in groundwater prospecting

In: Civil Engineering

1- A 20-cm well penetrates 25 m below the static water table. After 24 hours of...

1- A 20-cm well penetrates 25 m below the static water table. After 24 hours of pumping out at the rate of 800 lpm, the water level in a test well at 80 m from the pumping well is lowered by 0.53 m and in a test well 20 m away 2.11 m. Find the coefficient of transmissibility of the aquifer.

2-What is the nature of ground water flow? State the law governing the flow with limitations, if any.

3-A well penetrates into an unconfined aquifer having a saturated depth of 50 m. The discharge is 250 1pm at 8 m drawdown. What would be the discharge at 10 m drawdown. The radius of influence in both the cases may be taken as same.

4-Describe the method of construction of open wells:
(i) in a soil where a clayey stratum is encountered.
(ii) in rocky sub-strata.

5 -A tubwell penetrates fully an unconfined aquifer. Calculate the discharge from the well in lpm from the following data:

Diameter of the well 30 cm

Drawdown in the well 3 m

Effective length of the strainer under the above drawdown 10 m

Coefficient of permeability of the aquifer 40 m/day

Radius of zero drawdown 300 m

In: Civil Engineering