A water harvesting pond is to be constructed by constructing an embankment across a narrow valley....

A water harvesting pond is to be constructed by constructing an embankment across a narrow valley.

The top width of the embankment is kept at 3.6 m. using the information in the Table Q8, and taking the upstream and downstream side slopes as 3:1 and 2:1 respectively, a settlement allowance of 12.5%:

  1. .       Fill up the table and estimate the earth volume required to construct the dam. Show sample calculations only.
  2. .     Sketch the plan view, longitudinal section and centre cross section of the dam.

Table Q8

Station (m)

Ground elev.

(m)

Fill height

(m)

Distance (m)

End areas

(m2)

Volume (m3)

0+50

35.0

0

+68

32.7

2.3

1+00

25.9

9.1

+37

21.5

13.5

+53

20.0

15.0

+75

19.8

15.2

2+00

19.5

15.5

+19

20.3

14.7

+32

20.3

14.7

+36

18.8

16.2

+40

18.2

16.8

+43

18.5

16.5

+46

19.6

15.4

+59

19.8

15.2

3+00

20.8

14.2

+35

27.7

7.3

+60

31.6

3.4

3+96

35.0

0

Solutions

Expert Solution

End area = {(3.6+3.6+2d+3d)÷2 }×d

Here, d = fill height

Volume = {(end area 1 + end area 2 )÷2}× distance

here, settlement allowance means we have to increase the fill height by 12.5% which will fill the requirements even if there a settlement.


Related Solutions

A road embankment will be constructed using clayey sand from a local borrow excavation. The embankment...
A road embankment will be constructed using clayey sand from a local borrow excavation. The embankment has a volume of 100,000 cubic meters. Specifications require the soil to be compacted to at least 95 percent of the maximum dry density obtained in a Standard Proctor test (i.e., relative compaction, RC greater than or = 95%). It is estimated that the as-constructed embankment will be at an average RC of 97% since the contractor must meet or exceed this specification. Standard...
Need a good explanationIf a new railroad embankment is to be constructed in an area...
If a new railroad embankment is to be constructed in an area that restricts how wide its base may be, name some of the design alternatives you would consider to limit the embankment width at its base.
Harvesting Fish. A fish farmer has 5000 catfish in a pond. The number of catfish increases...
Harvesting Fish. A fish farmer has 5000 catfish in a pond. The number of catfish increases by 8% per month and the farmer harvests 420 catfish per month. a) (4 points) Find a recursive equation for the catfish population Pn for each month. b) (4 points) Solve the recursive equation to find an explicit equation for the catfish population. c) (3 points) How many catfish are in the pond after six months? d) (3 points) Is harvesting 420 catfish per...
A pond 2 m in diameter is to be filled with water by a flow that...
A pond 2 m in diameter is to be filled with water by a flow that varies linearly with the level of the pond so that it reaches the maximum value of 217 lt/h when the pond is empty and is zero when the level reaches 2 m. Calculate: a) Time it takes to reach the level of 1 m. b) Time it takes to fill up completely. Discuss this last result.
Our neighbor to the north across the pond, Canada, has recently experienced a reduction of the...
Our neighbor to the north across the pond, Canada, has recently experienced a reduction of the value of the Canadian dollar to the extent that in relation to the U.S. dollar the Canadian dollar is worth about 80 cents to $1.00 U.S. What caused this reduction in value? The number of cars with Canadian plates at the Galleria and Niagara outlet mall has greatly been reduced.. Why don't Canadian shoppers come over as much?
A new, wide highway embankment is planned across a relatively recent deposit of doubly-drained, saturated clay...
A new, wide highway embankment is planned across a relatively recent deposit of doubly-drained, saturated clay soil with cv = 5E-8 m2/sec. The settlement analysis of the 10 m thick clay layer yielded an estimated consolidation settlement of 800 mm for the new embankment loading. Determine and plot the settlement of the clay layer (as measured at the ground surface) at 0, 0.49, 3.12, 6.39, 13.44, and 18.44 years.
Green Valley Water and Granite Slope Water are sellers of spring water in the Republic of...
Green Valley Water and Granite Slope Water are sellers of spring water in the Republic of Bogritania. Like mineral water sellers in many simple examples, they have no costs so their payoffs are the revenues they obtain from selling water. The price of mineral water in Bogritania is 1,000-qv-qs , where qv is the quantity sold by Green Valley and qs is the quantity sold by Granite Slope. As a result: Proposition A: Each firm's best response is to sell...
1. Explain Hines view that the CF is a socially constructed and socially constructing document forming...
1. Explain Hines view that the CF is a socially constructed and socially constructing document forming a body of professional knowledge essential to the existence of the Accounting Profession. (ii) Could the two views be aligned based on the notion that accounting standards do change?b) Hines arguments is that a CF is a defensive document produced by the Accounting Profession in reaction to financial crises when it becomes threatened by government regulation. Explain whether you agree with this view.
a)(i) Explain Hines view that the CF is a socially constructed and socially constructing document forming...
a)(i) Explain Hines view that the CF is a socially constructed and socially constructing document forming a body of professional knowledge essential to the existence of the Accounting Profession. (ii) Could the two views be aligned based on the notion that accounting standards do change?b) Hines arguments is that a CF is a defensive document produced by the Accounting Profession in reaction to financial crises when it becomes threatened by government regulation. Explain whether you agree with this view.
Can you please suggest me a literature on "Conservation or harvesting of water in a hilly...
Can you please suggest me a literature on "Conservation or harvesting of water in a hilly region where there is no access to ground water due to the altitude". And a suggested list of technology to solve the above problems.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT