In: Civil Engineering
Chapter 9: Concrete Form Construction
Matching
Match terms to their definitions. Write the corresponding letters on the blanks. Not all terms will be used.
1. heavy timer or beam used to support vertical loads | a. buck |
2. the quality of being resistant to breaking under a pulling force | b. compressive strength |
3. column built within and usually projecting from a wall to reinforce the wall | c. girder |
d. microsilica | |
4. a rough frame used to form openings in poured concrete walls | e. pilaster |
5. vertical framing member in a wall running between plates | f. Portland cement |
6. in stairs, the vertical distance of the flight; in roofs, the vertical distance from plate to ridge | g. reinforcing rods |
7. a length of lumber or material applied over a joint to stiffen and strengthen it | h. rise |
i. run | |
8. a strip of wood used to keep other pieces a desired distance apart | j. scab |
k. spreader | |
9. the quality of being resistant to crushing | l. stud |
m. tensile strength |
True/False
Write True or False before the statement.
1. Footings are the first part of a building to be installed.
2. Building forms for slabs, walks, and driveways are exactly the same as building continuous footing forms.
3. A vapor retarder provides a barrier to soil gases, such as radon.
4. All wall form systems use similar components to make them perform as expected.
5. Outside corners of concrete-forming systems are created by attaching panels to angle irons with wedges.
6. Walers are difficult to install on forming systems.
7. Riser form boards for stairs are beveled on the top edge.
8. Water should be added to concrete so that it flows into forms without working it.
9. A slump test shows the wetness or dryness of a concrete mix.
10. Curing agents placed on green concrete contain harmful chemicals.
Multiple Choice
Choose the best answer. Write the corresponding letter on the blank.
1. A combined slab foundation/footing is called a slab.
2. When applying a vapor barrier of heavy plastic film under concrete, it should be lapped and sealed.
3. is the only insulation recommended for ground contact and can be placed between concrete and the subsoil.
4. The snap ties run through form boards and are wedged against additional form supports called .
5. Concrete-forming system panels are tied together with wedges.
6. The width of a step is called the .
7. Which of the following statements about the placement of concrete is true?
8. Concrete must be protected from freezing for after being placed.
9. If moist-cured for seven days, concrete strength will be full strength.
Terms
Read the descriptions of terms associated with concrete construction. Write the correct term on the corresponding blanks.
1. Provide a base on which to spread the load of a structure over a wider area of the soil
2. Provides a lock between the footing and the foundation wall
3. Hold wall forms together at the desired distance apart; support both sides against lateral pressure of concrete
4. Used to reinforce concrete floor slabs resting on the ground, driveways, and walks
5. Performed by inspectors on a job to determine the consistency of the concrete
Put in Order
Put in order the following steps for constructing footing forms. Write the corresponding numbers on the blanks.
A. Fasten the spreaders across the form at intervals necessary to hold the form the correct distance apart.
B. Stretch lines back on the batter boards in line with the outside edge of the footing.
C. Erect the inside forms in a manner similar to the outside forms.
D. Drive corner stakes to the correct elevation and stretch lines between the stakes, if desired.
Identify
Identify the following items use with concrete construction. Write the correct name on the line next to the item.
1.
Courtesy of Dayton/Richmond Concrete Accessories.
2.
Courtesy of Dayton/Richmond Concrete Accessories.
3.
© 2016 Cengage Learning®
4.
© 2016 Cengage Learning®
Procedures
Read the following procedures. Determine what procedure is being described and write the name of the procedure on the blank.
Procedure 1:
Procedure 2:
Calculations
Use the information provided to complete your calculations. Write answers on the lines provided within the exercises.
Estimating the Amount of Concrete for a Slab
Estimate the cubic yards of concrete for the slab shown below. The depth of the slab is 6 inches. Use the space provided for your calculations.
© 2016 Cengage Learning®
Total cubic yards:
Estimating the Amount of Concrete for a Footer
Estimate the cubic yards of concrete for a footer. Use the space provided for your calculations.
© 2016 Cengage Learning®
Total cubic yards:
Estimating Concrete Materials
Estimate the materials for a complete poured concrete foundation for a rectangular building 32' × 60'. Poured walls are 8 feet tall and 8 inches thick. Form boards are 12 feet long, and rebar is 20 feet long.
Estimate the materials for a foundation of a rectangular 30' × 56' building. Walls 8' tall and 10" thick, the footing is 2' wide by 12" thick, and slab is 5" thick. | |||
Item | Formula | Waste factor | Example |
Footing form boards | footing PERM × 2 sides ÷ 12' = NUM of 12' boards | 172' × 2 ÷ 12' = 28.6 ⇒ 29 boards | |
Slab form boards | slab PERM ÷ board LEN = NUM of boards | 172' ÷ 12' = 14.3 ⇒ 15 boards | |
Wall forms | wall PERM × 2 sides ÷ 2' WID of form = NUM of form panels | 172 × 2 ÷ 2' = 172 panels | |
Rebar footing | PERM × 2 ÷ 20' rebar LEN × waste = NUM of bars. | Add 10% for bar overlap | 172 × 2 ÷ 20' × 1.10 = 18.9 ⇒ 19 rebars |
Rebar walls 2' × 2' grid horizontal | PERM × [wall HGT ÷ 2 FT grid − 1] ÷ 20' rebar LEN × waste = NUM of 20' HOR bars | Add 10% for bar overlap | [8' ÷ 2 − 1] × 172' ÷ 20 × 1.10 = 28.3 ⇒ 29 rebars |
Rebar walls 2' × 2' grid vertical | PERM ÷ 2 ft grid + 1 per corner = NUM of VERT bars | 172 ÷ 2 + 4 = 90 vertical rebars | |
Concrete footing (Be sure all measurements are in terms of feet) | footing width × footing depth × PERM ÷ 27 = CY | Add 5% | 2' × 1' × 172' ÷ 27 × 1.05 5 5.6 1 5 3/4 CY |
Concrete slab | slab WID × slab LEN × slab thickness ÷ 27 = CY concrete | Add 10% | 30' × 56' × 5"/12 ÷ 27 × 1.10 = 28.5 ⇒ 28 3/4 CY |
Concrete wall | PERM × wall HGT × wall thickness ÷ 27 = CY | Add 5% | 172' × 8 × 10"/12 ÷ 27 × 1.05 = 44.5 ⇒ 44 3/4 CY |
© 2016 Cengage Learning®
Footing form boards | |
Slab form boards | |
Wall forms | |
Rebar footing | |
Rebar walls 2 × 2 grid horizontal | |
Rebar walls 2 × 2 grid vertical | |
Concrete footings | |
Concrete slab | |
Concrete walls |
File Upload
Maximum upload file size is 10MB
Matching
1. Heavy timer or beam used to support
vertical loads - Girder
2. The quality of being resistant to breaking under a pulling force
- Tensile Strength
3. Column built within and usually projecting from a wall to
reinforce the wall - Pilaster
4. A rough frame used to form openings in poured concrete walls -
Buck
5. Vertical framing member in a wall running between plates -
Stud
6. In stairs, the vertical distance of the flight; in roofs, the
vertical distance from plate to ridge - Rise
7. A length of lumber or material applied over a joint to stiffen
and strengthen it - Scab
8. A strip of wood used to keep other pieces a desired distance
apart - Spreader
9. A slump test shows the wetness or dryness of a concrete mix.
-
True/False
Letter on the blank
1. A combined slab foundation/footing
is called a slab. - monolithic
2. When applying a vapor barrier of heavy plastic film under
concrete, it should be lapped and sealed - at least 4 inches
3. is the only insulation recommended for ground contact and can be
placed between concrete and the subsoil- Extruded polystyrene
4. The snap ties run through form boards and are wedged against
additional form supports called . - walers
5. Concrete-forming system panels are tied together with wedges. -
wood or steel
6. The width of a step is called the - Tread
7. Which of the following statements about the placement of
concrete is true? - Working it by hand will cause voids or
honeycombs.
8. Concrete must be protected from freezing for after being placed.
- at least four days
9. If moist-cured for seven days, concrete strength will be full
strength. -up to about 60 percent of
Correct Sentence
1. The Footing for a Foundation
Provides a base on which to spread the load of a structure over a
wider area of the soil .
2. The Purpose of a keyway is to Provides a lock between the
footing and the foundation wall
3.Snap ties hold wall forms together at the desired distance apart;
support both sides against lateral pressure of concrete.
4. Welded wire mesh is used to reinforce concrete floor slabs
resting on the ground, driveways, and walks.
5. Slump tests are Performed by inspectors on a job to determine
the consistency of the concrete.
Correct Order