In: Finance
1. Compute the IRR for Project X and note whether the firm should accept or reject the project with the cash flows shown as follows if the appropriate cost of capital is 9 percent.
Time: |
0 |
1 |
2 |
3 |
4 |
5 |
Cash flow: |
?1,000 |
?75 |
100 |
100 |
0 |
2,000 |
A. 9 PERCENT, ACCEPT
B. 9 PERCENT, REJECT
C. 16.61 PERCENT, ACCEPT
D. 16.61 PERCENT, REJECT
The Answer is “C. 16.61 PERCENT, ACCEPT”
Step – 1, Firstly calculate NPV at Say 16%
Net Present Value [NPV] = Present Value of Annual cash flows – Initial Investment
= [ (-$75 x 0.862068) + (100 x 0.743162) + (100 x 0.640657) + ( 0 x 0.552291) + (2,000 x 0.4761130) ] – $1,000
= $1,025 – 1,000
= $25
Step – 2, NPV at 16% is positive, Calculate the NPV again at a higher rate, Say 17%
= [ (-$75 x 0.854700) + (100 x 0.730513) + (100 x 0.624370) + ( 0 x 0.533650) + (2,000 x 0.456111) ] – $1,000
= $983 – 1,000
= - $17
Therefore IRR = R1 + NPV1(R2-R1)
NPV1-NPV2
= 16% + $25 (17% - 16%)
$25 - ( - $17)
IRR = 16% + 0.61% = 16.61%
DECISION
“The Internal Rate of Return [IRR] of the Project is 16.61% which is greater than the required rate of return of 9%. Therefore, the project proposal should be accepted”