Question

In: Finance

1.      Compute the IRR for Project X and note whether the firm should accept or reject...

1.      Compute the IRR for Project X and note whether the firm should accept or reject the project with the cash flows shown as follows if the appropriate cost of capital is 9 percent.

Time:

0

1

2

3

4

5

Cash flow:

?1,000

?75

100

100

0

2,000

A.      9 PERCENT, ACCEPT

B.       9 PERCENT, REJECT

C.       16.61 PERCENT, ACCEPT

D.      16.61 PERCENT, REJECT

Solutions

Expert Solution

The Answer is “C. 16.61 PERCENT, ACCEPT”

Step – 1, Firstly calculate NPV at Say 16%

Net Present Value [NPV] = Present Value of Annual cash flows – Initial Investment

= [ (-$75 x 0.862068) + (100 x 0.743162) + (100 x 0.640657) + ( 0 x 0.552291) + (2,000 x 0.4761130) ] – $1,000

= $1,025 – 1,000

= $25

Step – 2, NPV at 16% is positive, Calculate the NPV again at a higher rate, Say 17%

= [ (-$75 x 0.854700) + (100 x 0.730513) + (100 x 0.624370) + ( 0 x 0.533650) + (2,000 x 0.456111) ] – $1,000

= $983 – 1,000

= - $17

Therefore IRR = R1 + NPV1(R2-R1)

                                   NPV1-NPV2

= 16% + $25 (17% - 16%)

             $25 - ( - $17)

IRR = 16% + 0.61% = 16.61%

DECISION

“The Internal Rate of Return [IRR] of the Project is 16.61% which is greater than the required rate of return of 9%. Therefore, the project proposal should be accepted”


Related Solutions

Compute the PI statistic for Project X and note whether the firm should accept or reject...
Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown as follows if the appropriate cost of capital is 10%. Time 0 1 2 3 4 5 Cash Flow -250 75 0 100 75 50 a) 2.41, accept b) 0.023, reject c) 0.90, reject d) 1.97, accept
Compute the PI statistic for Project X and note whether the firm should accept or reject...
Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 8 percent. Time: 0, 1, 2, 3, 4, 5 Cash Flow: -82, -82, 0, 117, 92, 67 Time: 0 1 2 3 4 5 Cash flow: -82 -82 0 117 92 67 Multiple Choice 48.17 percent, reject 8.00 percent, accept 58.74 percent, accept 47.21 percent, reject All information is...
Compute the PI statistic for Project X and note whether the firm should accept or reject...
Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 10 percent.   Time: 0 1 2 3 4 5   Cash flow: -75 -75 0 100 75 50
Compute the PI statistic for Project X and note whether the firm should accept or reject...
Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 10 percent.   Time: 0 1 2 3 4 5   Cash flow: -80 -80 0 115 90 65   
Compute the PI statistic for Project X and note whether the firm should accept or reject...
Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 6 percent. Time: 0 1 2 3 4 5 Cash flow:-84 -84 0 109 84 59
Compute the Discounted Payback statistic for Project X and recommend whether the firm should accept or...
Compute the Discounted Payback statistic for Project X and recommend whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 14 percent and the maximum allowable discounted payback is 3 years. Time: 0 1 2 3 4 5 Cash flow: -960 460 520 440 340 190 Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows...
Compute the Discounted Payback statistic for Project X and recommend whether the firm should accept or...
Compute the Discounted Payback statistic for Project X and recommend whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 12 percent and the maximum allowable discounted payback is 3 years.   Time: 0 1 2 3 4 5   Cash flow: -980 380 600 520 420 270 Multiple Choice 2.78 years, accept 3.44 years, reject 2.44 years, accept 4.78 years, reject
Compute the payback statistics (Not discounted) for Project X and recommend whether the firm should accept...
Compute the payback statistics (Not discounted) for Project X and recommend whether the firm should accept or reject the project with the cash flows shown as follows if the appropriare cost of capital is 10 percent and the maximum allowable payback is five years. Time:                  0        1      2        3         4       5 Cash flow:        -75   -75     0     100     75     50 a. 3.67 years, accept b. 4.67 years, accept c. 3.67 years, reject d. 4.67 years, reject
You are trying to decide whether to accept or reject a project. The project will generate...
You are trying to decide whether to accept or reject a project. The project will generate a cash flow of $15,000 in year one; $25,000 in year two; $20,000 in year three; and $4,000 in year four. The project costs $40,000 initially. The firm has a weighted average cost of capital of 8%. Your firm generally accepts projects that payback in three years or less. What is the discounted payback of the project? Should you accept or reject the project?
Determine whether management should accept or reject the new business.
Question Goshford Company produces a single product and has capacity to produce 100,000 units per month. Costs to produce its current sales of 80,000 units follow. The regular selling price of the product is $100 per unit. Management is approached by a new customer who wants to purchase 20,000 units of the product for $75 per unit. If the order is accepted, there will be no additional fixed manufacturing overhead and no additional fixed selling and administrative expenses. The customer...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT