Question

In: Finance

Compute the PI statistic for Project X and note whether the firm should accept or reject...

Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 10 percent.

  Time: 0 1 2 3 4 5
  Cash flow: -80 -80 0 115 90 65

  

Solutions

Expert Solution

Please give a like to my answer if you found it helpful. and in case if you have any query feel free to comment. Thank you


Related Solutions

Compute the PI statistic for Project X and note whether the firm should accept or reject...
Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown as follows if the appropriate cost of capital is 10%. Time 0 1 2 3 4 5 Cash Flow -250 75 0 100 75 50 a) 2.41, accept b) 0.023, reject c) 0.90, reject d) 1.97, accept
Compute the PI statistic for Project X and note whether the firm should accept or reject...
Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 8 percent. Time: 0, 1, 2, 3, 4, 5 Cash Flow: -82, -82, 0, 117, 92, 67 Time: 0 1 2 3 4 5 Cash flow: -82 -82 0 117 92 67 Multiple Choice 48.17 percent, reject 8.00 percent, accept 58.74 percent, accept 47.21 percent, reject All information is...
Compute the PI statistic for Project X and note whether the firm should accept or reject...
Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 10 percent.   Time: 0 1 2 3 4 5   Cash flow: -75 -75 0 100 75 50
Compute the PI statistic for Project X and note whether the firm should accept or reject...
Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 6 percent. Time: 0 1 2 3 4 5 Cash flow:-84 -84 0 109 84 59
1.      Compute the IRR for Project X and note whether the firm should accept or reject...
1.      Compute the IRR for Project X and note whether the firm should accept or reject the project with the cash flows shown as follows if the appropriate cost of capital is 9 percent. Time: 0 1 2 3 4 5 Cash flow: ?1,000 ?75 100 100 0 2,000 A.      9 PERCENT, ACCEPT B.       9 PERCENT, REJECT C.       16.61 PERCENT, ACCEPT D.      16.61 PERCENT, REJECT
Compute the Discounted Payback statistic for Project X and recommend whether the firm should accept or...
Compute the Discounted Payback statistic for Project X and recommend whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 14 percent and the maximum allowable discounted payback is 3 years. Time: 0 1 2 3 4 5 Cash flow: -960 460 520 440 340 190 Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows...
Compute the Discounted Payback statistic for Project X and recommend whether the firm should accept or...
Compute the Discounted Payback statistic for Project X and recommend whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 12 percent and the maximum allowable discounted payback is 3 years.   Time: 0 1 2 3 4 5   Cash flow: -980 380 600 520 420 270 Multiple Choice 2.78 years, accept 3.44 years, reject 2.44 years, accept 4.78 years, reject
Compute the payback statistics (Not discounted) for Project X and recommend whether the firm should accept...
Compute the payback statistics (Not discounted) for Project X and recommend whether the firm should accept or reject the project with the cash flows shown as follows if the appropriare cost of capital is 10 percent and the maximum allowable payback is five years. Time:                  0        1      2        3         4       5 Cash flow:        -75   -75     0     100     75     50 a. 3.67 years, accept b. 4.67 years, accept c. 3.67 years, reject d. 4.67 years, reject
Compute the Profitability Index statistic for 345 Rayzor Sharp Project and note whether the firm should...
Compute the Profitability Index statistic for 345 Rayzor Sharp Project and note whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 10 percent. CF0 = -1000 CF1 = 500 CF2 = 480 CF3 = 400 CF4 = 300 CF5 = 150 0.19, reject 0.45, reject 1.19, accept 1.45, accept
Compute the Profitability Index statistic for 345 Rayzor Sharp Project and note whether the firm should...
Compute the Profitability Index statistic for 345 Rayzor Sharp Project and note whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 10 percent. CF0 = -1000 CF1 = 500 CF2 = 480 CF3 = 400 CF4 = 300 CF5 = 150 0.19, reject 0.45, reject 1.19, accept 1.45, accept
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT