Question

In: Operations Management

The total plan for the project involved 1000 staff-days of value (the Budgeted at Completion or...

The total plan for the project involved 1000 staff-days of value (the Budgeted at Completion or BAC) accumulated over 10 months with a staff of 5 full-time people. At the 4-month mark, with no open tasks, the total accumulated earned value is 320 staff-days. The plan at this point is for 340 staff-days to have been earned. Alas, the actual amount spent (because extra staff time has already been spent on this project) is 370 staff-days.
A summary of the facts:
1. Original project cost: 1000 staff-days
2. Original project schedule: 10 months
3. Planned value: 340 staff-days at 4 months
4. Actual cost: 370 staff-days
5. Earned value: 320 staff-days
6. Current monthly staff: 5 people

5. What is the projected total cost Estimate at Completion (EAC)?
a. If we assume cost variance was atypical (and the rest of the project will go as originally planned)?
b. If we assume cost variance was typical (and the rest of the project will have a proportional variance)?
c. If we assume we can re-plan the remaining project and make a whole new estimate?
6. What is the projected schedule Estimate at Completion (EAC)?
a. If we assume schedule variance was atypical (and the rest of the project will be as originally planned)?
b. If we assume schedule variance was typical (and the rest of the project will have a proportional variance)?
c. If we assume we can re-plan the remaining project and make a whole new estimate?
7. What are the remaining cost-to-complete and schedule-to-complete figures for each of a, b, and c?
8. What is the intensity of work required to finish the work with the available funds? (These funds can be defined as either the original Budget at Completion (BAC) or the current Cost Estimate at Completion (EAC).)

Solutions

Expert Solution

Original project cost: 1000 staff-days

Original project schedule: 10 months

Planned value: 340 staff-days at 4 months

Actual cost: 370 staff-days at 4 months

Earned value: 320 staff-days at 4 months

Current monthly staff: 5 people

5. What is the projected total cost Estimate at Completion (EAC)?

a. If we assume cost variance was atypical (and the rest of the project will go as originally planned)?

Since we assume that the rest of the project will go as planned, the cost variance at the completion of the project would be the cost variation at the end of the 4 months:

· Cost variation at the end of 4 months = Total Actual cost at the end of 4 months – Earned value at the end of 4 months

· Cost variation at the end of 4 months = 370 – 320 = 50 staff-days

· Projected Total cost estimate at completion = Original project cost + cost variation at the end of 4 months

= 1000 staff-days + 50 staff-days

=1050 staff-days

b. If we assume cost variance was typical (and the rest of the project will have a proportional variance)?

If we assume that the projected total cost variance at completion is proportional to the 4-month period, then we would have an additional cost of 50 staff-days for every 320 staff-days earned.

For a project requiring 1000 staff-days, the expected cost variance would be = (50/320) *1000

= 156.25 staff-days

Projected Total cost estimate at completion = Original project cost + expected cost variance

                                                                                = 1000 staff-days + 156.25 staff-days

                                                                                = 1156.25 (or 1157 staff-days rounded up)

c. If we assume we can re-plan the remaining project and make a whole new estimate?

If we assume that we can re-plan the remaining project to complete it within the next 6 months and 660 staff-days as planned, the cost variance would be

=              50 staff-days (at the end of 4 months) + (50/320) *660 staff-days

=              50 staff-days + 103.125 staff-days

=              153.125 staff-days

The new estimate would be

= Original project cost + cost variance for the remaining period

= 1000 staff-days + 153.125 staff-days

= 1153.125 staff-days (or 1154 staff-days rounded up)

6. What is the projected schedule Estimate at Completion (EAC)?

a. If we assume schedule variance was atypical (and the rest of the project will be as originally planned)?

If we assume schedule variance was atypical, the time variation would be the extra time needed to complete the 20 staff-days (340 - 320) we are behind on after the 4-month period. Since the original estimate is 340 staff-days in 4 months,

Time variation = (20 staff-days/340 staff-days) *4 months = 0.235 months

Project schedule estimate at completion = original project schedule + time variation

                                                                = 10 + 0.235 months = 10.235 months


Related Solutions

A project is represented by the activity duration (in days, estimated at 90% likelihood of completion)...
A project is represented by the activity duration (in days, estimated at 90% likelihood of completion) and precedence requirements shown in the table. How many feeder buffers are needed if this project is managed using critical chain methodology? Activity Predecessor Length Activity Predecessor Length A -- 18 E C, D 13 B -- 16 F C 9 C A 22 G E, F 15 D B 14 ​ ​ ​ Options: 0 1 2 3
Find the future value of $20000 CD for 1000 days at a 6.25% effective rate. Answer...
Find the future value of $20000 CD for 1000 days at a 6.25% effective rate. Answer is $23613.70 but I don’t know how to get there. Effective rate=(1- r/c)^c -1
The following table represents a plan for a project: PREDECESSOR JOB(S) TIMES (DAYS) JOB NO. a...
The following table represents a plan for a project: PREDECESSOR JOB(S) TIMES (DAYS) JOB NO. a m b 1 – 2 4 6 2 1 3 3 15 3 1 3 4 11 4 1 1 2 9 5 2 2 6 7 6 3 3 7 8 7 4 4 6 8 8 5,6 2 3 4 9 8 1 4 7 10 7 3 4 5 11 9,10 5 6 7    b. Indicate the critical path. 1-2-5-8-9-11...
A project earns $10,000 a year for five years. The present total value of the project...
A project earns $10,000 a year for five years. The present total value of the project is (using a discount rate of 5.75%): a) $50,000 b) more than $50,000 c) less than $50,000 The NPV of a project is $1,012, using a discount rate of 9.75% p.a. The rate of return on this project is: a) 9.75% b) more than 9.75% c) less than 9.75% The NPV of a project is 0, using a discount rate of 10%. The rate...
Our Minor Project requires you to create a savings and investing plan to reach a total...
Our Minor Project requires you to create a savings and investing plan to reach a total savings of $1,000,000. The objective is to accumulate $1,000,000 in savings, in 30 years from today. What amount of money must be set aside each month, to reach our goal, assuming that the money is not invested and no interest is earned? Assume that the money is placed in a checking account that pays a 2% interest rate. The interest is compounded annually. What...
Our Minor Project requires you to create a savings and investing plan to reach a total...
Our Minor Project requires you to create a savings and investing plan to reach a total savings of $1,000,000. The objective is to accumulate $1,000,000 in savings, in 30 years from today. What amount of money must be set aside each month, to reach our goal, assuming that the money is not invested and no interest is earned? Please, show your calculations and include your results in a table, for ease of comparison. Based on the above calculations, how difficult...
1. What is value-weighted selection? 2. Give the steps involved in an attributes sampling plan. 3....
1. What is value-weighted selection? 2. Give the steps involved in an attributes sampling plan. 3. Give at least three determinants of the sample size for tests of controls. Relate each determinant to sample size. 4. Give the steps involved in a variables sampling plan. 5. Give at least three determinants of the sample size for substantive tests. Relate each determinant to sample size.
If a 91-day T-Bill (bill-A) with face value Rs.1000, issued exactly 10 days ago, is trading...
If a 91-day T-Bill (bill-A) with face value Rs.1000, issued exactly 10 days ago, is trading at Rs.988.40 and a T-Bill (bill-B) issued today is trading at Rs.987.00. (Assume actual/360 day-counting convention) Find the yields of bill-A and bill-B. Which one shall you buy? Cite reason.
Project A has a total present value of future cash flows of $98,200 and a cost...
Project A has a total present value of future cash flows of $98,200 and a cost of $102,000. Project B has a total present value of future cash flows of $386,911 and a cost of $287,211. Project C has a total present value of future cash flows of $784,000 and a cost of $668,000. Project D has a total present value of future cash flows of $119,865 and a cost of $98,770. Which of these projects has the highest Profitability...
Redmond Company issued 4000 of its $1000 par value bonds for $1500, providing total cash proceeds...
Redmond Company issued 4000 of its $1000 par value bonds for $1500, providing total cash proceeds of $6,000,000. There are no bond issue costs. The market price of Redmond's common shares on the date that the bonds were issued was $55 per share. The bonds were sold with 140,000 warrants to acquire 140,000 shares of the company's $5 par value common stock for $65 per share. That is, each bond carries 35 warrants. Redmond has existing bonds outstanding that currently...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT