Question

In: Finance

The project is estimated to be of 10 years duration. It involves setting up new machinery...

The project is estimated to be of 10 years duration. It involves setting up new machinery with an estimated cost of as much as Thai baht (THB) 375 million, including installation. This amount could be depreciated using the straight-line method (SLM) over a period of 10 years with a resale value of THB 13.5 million. The project would require an initial working capital of THB 15.5 million. With the planned new capacity, the company would be able to produce 200,000 pieces of shirts each year for the next 10 years. In terms of pricing, each shirt can initially be sold at THB 900 a piece, which takes into account the target segment and competitor pricing. The project proposal incorporates an annual increase of 3% in the price of the shirt to compensate for inflationary impact.

With regards to the raw material costs and other expenses, the project estimated the following details: Raw material cost for manufacturing shirts at THB 325 per shirt, slated to rise by 2.5% per annum on account of inflation. Other direct manufacturing costs at THB 55 per shirt with an annual increase of 2.5% per annum on account of inflation. Selling, general, and administrative expenses (including employee expenses) at THB 24 million per annum, expected to increase by 6% each year. Depreciation expense on the basis of SLM. Tax rate was assumed to be 30%.

For funding of the expansion project, the promoters agreed to infuse 50% in the form of equity with the rest (50%) being financed from issue of new debt. Based on the current credit position and market scenario, new debt can be raised by the company at 12% per annum. Cost of equity was assumed to be 15%. The requisite discounting rate or weighted average cost of capital (WACC) for NPV and IRR calculations can now be calculated with the help of the above assumptions.

Demand Scenario Although the project proposal estimates maximum annual production of 240,000 shirts, Saurabh decided to do capital budgeting analysis under two demand scenarios: Optimistic and Expected.

The likely annual demand estimated under each scenario is as follows:

Annual demand
Optimistic scenario 200,000
Expected scenario 150,000

A. On the basis of the financial information given in the case, calculate the after-tax operating cash flows, NPV, and IRR under the Optimistic and Expected scenarios. Clearly specify the calculations required for the same.

B. Based on your analysis, as Boon Mee, what recommendation would you make on whether the company should undertake the project or not? Clearly specify the decision based on both the NPV technique as well as the IRR criterion.

Solutions

Expert Solution

Cost of Production :

Fixed Cost of Plant and installation = 375000000

Resale value after 10 years = 13500000

Depreciation Rate using straight line method

= (Initial cost - Resale value)/ Number of useful years

= (375000000-13500000)/10 = 36150000 approx 9.64%

Working capital requirement = 15500000

Annual Production of Shirt 200000

Revenue Per Year (Optimistic Case)

200000*900 = 180000000

Variable Cost of Production:

Raw Material 325

other direct costs 55

Selling Distribution and Administration Cost:

24000000

Calculation of weighted average cost of capital:

K = Cost of Equity * Weightage of Equity + Cost of Debt * Weightage of Debt

= 0.15* 0.5 + 0.12 * 0.5

= 13.5%

Below is the worksheet image of calculations done using the data given in the question

Operating Profit in Best Case : 257969028

Operating Profit in Expected Case : 45861807

Company Should take the project as in best case scenario it would make a profit of 34844004


Related Solutions

You are advising an entrepreneur who is considering investing in a project that involves setting up...
You are advising an entrepreneur who is considering investing in a project that involves setting up a coffee shop and selling it at the end of the year. The project requires an initial investment of £800,000 today (at date 0) and is expected to generate a single cash flow at the end of the year (at date 1). The size of the cash flow at date 1 depends on the state of the economy, and the entrepreneur expects the cash...
Temporary Housing Services Incorporated (THSI) is considering a project that involves setting up a temporary housing...
Temporary Housing Services Incorporated (THSI) is considering a project that involves setting up a temporary housing facility in an area recently damaged by a hurricane. THSI will lease space in this facility to various agencies and groups providing relief services to the area. THSI estimates that this project will initially cost $5.23 million to setup and will generate $20 million in revenues during its first and only year in operation (paid in one year). Operating expenses are expected to total...
Temporary Housing Services Incorporated (THSI) is considering a project that involves setting up a temporary housing...
Temporary Housing Services Incorporated (THSI) is considering a project that involves setting up a temporary housing facility in an area recently damaged by a hurricane. THSI will lease space in this facility to various agencies and groups providing relief services to the area. THSI estimates that this project will initially cost $5.64 million to setup and will generate $20 million in revenues during its first and only year in operation (paid in one year). Operating expenses are expected to total...
Consider the following probability distribution of returns estimated for a proposed project that involves a new...
Consider the following probability distribution of returns estimated for a proposed project that involves a new ultrasound machine: State of the Economy Probability of Occurrence Rate of Return Very poor 0.10 -10.0% Poor 0.20 -2.0% Average 0.40 14.0% Good 0.20 22.0% Very good 0.10 34.0% a. What is the expected rate of return on the project? b. What is the project’s standard deviation of returns? c. What is the project’s coefficient of variation (CV) of returns? d. What type of...
Zeynab Inc. is considering a new 5-year expansion project that consists of setting up a new...
Zeynab Inc. is considering a new 5-year expansion project that consists of setting up a new manufacturing plant. The company bought a land 3 years ago for $1.1 million but did not use it. The company wants to build its new manufacturing plant on this land; the plant will cost $1.9 million to build. If the land was sold today, the company would net $1.2 million. Assume a straight-line depreciation (of the initial investment in fixed assets). This project is...
The average duration of the loans is 10 years. The average duration of the deposits is...
The average duration of the loans is 10 years. The average duration of the deposits is 3 years. Consumer Loans $50 million Deposits $235 million Commercial Loans $200 million Equity $15 million Total Assets $250 million Total Liabilities & Equity $250 million The bank’s manager expects a 1 percent increase in interest rates from the current rates of 10 percent. Given such expectations, 1) what is the number of T-bond futures contracts necessary to hedge the balance sheet if the...
Klingon Cruisers, Inc., purchased new cloaking machinery five years ago for $10 million. The machinery can...
Klingon Cruisers, Inc., purchased new cloaking machinery five years ago for $10 million. The machinery can be sold to the Romulans today for $9.1 million. Klingon's current balance sheet shows net fixed assets of $8 million, current liabilities of $780,000, and net working capital of $220,000. If all the current accounts were liquidated today, the company would receive $1.02 million cash. a. What is the book value of Klingon's assets today? (Do not round intermediate calculations and enter your answer...
A project is represented by the activity duration (in days, estimated at 90% likelihood of completion)...
A project is represented by the activity duration (in days, estimated at 90% likelihood of completion) and precedence requirements shown in the table. How many feeder buffers are needed if this project is managed using critical chain methodology? Activity Predecessor Length Activity Predecessor Length A -- 18 E C, D 13 B -- 16 F C 9 C A 22 G E, F 15 D B 14 ​ ​ ​ Options: 0 1 2 3
The project has a useful life of 10 years. Land costs $5m and is estimated to...
The project has a useful life of 10 years. Land costs $5m and is estimated to have a resale value of $7m at the completion of the project. Buildings cost $4m, with allowable depreciation of 5% pa straight-line and a salvage value of $0.8m. Equipment costs $3m, with allowable depreciation of 20% pa straight-line and a salvage value of $0.4m. An investment allowance of 20% of the equipment cost is available. Revenues are expected to be $5m in year one...
On January 1, 2016, Verlin Co. purchased new machinery for $300,000. The machinery has an estimated...
On January 1, 2016, Verlin Co. purchased new machinery for $300,000. The machinery has an estimated useful life of ten years, and depreciation is computed by the sum-of-the-years'-digits method. 20,000 Salvage. A) The accumulated depreciation on this machinery at December 31, 2017 is __________. Please prepare/show the journal entries for 12/31/2016; 12/31/2017; and 12/31/2018.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT