In: Operations Management
Original Project Cost, staff days | 1000 | staff days | |||
Original Project Schedule, months | 10 | months | |||
Planned Value | 340 | staff days | at | 4 | months |
Actual Cost | 370 | staff days | |||
Earned Value | 320 | staff days | |||
Current monthly staff | 5 | people | |||
Ans 6 | |||||
Cost variance (Earned value-actual cost, 320-370) | -50 | ||||
CPI (Earned value/actual cost, 320/370) | 0.86 | ||||
Cost shortfall (-50=50) | 50 | ||||
Scheduled variance (Earned value-planned value, 320-340) | -20 | ||||
SPI (Earned value-Planned value, 320/340) | 0.94 | ||||
Schedule shortfall (-20=20) | 20 | ||||
Cost EAC (If atypical variance)=original project cost-CV, 1000-(50) | 1050 | Staff days | |||
Cost EAC (If Typical variance)=original project cost/CPI, 1000/.86 | 1156 | Staff days | |||
Projected scheduled EAC | |||||
Schedule variance atypical (Project schedule x orginal project cost+schedule shortfall)/original project cost, 10x(1000+20)/1000 | 10.2 | Months | |||
Schedule variance typical (Project schedule months / SPI, 10/.94) | 10.6 | Months | |||
re-plan the remaining project and make a whole new estimate | Some date later than current actual date | ||||
Ans 7 | |||||
remaining cost-to-complete and schedule-to-complete | |||||
a Assumption CV is atypical and rest of work will be performed at original budgeted rate, Cost ETC=cost EAC atypical-actual cost, 1050-370) | 680 | Staff days | |||
b Assumption CV is typical and rest of work will be performed at present CPI, Cost ETC=cost EAC atypical-actual cost, 1156-370) | 786 | Staff days | |||
c : Assumption is we can replan the reamining project and makea new estimate then ETC is a new value which is result of our re plan | |||||
Ans 8 | |||||
intensity of work required to finish the work with the available funds | |||||
Assuming we want to complete within the BAC then to complete performance index is the work remaining (BAC-EV) divide by remaining fund (BAC-ActUal cost) | |||||
BAC (Budget at completion) BAC-EV/BAC-AC, TCPI=1000-320/1000-370 | 1.08 | ||||
Interpretation:BAC indicates we need to work at greater cost effeciency than originally pallned to be within our BAC | |||||
Assuming BAC is no longer a reasonable goal, we need to complete within current EAC and TCPI become work remaining, (BAC-EV)/(EAC-AC) | |||||
TCPI=BAC-EV/EAC-AC=(1000-320)/(1156-370) | 0.86 | ||||
Interpretation: We can work at lower cost effeciency than originally planned and finish within our current EAC | |||||