Question

In: Computer Science

Consider the table below, which includes time and activity data for a Small IT Project. All...

Consider the table below, which includes time and activity data for a Small IT Project. All duration estimates or estimated times are in days. Perform a critical path analysis for this project.

Activity

Duration (Days)

Predecessor

A

8

-

B

10

A

C

18

A

D

4

A

E

28

B, D

F

2

C, E

G

32

E

H

18

B

I

12

F

J

2

H, G, I

  1. Draw a network diagram representing the project. MS PowerPoint or Visio are good tools for this task. (10 points)
  2. Identify and list all of the paths through the network diagram and note how long they are. (4 points)
  3. What is the timeline within which the project can earliest be completed? (3 points)
  4. If D takes 7 days, what will be the impact to the project and the critical path? (4 points)
  5. If G takes an additional 7 days, what will be the impact to the project and the critical path? (4 points)

Solutions

Expert Solution

1). ANSWER :

GIVENTHAT :

As per given table the network diagram is as follows:

And also represented list of possible paths and their costs:

What is the timeline within which the project can earliest be completed?

Answer: 38 days

The shortest path is A-->B-->H-->J. which takes 38 days.

If D takes 7 days, what will be the impact to the project and the critical path?

The shortest path which the project can complete is : A-->B-->H-->J

It does not contain D. So even if D takes 7 days, there will be no impact on project completeion time.

The critical path is nothing but the longest path: A-->B-->E-->G-->J

It does not contain D. So even if D takes 7 days, there will be no impact on critical path.

If G takes an additional 7 days, what will be the impact to the project and the critical path?

If G takes an additional 7 days, the value of G will be = 32+7 = 39

The shortest path which the project can complete is : A-->B-->H-->J

It does not contain G. So even if G takes an additional 7 days, there will be no impact on project completeion time.

The critical path is nothing but the longest path: A-->B-->E-->G-->J

It contains 'G'. So if G takes an additional 7 days, the cost of critical path will change to = 87.


Related Solutions

Consider the data in table below which shows the time required to produce a particular item....
Consider the data in table below which shows the time required to produce a particular item. Using that data, calculate the learning rate associated with this product. Units Labor Hrs 5 155 9 147 13 137 17 97 25 72
The data in the table below are for the small country of Xanadu. Assume that the...
The data in the table below are for the small country of Xanadu. Assume that the economy is originallly producing combination C. A B C D E F   Capital Goods 0 20 28 35 39 41   Capital Goods 2   Consumer Goods 25 20 15 10 5 0
Consider the data provided in the table below, which shows years of education and income for...
Consider the data provided in the table below, which shows years of education and income for ten individuals. Education Income(1) Income(2) 10 15,000 15 12 20,000 20 12 35,000 35 12 40,000 40 12 60,000 60 16 50,000 50 16 60,000 60 16 70,000 70 18 60,000 60 21 80,000 80 A) Calculate the covariance and correlation of education and income, using the “Income1” column for income, which is measured in dollars. B) Calculate the covariance and correlation of education...
Consider the following hypothetical data in the table below describing a survey in which dog and...
Consider the following hypothetical data in the table below describing a survey in which dog and cat owners are asked whether they go for daily walks. Assume that we want to use a 0.01 significance level to test the claim that whether you own a dog or a cat is independent of whether you take a daily walk (based on Concepts and Applications of two-way table hypothesis tests, Daily walk No Daily walk Dog owner 95 15 Cat owner 40...
Consider the project described in the below Excel a. Construct an Activity-on-Node network for the project....
Consider the project described in the below Excel a. Construct an Activity-on-Node network for the project. b. Determine the critical path using the expected time for each activity (you can use Excel), and the expected project duration. c. What is the probability that the project will be finished in 3 weeks? In 4 weeks? Time estimates (days) Activity Predecessor a m b a -- 1 3 5 b -- 2 3 5 c -- 2 4 7 d a 1...
Consider the table​ below, which shows current account information for a country. All figures are in...
Consider the table​ below, which shows current account information for a country. All figures are in billions of dollars. Exports of goods 4565 Imports of goods - 3967 Exports of services 899 Imports of services -845 Net unilateral transfers -23 According to the​ table, the merchandise trade balance for this country is ​$? billion.​ (Enter your response as an​ integer.) According to the​ table, the current account balance is ​? ​billion and​ thus, if there is no government​ intervention, the...
Consider the table​ below, which shows current account information for a country. All figures are in...
Consider the table​ below, which shows current account information for a country. All figures are in billions of dollars. Exports of goods 3344 Imports of goods -3945 Exports of services 899 Imports of services -845 Net unilateral transfers -67 According to the​ table, the merchandise trade balance for this country is ​$ billion.​ (Enter your response as an​ integer.) According to the​ table, the current account balance is ​$ ​billion, and​ thus, if there is no government​ intervention, the financial...
make a plot of the data in the table below , plot position versus time time...
make a plot of the data in the table below , plot position versus time time squared (t2 ). make sure to label your graph properly.( Y axis title with units, X axis title with unit, title of the graph with equation , major tick marks. use data to plot the graph manually. use proper scal measurement position(m) time(s) time2 (s2 ) 1 0 0 0 2 5 1 1 3 21 2 4 4 46 3 9 5 82...
Consider the data contained in the table below, which lists 30 monthly excess returns to two...
Consider the data contained in the table below, which lists 30 monthly excess returns to two different actively managed stock portfolios (A and B) and three different common risk factors (1, 2, and 3). (Note: You may find it useful to use a computer spreadsheet program such as Microsoft Excel to calculate your answers.) Period Portfolio A Portfolio B Factor 1 Factor 2 Factor 3 1 1.00 % 0.00 % 0.02 % -0.99 % -1.73 % 2 7.52 6.61 6.85...
The following table represents a project with four activities. All times are in weeks. Activity Immediate...
The following table represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 4 8 16 B - 7 8 9 C A 6 10 18 D B 5 13 18 A. According to the data in the table. What is the critical path? B. According to the data in the table, what is the minimum expected completion time for the project? C. According to the table...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT