Question

In: Civil Engineering

Construction Documents Review 11. Explain Addendum, Addenda, and Change Order in construction projects. 12. Name and...

Construction Documents Review

11. Explain Addendum, Addenda, and Change Order in construction projects.

12. Name and explain three items (required at minimum) in a Change Order.

13. What is the Door Schedule, Window Schedule & Room Finishes?


Solutions

Expert Solution


Related Solutions

Construction Documents Review 26. Define Attention to Details and Negligence in construction projects 27. Explain Bidding...
Construction Documents Review 26. Define Attention to Details and Negligence in construction projects 27. Explain Bidding Process / Bid Day 28. What is a Construction contract administration / Error and Omission insurance 29.What is a Project file / Project Evaluation / BIM 30. Explain Communication in Construction projects (relationship of GC, owner, etc.)
Construction Documents 1. What is included in a Bid Package for a construction project? 2. Name...
Construction Documents 1. What is included in a Bid Package for a construction project? 2. Name and explain the three different stages of construction projects development. 3. Name and explain the three different stages of Architectural Design process for construction projects. 4. Name ten (10) different drawings in a set of drawing for a construction project. 5. What is Title Block and what type of information you can find in a Title Block?  
Construction Documents Review 21. Difference between Insurance and Bond 22. Explain Lien and Lien process 23....
Construction Documents Review 21. Difference between Insurance and Bond 22. Explain Lien and Lien process 23. Construction cost estimating / Different types / Cost Monitoring / Units of Measurement 24. Construction Contract types / Lump Sum / Cost plus contracts / GMP 25. Construction Scheduling / CPM / Delay / Fast Track / Turn Key / Liquidated Damages
1. How is BOQ (Bill of Quantities) related to change order payment in construction projects? 2....
1. How is BOQ (Bill of Quantities) related to change order payment in construction projects? 2. Explain if owner has direct relationship with the subcontractors. What happens if the owner interferes into the work of the subcontractors.
Construction Documents Review 17. Definitions; Submittal, Constructability, Vented soffit, Specifier, Lead time, etc. 18. Four levels...
Construction Documents Review 17. Definitions; Submittal, Constructability, Vented soffit, Specifier, Lead time, etc. 18. Four levels of certification for Green projects? Three levels of credentials for individuals? 19. Four Insurances required at minimum for Construction Projects? 20. Three Bonds required for Construction projects?
Exercise 11-12 In 1993, Nash Company completed the construction of a building at a cost of...
Exercise 11-12 In 1993, Nash Company completed the construction of a building at a cost of $2,040,000 and first occupied it in January 1994. It was estimated that the building will have a useful life of 40 years and a salvage value of $59,200 at the end of that time. Early in 2004, an addition to the building was constructed at a cost of $510,000. At that time, it was estimated that the remaining life of the building would be,...
Exercise 11-12 In 1990, Pina Company completed the construction of a building at a cost of...
Exercise 11-12 In 1990, Pina Company completed the construction of a building at a cost of $2,120,000 and first occupied it in January 1991. It was estimated that the building will have a useful life of 40 years and a salvage value of $63,600 at the end of that time. Early in 2001, an addition to the building was constructed at a cost of $530,000. At that time, it was estimated that the remaining life of the building would be,...
11. Solubility of O2 _______________with the increase in temp. Select one: Increases Decreases No Change 12....
11. Solubility of O2 _______________with the increase in temp. Select one: Increases Decreases No Change 12. For isokinetic sampling, static pressure at nozzle tip should be _____________than that of free stream Select one: Less More Equal 13The DO level in the water _________ from 12.30 pm to 3.30pm. Select one: Increasses Decreases Remains same 14. Which of the following particulate matter are collected in collection devices in steel industry? Select one: Oil Acetic acid Iron oxide Boron 15. Eutrophication causes...
Problem 11-12 IRR and NPV A company is analyzing two mutually exclusive projects, S and L,...
Problem 11-12 IRR and NPV A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $898.26 $240 $5 $10 Project L -$1,000 $5 $250 $380 $827.29 The company's WACC is 9.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places.
Problem 12-11 (Algorithmic) Over a five-year period, the quarterly change in the price per share of...
Problem 12-11 (Algorithmic) Over a five-year period, the quarterly change in the price per share of common stock for a major oil company ranged from -7% to 10%. A financial analyst wants to learn what can be expected for price appreciation of this stock over the next two years. Using the five-year history as a basis, the analyst is willing to assume that the change in price for each quarter is uniformly distributed between -7% and 10%. Use simulation to...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT