Question

In: Accounting

Exercise 11-12 In 1990, Pina Company completed the construction of a building at a cost of...

Exercise 11-12

In 1990, Pina Company completed the construction of a building at a cost of $2,120,000 and first occupied it in January 1991. It was estimated that the building will have a useful life of 40 years and a salvage value of $63,600 at the end of that time.

Early in 2001, an addition to the building was constructed at a cost of $530,000. At that time, it was estimated that the remaining life of the building would be, as originally estimated, an additional 30 years, and that the addition would have a life of 30 years and a salvage value of $21,200.

In 2019, it is determined that the probable life of the building and addition will extend to the end of 2050, or 20 years beyond the original estimate.

Compute the annual depreciation to be charged, beginning with 2019. (Round answer to 0 decimal places, e.g. 45,892.)

Solutions

Expert Solution


Related Solutions

Exercise 11-12 In 1993, Nash Company completed the construction of a building at a cost of...
Exercise 11-12 In 1993, Nash Company completed the construction of a building at a cost of $2,040,000 and first occupied it in January 1994. It was estimated that the building will have a useful life of 40 years and a salvage value of $59,200 at the end of that time. Early in 2004, an addition to the building was constructed at a cost of $510,000. At that time, it was estimated that the remaining life of the building would be,...
Practice Exercise 11-2 In 1990, Carla Vista Company completed the construction of a building at a...
Practice Exercise 11-2 In 1990, Carla Vista Company completed the construction of a building at a cost of $900,000 and first occupied it in January 1991. It was estimated that the building would have a useful life of 40 years and a salvage value of $27,000 at the end of that time. Early in 2001, an addition to the building was constructed at a cost of $225,000. At that time, it was estimated that the remaining life of the building...
In 1990, Metlock Company completed the construction of a building at a cost of $2,300,000 and...
In 1990, Metlock Company completed the construction of a building at a cost of $2,300,000 and first occupied it in January 1991. It was estimated that the building will have a useful life of 40 years and a salvage value of $69,000 at the end of that time. Early in 2001, an addition to the building was constructed at a cost of $575,000. At that time, it was estimated that the remaining life of the building would be, as originally...
In 1990, Flounder Company completed the construction of a building at a cost of $2,300,000 and...
In 1990, Flounder Company completed the construction of a building at a cost of $2,300,000 and first occupied it in January 1991. It was estimated that the building will have a useful life of 40 years and a salvage value of $69,000 at the end of that time. Early in 2001, an addition to the building was constructed at a cost of $575,000. At that time, it was estimated that the remaining life of the building would be, as originally...
Pina Company is constructing a building. Construction began on February 1 and was completed on December...
Pina Company is constructing a building. Construction began on February 1 and was completed on December 31. Expenditures were $2,004,000 on March 1, $1,284,000 on June 1, and $3,039,450 on December 31. Compute Pina’s weighted-average accumulated expenditures for interest capitalization purposes.
In 1993, Nash Company completed the construction of a building at a cost of $2,040,000 and...
In 1993, Nash Company completed the construction of a building at a cost of $2,040,000 and first occupied it in January 1994. It was estimated that the building will have a useful life of 40 years and a salvage value of $59,200 at the end of that time. Early in 2004, an addition to the building was constructed at a cost of $510,000. At that time, it was estimated that the remaining life of the building would be, as originally...
In 1993, Windsor Company completed the construction of a building at a cost of $2,160,000 and...
In 1993, Windsor Company completed the construction of a building at a cost of $2,160,000 and first occupied it in January 1994. It was estimated that the building will have a useful life of 40 years and a salvage value of $65,600 at the end of that time. Early in 2004, an addition to the building was constructed at a cost of $540,000. At that time, it was estimated that the remaining life of the building would be, as originally...
In 1993, Windsor Company completed the construction of a building at a cost of $2,160,000 and...
In 1993, Windsor Company completed the construction of a building at a cost of $2,160,000 and first occupied it in January 1994. It was estimated that the building will have a useful life of 40 years and a salvage value of $65,600 at the end of that time. Early in 2004, an addition to the building was constructed at a cost of $540,000. At that time, it was estimated that the remaining life of the building would be, as originally...
In 1993, Novak Company completed the construction of a building at a cost of $2,500,000 and...
In 1993, Novak Company completed the construction of a building at a cost of $2,500,000 and first occupied it in January 1994. It was estimated that the building will have a useful life of 40 years and a salvage value of $76,000 at the end of that time. Early in 2004, an addition to the building was constructed at a cost of $625,000. At that time, it was estimated that the remaining life of the building would be, as originally...
In 1993, Skysong Company completed the construction of a building at a cost of $2,120,000 and...
In 1993, Skysong Company completed the construction of a building at a cost of $2,120,000 and first occupied it in January 1994. It was estimated that the building will have a useful life of 40 years and a salvage value of $64,000 at the end of that time. Early in 2004, an addition to the building was constructed at a cost of $530,000. At that time, it was estimated that the remaining life of the building would be, as originally...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT