Question

In: Operations Management

The project manager should anticipate the affects the changes could have on the overall project, and...

The project manager should anticipate the affects the changes could have on the overall project, and prepare to compensate for any shortcomings. Have you experienced this sort of ripple affect on any projects?

Solutions

Expert Solution

Yes, we have experienced ripple effects on one of our projects. As part of our project, we were supposed to build a mobile application for patients. Each deliverable required approval from key stakeholders including the project sponsor. Further, we had a strict change order request in place to control scope creek.

Once the project implementation started, a risk plan was formulated by project manager but it overlooked a key risk - " Absence of stakeholder" i.e. it failed to define how the project would move forward if key approvals were delayed. During the business requirements phase a lot of changes to initial scope were made, however, project sponsor had resigned from the client side. Due to this, there was a delay of 2-3 weeks in the getting approval on business requirements of the project. The client was unable to give us a replacement approver for this duration and we had not mentioned any mitigation plan for this risk earlier. Due to serial delays at business requirements phase, design phase was delayed by 5-6 weeks. The requirements had considerably changed and our estimated time for the design was not sufficient to meet the timelines decided.

Finally, our project manager decided to redo the entire project timeline incorporating delays that were expected. Overall the entire project was delayed by 4 months.


Related Solutions

A project manager and the project team should not focus on ‘project firefighting ‘but should allocate...
A project manager and the project team should not focus on ‘project firefighting ‘but should allocate sufficient time and resources to preventing problems throughout the life of the project. Project Risk management is one way of preventing problems that can negatively affect the project objectives of cost, schedule, scope, and quality. Effective risk management is directed at eliminating threats and increasing opportunities to ensure project success. (1) Examine a project that you have worked on or know about and discuss...
A project manager and the project team should not focus on ‘project firefighting ‘but should allocate...
A project manager and the project team should not focus on ‘project firefighting ‘but should allocate sufficient time and resources to preventing problems throughout the life of the project. Project Risk management is one way of preventing problems that can negatively affect the project objectives of cost, schedule, scope, and quality. Effective risk management is directed at eliminating threats and increasing opportunities to ensure project success. (1) Examine a project that you have worked on or know about and discuss...
What are the critical success factors for a project manager? What skills should project managers have...
What are the critical success factors for a project manager? What skills should project managers have to be successful in this job?
Should Manager and Deputy Manager pay rates be reconsidered in light of the changes? What are...
Should Manager and Deputy Manager pay rates be reconsidered in light of the changes? What are the pros and cons of different options?
4. How could both sides have prepared better to anticipate the problems faced in the negotiation?...
4. How could both sides have prepared better to anticipate the problems faced in the negotiation? Refer to journal case "  Cross Cultural Negotiations: Americas Negotiating a Contract in China "
A project manager is preparing two documents for risk management. One contains sources of overall project...
A project manager is preparing two documents for risk management. One contains sources of overall project risk and also summary information on individual risks. The second describes individual risks identified. What name should the project manager give to the first document?
subject...project management 4. As a project manager, you should know the characteristics of a project. The...
subject...project management 4. As a project manager, you should know the characteristics of a project. The project, for example, utilizes processes to move the project work forward. All of the following are typical of a project, except for which one? a,It is a temporary endeavor. b, It creates a unique product or service. c, It occurs monthly. d,It has an end date. 5. An organization is considering investing in a new project, but they want to make certain the investment...
Why should project manager even if only involved in the financial aspects of a project be...
Why should project manager even if only involved in the financial aspects of a project be aware of codes, standards, acts regulations and building legislation
Requirement in project documentation. What should the project manager do to resolve the situation with the...
Requirement in project documentation. What should the project manager do to resolve the situation with the stakeholders?
Why should a project manager in charge of a medium rise building project make a comparison...
Why should a project manager in charge of a medium rise building project make a comparison of the costs associated with the risk, both to mitigate the risk and the cost if the risk presents itself
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT