Question

In: Operations Management

subject...project management 4. As a project manager, you should know the characteristics of a project. The...

subject...project management

4. As a project manager, you should know the characteristics of a project. The project, for example, utilizes processes to move the project work forward. All of the following are typical of a project, except for which one?

a,It is a temporary endeavor.

b, It creates a unique product or service.

c, It occurs monthly.

d,It has an end date.

5. An organization is considering investing in a new project, but they want to make certain the investment is a wise decision. Which project selection method would consider the return on investment for a given project?

a,

Funds that have been invested into a project

b,

Benefit measurement methods

c,

Linear programming methods

d,

Dynamic algorithms

6,

A project manager has created a project charter but cannot get it signed. The project sponsor has requested the project manager get started on the project immediately. Of the following, which one is the best action?

a,

Request the project charter be signed before starting the project work.

b,

Create a risk impact statement for not having a charter.

c,

Complete the activities on the critical path.

d,

Ask the project sponsor to create a letter of intent.

7, James is the project manager for his organization, and he’s working with Lila to select a new project. Lila wants to know the exact software solution James will be proposing for the organization. James wants to focus on the long-range vision of how the software will help the organization. What statement best describes these two people?

a,James is using management. Lila is using leadership.

b,

James is using leadership. Lila is using management.

c,

James is using management. Lila is using micromanagement.

d,

James is using leadership. Lila is emotional intelligence.

8, You are the project manager for your organization, and you’re working with Scott, the project sponsor, to define the characteristics of a project. Scott is confused about constraints, assumptions, needs for a project, and the duration of new projects. To help Scott, you could say that customer demands, changes to the marketplace, and opportunity are all examples of what?

a,

Project constraints

b,

Project assumptions

c.Reasons for project initiation

d, Components of a long-term project

9, Laura is the project manager for her organization and she’s working with management to launch a new project. All of the following activities happen with the initiation process group except which one?

a,Create the project charter.

b,Create the product description.

c,

Identify the project constraints.

d, Define the project activities.

10..You are the project manager for your organization, and you’re working with Nancy, the CIO in your company, to launch the project. Nancy wants you to draft the project charter for a new project. All of the following statements about a project charter are incorrect except for which one?

a,

Charters are not needed until the project plan is developed.

b,The project manager issues the charter to the project team.

c,

The project charter authorizes the project.

d,

The project charter is not needed on all projects.

  

Solutions

Expert Solution

4.As a project manager, you should know the characteristics of a project. The project, for example, utilizes processes to move the project work forward. All of the following are typical of a project, except for which one?

c) it occurs monthly

5.An organization is considering investing in a new project, but they want to make certain the investment is a wise decision. Which project selection method would consider the return on investment for a given project?

b) Benefit measurement methods

6. A project manager has created a project charter but cannot get it signed. The project sponsor has requested the project manager get started on the project immediately. Of the following, which one is the best action?

a) Request the project charter be signed before starting the project work

7. James is the project manager for his organization, and he’s working with Lila to select a new project. Lila wants to know the exact software solution James will be proposing for the organization. James wants to focus on the long-range vision of how the software will help the organization. What statement best describes these two people?

c) James is using management. Lila is using micromanagement

8. You are the project manager for your organization, and you’re working with Scott, the project sponsor, to define the characteristics of a project. Scott is confused about constraints, assumptions, needs for a project, and the duration of new projects. To help Scott, you could say that customer demands, changes to the marketplace, and opportunity are all examples of what?

c) reasons for project initiation

9.Laura is the project manager for her organization and she’s working with management to launch a new project. All of the following activities happen with the initiation process group except which one?

b) create the Product description

10.You are the project manager for your organization, and you’re working with Nancy, the CIO in your company, to launch the project. Nancy wants you to draft the project charter for a new project. All of the following statements about a project charter are incorrect except for which one?

c) the project charter authorizes the project


Related Solutions

You are a junior manager with expertise in project management and a member of a project...
You are a junior manager with expertise in project management and a member of a project team of a company that just won the bid to develop a new internet banking management system for a major bank in South Africa. The project will entail the following activities along with their respective precedence, duration and cost. Activity Code Activity Immediate Predecessor Normal Time(Weeks) Crashing Time(weeks) Normal Cost Crashing cost 1 A – 12 8 $100000 $104000 2 B A 17 15...
Hi, can you answer this question in more detail? Subject: Project Management ② Why project management...
Hi, can you answer this question in more detail? Subject: Project Management ② Why project management has become such a popular business tool in recent years? Discuss with a company case as example.
Given a project with the following characteristics, answer the following questions: You are the project manager...
Given a project with the following characteristics, answer the following questions: You are the project manager of a project to upgrade the generators at cell phone towers. Your project is scheduled to last for 12 months. It is the beginning of month 4. Your crews are to upgrade 8 cell phone towers per month for 12 months. Each generator is planned to cost $40,000 which includes equipment, labor, and fueling costs. You have upgraded 30 cell phone towers and your...
Use a project that you know of and provide a risk management plan for the project....
Use a project that you know of and provide a risk management plan for the project. Conduct an analysis of the risk management process as evidenced by the plan.
What special characteristics should a recovery project manager possess? Which of these is more critical for...
What special characteristics should a recovery project manager possess? Which of these is more critical for the role of recovery project manager vs. project manager and why? Answer with 250 words.
Hi, can you answer this question in more detail? Subject: Project Management (2) Why project management...
Hi, can you answer this question in more detail? Subject: Project Management (2) Why project management has become such a popular business tool in recent years? Discuss with a company case as example.
This assignment is the subject of project planning, monitoring, and evaluation. As a project manager, the...
This assignment is the subject of project planning, monitoring, and evaluation. As a project manager, the board of the organization has asked you to develop a sustainability and risk plan of a health project that you have proposed to the board. this is the question (Prepare a document to discuss approaches to enhance sustainability and mitigate against any risk.)
You are the project manager for a software development project for an updated management system. The...
You are the project manager for a software development project for an updated management system. The cost of doing it in-house is $27,000. You estimate you'll spend $2,000 per month updating the software with client information, government regulations, and maintenance. You know that a contractor do the programming for your company and charge a fee based on the number of personnel using the program every month. This contractor will charge you $4 per month per user of the accounting system....
Elaborate on the characteristics of the public management environments. Subject: Public Administration
Elaborate on the characteristics of the public management environments. Subject: Public Administration
A project manager and the project team should not focus on ‘project firefighting ‘but should allocate...
A project manager and the project team should not focus on ‘project firefighting ‘but should allocate sufficient time and resources to preventing problems throughout the life of the project. Project Risk management is one way of preventing problems that can negatively affect the project objectives of cost, schedule, scope, and quality. Effective risk management is directed at eliminating threats and increasing opportunities to ensure project success. (1) Examine a project that you have worked on or know about and discuss...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT