A project manager is preparing two documents for risk management. One contains sources of overall project risk and also summary information on individual risks. The second describes individual risks identified. What name should the project manager give to the first document?
As the file contains sources of risks for the whole project and also the details of individual risks identified which would help as a reference for risks at every point of the project, it can be names as source document or reference document. It is because the first file contains all the information we can refer to at ant point and which can even be referred for details regarding risks of second file.