Question

In: Operations Management

Your project to obtain charitable donations is now 45 days into a planned 55-day project. The...

Your project to obtain charitable donations is now 45 days into a planned 55-day project. The project is divided into 3 activities. The first activity is designed to solicit individual donations. It is scheduled to run the first 40 days of the project and to bring in $24,900. Even though we are 45 days into the project, we still see that we have only 91% of this activity complete. The second activity relates to company donations and is scheduled to run for 45 days starting on day 5 and extending through day 50. We estimate that even though we should have (40/45) 89% of this activity complete, it is actually only 60% complete. This part of the project was scheduled to bring in $149,900 in donations. The final activity is for matching funds. This activity is scheduled to run the last 10 days of the project and has not started. It is scheduled to bring in an additional $49,800. So far $175,800 has actually been brought in on the project.

Calculate the schedule variance, schedule performance index, cost variance and cost (actually value in this case) performance index. (Negative values should be indicated by a minus sign. Do not round intermediate calculations. Round your dollar amounts to the nearest whole number. Round your "performance index" values to 3 decimal places.)

rev: 08_07_2014_QC_522

Schedule variance $__________
Schedule performance index ___________
Cost variance $__________
Cost performance index ___________

Solutions

Expert Solution

Let the three activities be names as 1, 2 and 3 respectively.

First, lets compute budgeted revenue of the project till 45th day. To do that, we need to compute budgeted revenue of each activity.

Budgeted revenue of work completed for Activity 1= Budgeted revenue X Planned completion till date

= 24900 X 100% = $24900

Budgeted revenue of work completed for Activity 2= Budgeted revenue X Planned completion till date

= 149900 X 89% = $133411

Budgeted recenue of work completed for Activity 3= Budgeted revenue X Planned completion till date

=49800 X 0% = 0

Thus, budgeted revenue of the project = Budgeted rev. of Activity 1 + Budgeted rev. of Activity 2 + Budgeted rev. of Activity 3

= 24900 + 133411 + 0= $158311

Budgeted revenue of work performed till 45th day,

Budgeted revenue of work performed for Activity 1= Budgeted revenue X actual completion date

= 25000 X 91% = $22750

Budgeted revenue of work performed for Activity 2= Budgeted revenue X actual completion date

= 149900 X 60% = $89940

Budgeted revenue for work performed for Activity 3= Budgeted revenue X actual completion date

= 49800 X 60% = $89940

Thus, budgeted revenue of work performed project = Budgeted rev. of Activity 1 + Budgeted rev. of  Activity 2 + Budgeted rev. of  Activity 3

= 22750 + 89940 + 0= $112690

Schedule variance = Budgeted revenue of work performed - budgeted revenue of work scheduled = 112690 - 158311 = -$45621

This indicates project is behind schedule.

Schedule performance index = Budgeted revenue of work performed/ budgeted revenue of work scheduled = 112690/158311= 0.712

A scheduled performance index of less than 1 also indicates project is behind schedule.

Cost variance = Budgeted revenue of work performed - Actual revenue = 112690 -175800 = -$63110

Cost performance index = Budgeted revenue of work performed / Actual revenue = 112690/ 175800 = 0.641

A cost performance index of less than 1 also indicates project is performing better than planned performance in terms of revenue


Related Solutions

Your project to obtain charitable donations is now 38 days into a planned 48-day project. The...
Your project to obtain charitable donations is now 38 days into a planned 48-day project. The project is divided into 3 activities. The first activity is designed to solicit individual donations. It is scheduled to run the first 33 days of the project and to bring in $25,300. Even though we are 38 days into the project, we still see that we have only 88% of this activity complete. The second activity relates to company donations and is scheduled to...
Medwig Corporation has a DSO of 45 days. The company averages $4,500 in sales each day...
Medwig Corporation has a DSO of 45 days. The company averages $4,500 in sales each day (all customers take credit). What is the company's average accounts receivable? Round your answer to the nearest dollar.
Your client John Smith is 45. He wants to retire at the age of 55. He...
Your client John Smith is 45. He wants to retire at the age of 55. He plans to sell his business sometime in the next five years and he is considering using the $100,000 proceeds from the sale to purchase an annuity. Explain to your client what an annuity does. Under what set of circumstances would the annuity be desirable to Smith? If the annuity is purchased, what features should it have with respect to guarantees? If Mr. Smith does...
Your client John Smith is 45. He wants to retire at the age of 55. He...
Your client John Smith is 45. He wants to retire at the age of 55. He plans to sell his business sometime in the next five years and he is considering using the $100,000 proceeds from the sale to purchase an annuity. Explain to your client what an annuity does. Under what set of circumstances would the annuity be desirable to Smith? If the annuity is purchased, what features should it have with respect to guarantees? If Mr. Smith does...
Max Wholesaler borrowed $3,000 on a 8%, 120-day note. After 45 days, Max paid $1,050 on...
Max Wholesaler borrowed $3,000 on a 8%, 120-day note. After 45 days, Max paid $1,050 on the note. Thirty days later, Max paid an additional $900. Use ordinary interest. a) Determine the total interest use the U.S. Rule. (Do not round intermediate calculations. Round your answers to the nearest cent.) b) Determine the ending balance due use the U.S. Rule.(Do not round intermediate calculations. Round your answers to the nearest cent.)
Max Wholesaler borrowed $5,000 on a 12%, 120-day note. After 45 days, Max paid $1,750 on...
Max Wholesaler borrowed $5,000 on a 12%, 120-day note. After 45 days, Max paid $1,750 on the note. Thirty days later, Max paid an additional $1,500. Use ordinary interest. a. Determine the total interest using the U.S. Rule. (Round your intermediate balances and interest amounts to the nearest cent. Round your final answer to the nearest cent.) Total interest amount            $ b. Determine the ending balance due using the U.S. Rule. (Round your intermediate balances and interest amounts to the...
Your dad is now 55 years old and plans to retire at age 70. He currently...
Your dad is now 55 years old and plans to retire at age 70. He currently has a stock portfolio worth $450,000. The portfolio is expected to earn a return of 8 percent per year. b. Assume he plans to invest an additional $12,000 every year in his portfolio for the next 15 years (starting one year from now). How much will his investments be worth when he retires at 70? c. Assume that your dad expects to live 20...
Now, it's time to turn in your semester project. Remember your project should include the following:...
Now, it's time to turn in your semester project. Remember your project should include the following: A Mental Health Concern - and the Patient or Community - for your project. A brief history of the patient including diagnoses and medications - or a brief description of the community issue. Any substance abuse, addiction or violence issues surrounding this mental health problem. Describe the attempted interventions that have been made for your patient or community, and identify what has been successful...
WEEK 10 DISCUSSION We are now at the end of the road and your project is...
WEEK 10 DISCUSSION We are now at the end of the road and your project is coming to a completion. Before you celebrate, there are still a few more steps before you close-out this project. It is time to discuss lessons learned with your team about this project and your communication management plan. In a few paragraphs respond to the following question: Discuss the importance of conducting lessons learned meeting with the team and why it should be documented and...
Obtain the supporting information from your Portfolio Project option. You will also use the Schedule A...
Obtain the supporting information from your Portfolio Project option. You will also use the Schedule A template included under that same option. Show all calculations within the cells of the template. This means that you must use formulas and links so that the thought process can be examined. Make good use of comments to convey your thought process as well; no hard coding of solutions. Submit a single MS Excel file for grading. The deliverable is as follows: The completed...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT