Question

In: Operations Management

Your project to obtain charitable donations is now 38 days into a planned 48-day project. The...

Your project to obtain charitable donations is now 38 days into a planned 48-day project. The project is divided into 3 activities. The first activity is designed to solicit individual donations. It is scheduled to run the first 33 days of the project and to bring in $25,300. Even though we are 38 days into the project, we still see that we have only 88% of this activity complete. The second activity relates to company donations and is scheduled to run for 38 days starting on day 5 and extending through day 43. We estimate that even though we should have (33/38) 87% of this activity complete, it is actually only 50% complete. This part of the project was scheduled to bring in $150,300 in donations. The final activity is for matching funds. This activity is scheduled to run the last 10 days of the project and has not started. It is scheduled to bring in an additional $50,600. So far $175,800 has actually been brought in on the project.

Calculate the schedule variance, schedule performance index, cost variance and cost (actually value in this case) performance index. (Negative values should be indicated by a minus sign. Do not round intermediate calculations. Round your dollar amounts to the nearest whole number. Round your "performance index" values to 3 decimal places.)

Schedule variance $
Schedule performance index
Cost variance $
Cost performance index

Solutions

Expert Solution


Related Solutions

Your project to obtain charitable donations is now 45 days into a planned 55-day project. The...
Your project to obtain charitable donations is now 45 days into a planned 55-day project. The project is divided into 3 activities. The first activity is designed to solicit individual donations. It is scheduled to run the first 40 days of the project and to bring in $24,900. Even though we are 45 days into the project, we still see that we have only 91% of this activity complete. The second activity relates to company donations and is scheduled to...
Now, it's time to turn in your semester project. Remember your project should include the following:...
Now, it's time to turn in your semester project. Remember your project should include the following: A Mental Health Concern - and the Patient or Community - for your project. A brief history of the patient including diagnoses and medications - or a brief description of the community issue. Any substance abuse, addiction or violence issues surrounding this mental health problem. Describe the attempted interventions that have been made for your patient or community, and identify what has been successful...
WEEK 10 DISCUSSION We are now at the end of the road and your project is...
WEEK 10 DISCUSSION We are now at the end of the road and your project is coming to a completion. Before you celebrate, there are still a few more steps before you close-out this project. It is time to discuss lessons learned with your team about this project and your communication management plan. In a few paragraphs respond to the following question: Discuss the importance of conducting lessons learned meeting with the team and why it should be documented and...
Obtain the supporting information from your Portfolio Project option. You will also use the Schedule A...
Obtain the supporting information from your Portfolio Project option. You will also use the Schedule A template included under that same option. Show all calculations within the cells of the template. This means that you must use formulas and links so that the thought process can be examined. Make good use of comments to convey your thought process as well; no hard coding of solutions. Submit a single MS Excel file for grading. The deliverable is as follows: The completed...
Obtain the supporting information from your Portfolio Project option. You will also use the Schedule A...
Obtain the supporting information from your Portfolio Project option. You will also use the Schedule A template included under that same option as applicable. If Schedule A is not applicable, state so on the form. Show all calculations within the cells of the template. This means that you must use formulas and links so that your thought process can be examined. Make good use of comments to convey your thought process as well. No hard coding of solutions. Submit a...
If you borrow the entire fund of your renovation project now (e.g. $100,000)
If you borrow the entire fund of your renovation project now (e.g. $100,000) from a bank at an interest of 6% compounded daily and the project takes 2 years to complete, what would be the actual value of your renovation work at completion?
Now that you have identified your capstone change project below, it is time to look at...
Now that you have identified your capstone change project below, it is time to look at its feasibility. Leppin, A. L., Gionfriddo, M. R., Kessler, M., Brito, J. P., Mair, F. S., Gallacher, K., & ... Montori, V. M. (2014). Preventing 30-day hospital readmissions: a systematic review and meta-analysis of randomized trials. JAMA Internal Medicine, 174(7), 1095-1107. doi:10.1001/jamainternmed.2014.160 What tangible and intangible resources will be needed to implement your project? What improved outcomes do you anticipate will occur that could...
Change can be difficult to implement. Now that you are almost finished with your change project,...
Change can be difficult to implement. Now that you are almost finished with your change project, if you were to implement your project in your clinical practice, what type of resistance do you expect from staff? List at least three ways that you can lessen the resistance you may encounter to help ensure the success of your project.
You are a project team manager, and your team members report each day to you to...
You are a project team manager, and your team members report each day to you to receive their primary assignments.   Not every team member is as efficient as another with particular kinds of tasks.    Time required (hours) to complete tasks Task Task complexity Team member 1 - Jones Team member 2 - Nguyen Team member 3 - Walpita Team member 4 - Manderas Task A Very high 3 5 4 3 Task A High 2 1 3 2 Task...
CONFIDENCE INTERVAL PROJECT – Day 3 AFTER YOUR DONE CALCULATING, FOR EACH CONFIDENCE INTERVAL: Describe your...
CONFIDENCE INTERVAL PROJECT – Day 3 AFTER YOUR DONE CALCULATING, FOR EACH CONFIDENCE INTERVAL: Describe your process of constructing the 95% CI Interpret your results of the CI in context Do you believe your CI is accurate? Explain why or why not, using values as your justification. (You will not be graded on whether or not it’s accurate, but instead on how you discuss its accuracy.) Who do you think might be interested in your data? Why? How might they...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT