Project Management Analytics Exercise This is an example of a construction project. The construction for a...

Project Management Analytics Exercise

This is an example of a construction project. The construction for a large corporate building must be started by February 19th and completed by the end of the year. The legal contract for the project includes a penalty of $10,000 for every week of delay beyond December 31st. This implies 315 days or 45 weeks for the expected project duration assuming a seven-day work schedule and no holidays in between!

The details of the project activities are as follows –

The project begins with clearing the site, an activity that takes eight weeks. Once the site is cleared, laying of the subsurface drainage takes another eight weeks, followed by filling of the earth which takes 14 weeks. Only after this activity is completed can installation of the artificial turf outside of the building can start – the task then takes 12 weeks. Simultaneously, the work on the building can also start once the site is cleared.

The work on the building starts first by excavating and then by pouring of the concrete basement. Each of these activities takes 4 weeks to complete. Next comes the construction of the walls (12 weeks), followed by constructing the roof (13 weeks). The interiors are then completed (5 weeks) followed by internal painting (4 weeks). However, painting cannot be started until electrical work is completed (4 weeks). The electrical work cannot be started until the outside power lines are laid (8 weeks), which needs an additional activity of getting the permits before it can be started. The permit takes 4 weeks. Assume that you would start on the permits after the excavation activity for the building begins.

Once the roof of the building is erected, work can start simultaneously on the outside lighting (5 weeks), and on the signage and other external landscaping (4 weeks). For simplicity, assume you start the project on February 19th and you follow a 7-day work schedule where each week of an activity’s duration takes 7 days.

Analyze the following questions based on the estimates of the above activities -

1) When do you complete the project?

Solutions

Expert Solution

The first step is to prepare a table listing the project activities, their predecessors and duration as under:

Activity Description Predecessor Duration
A Clearing the site 8
B Laying of subsurface drainage A 8
C Filling of earth B 14
D Installation of artificial turf C 12
E Excavation A 4
F Pouring of concrete basement E 4
G Construction of walls F 12
H Constructing the roof G 13
I Complete interiors H 5
J Internal painting I,M 4
K Start on the permits D 4
L Lay outside power lines K 8
M Electrical work L 4
N Outside lighting H 5
O Singage and ther external landscaping H 4

Draw the activity on node network diagram as under

There are two paths in the network.

i) A-B-C-D-K-L-M-J , duration = 62 weeks (sum of individual activity run

ii) E-F-G-H-I-J, duration = 42 weeks

Longest path is the ceitical path. The duration of critical path is 62 weeks. This is 17 weeks more than the planned duration of 45 weeks.

1) The project would complete on 29th April .

It means the project would complete


Related Solutions

Project Management Analytics Exercise This is an example of a construction project. The construction for a...
Project Management Analytics Exercise This is an example of a construction project. The construction for a large corporate building must be started by February 19th and completed by the end of the year. The legal contract for the project includes a penalty of $10,000 for every week of delay beyond December 31st. This implies 315 days or 45 weeks for the expected project duration assuming a seven-day work schedule and no holidays in between! The details of the project activities...
Define rework in construction project and milestone in construction project and give example .
Define rework in construction project and milestone in construction project and give example .
Give an example of a project management standard and an example of a project management metric....
Give an example of a project management standard and an example of a project management metric. Describe how each advances the organization’s project management effectiveness.
Please provide an example of a Project Scope of a house construction
Please provide an example of a Project Scope of a house construction
define group risks in project management with an example
define group risks in project management with an example
1. Find an example of data analytics project that has published its data publicly and state...
1. Find an example of data analytics project that has published its data publicly and state the source. 2. Explain about the project and why it is interesting to you? 3. Identify and explain the objective of the data analytics. 4. Identify and explain the data types.   5. Explain the data mining techniques involved 6. State the insights discovered in the project.
example of case study in terms of business analytics
example of case study in terms of business analytics
Key roles for a successful analytics project. Select a data analytics of your choice and discuss...
Key roles for a successful analytics project. Select a data analytics of your choice and discuss how the following roles add value to this initiative: Business User, Project Sponsor, Project Manager, Business Intelligence Analyst, Database Administrator, and Data Engineer. Again, please note that you will discuss specific activities that each of these roles may perform on a data analytics project that you select. Need 500 discussion
What is the definition of Project Management? Using your own example, discuss project scheduling with the...
What is the definition of Project Management? Using your own example, discuss project scheduling with the critical path method (CPM).
Suburban Homes Construction Project Quality Management Plan (QMP) Prepare a quality management plan using the elements...
Suburban Homes Construction Project Quality Management Plan (QMP) Prepare a quality management plan using the elements described in the PMBOK 6e (Section 8.1.3.1) for the Suburban Homes Construction Project. Content (90 points) Over the course the semester you’ve become familiar with the project and as part of the overall project management plan, a quality management plan is needed to communicate how quality will be met to the satisfaction of each stakeholder involved in a typical residential construction project. You should...