In: Finance
As the director of Big Sky Corp, you are evaluating two mutually exclusive projects with the following net cash flow:
Year Cash Flow X ($) Cash Flow Y ($)
0 -100,000 -100,000
1 60,000 20,000
2 30,000 20,000
3 30,000 40,000
4 10,000 60,000
5 10,000 20,000
What is the discount payback for project Y if the interest rate is 10% per year?
4.26 years
3.86 years
4.16 years
2.36 years
What is the NPV for project Y if the discount rate is 10% per year?
$21,588.77
$21,624.87
$18,162.57
$21,323.67
What is the IRR for Project Y?
15.150%
It has no IRR
14.150%
16.150%
What is the crossover rate for the two projects?
13.81%
15.81%
12.81%
14.81%
The intercept on the x-axis for project Y is…?
16.15%
14.15%
15.15%
It does not intercept X-axis
PLEASE show your work!
1.
Discounted payback for project Y is calculated in excel and screen shot provided below:
Discounted payback for project Y is 3.86 years.
Option (B) is correct answer.
2.
NPV of project X and Y is calculated in excel and screen shot provided below:
NPV of project X is $14,917,.63 and NPV of project Y is $18,162.57.
Option (C) is correct answer.
3.
IRR of project X and Y is calculated in excel and screen shot provided below:
IRR of project X is 18.11% and NPV of project Y is 16.15.
Option (D) is correct answer.
4.
crossover rate is the rate at which NPV of both project is equal. So, crossover rate is calculated in excel and screen shot provided below:
Crossover rate is 12.806%.
Option (C) is correct answer.
5.
from the above graph we can see that The intercept on the x-axis for project Y is 16.15%.
Option (A) is correct answer.