Question

In: Finance

As the director of Big Sky Corp, you are evaluating two mutually exclusive projects with the...

As the director of Big Sky Corp, you are evaluating two mutually exclusive projects with the following net cash flow:

Year     Cash Flow X ($)            Cash Flow Y ($)

0          -100,000                       -100,000

1          60,000                          20,000

2          30,000                          20,000

3          30,000                          40,000

4          10,000                          60,000

5          10,000                          20,000

What is the discount payback for project Y if the interest rate is 10% per year?

4.26 years

3.86 years

4.16 years

2.36 years

What is the NPV for project Y if the discount rate is 10% per year?

$21,588.77

$21,624.87

$18,162.57

$21,323.67

What is the IRR for Project Y?

15.150%

It has no IRR

14.150%

16.150%

What is the crossover rate for the two projects?

13.81%

15.81%

12.81%

14.81%

The intercept on the x-axis for project Y is…?

16.15%

14.15%

15.15%

It does not intercept X-axis

PLEASE show your work!

Solutions

Expert Solution

1.

Discounted payback for project Y is calculated in excel and screen shot provided below:

Discounted payback for project Y is 3.86 years.

Option (B) is correct answer.

2.

NPV of project X and Y is calculated in excel and screen shot provided below:

NPV of project X is $14,917,.63 and NPV of project Y is $18,162.57.

Option (C) is correct answer.

3.

IRR of project X and Y is calculated in excel and screen shot provided below:

IRR of project X is 18.11% and NPV of project Y is 16.15.

Option (D) is correct answer.

4.

crossover rate is the rate at which NPV of both project is equal. So, crossover rate is calculated in excel and screen shot provided below:

Crossover rate is 12.806%.

Option (C) is correct answer.

5.

from the above graph we can see that The intercept on the x-axis for project Y is 16.15%.

Option (A) is correct answer.


Related Solutions

As the director of capital budgeting for Bissett Corporation, you are evaluating two mutually exclusive projects...
As the director of capital budgeting for Bissett Corporation, you are evaluating two mutually exclusive projects (you can only choose one) with the following cash flows. The discount rate is 15%. Year Project X Project Y 0 - 100,000 - 100,000 1 50,000 10,000 2 40,000 30,000 3 10,000 40,000 4 10,000 30,000 Which project would you choose? Project X since it has higher IRR Project Y since it has higher NPV Project X since it has higher NPV Neither...
As the director of capital budgeting for EFG Corporation, you are evaluating two mutually exclusive projects...
As the director of capital budgeting for EFG Corporation, you are evaluating two mutually exclusive projects with the following net cash flows: Project E Project F Year Cash Flow Cash Flow 0 -$100,000 -$100,000 1 50,000 10,000 2 40,000 30,000 3 30,000 40,000 4 10,000 60,000 If EFG’s cost of capital is 15 percent, What is the NPV and IRR of the better project, respectively??
As the director of capital budgeting for EFG Corporation, you are evaluating two mutually exclusive projects...
As the director of capital budgeting for EFG Corporation, you are evaluating two mutually exclusive projects with the following net cash flows:                                Project E Project F                   Year     Cash Flow     Cash Flow                    0       -$100,000        -$100,000                    1          50,000            10,000                    2          40,000            30,000                    3          30,000            40,000                    4          10,000            60,000 If EFG’s cost of capital is 15 percent, What is the NPV and IRR of the better project, respectively??
As the director of capital budgeting for EFG Corporation, you are evaluating two mutually exclusive projects...
As the director of capital budgeting for EFG Corporation, you are evaluating two mutually exclusive projects with the following net cash flows:                                Project E Project F                   Year     Cash Flow     Cash Flow                    0       -$100,000        -$100,000                    1          50,000            10,000                    2          40,000            30,000                    3          30,000            40,000                    4          10,000            60,000 If EFG’s cost of capital is 15 percent, What is the NPV and IRR of the better project, respectively??
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: If the appropriate discount rate on these projects is 11 ​percent, which would be chosen and​ why? What is the NPV of project​ A? ​$ nothing ​ (Round to the nearest​ cent.) What is the NPV of project​ B? ​$ ​(Round to the nearest​ cent.) Which project would be chosen and​ why? ​(Select the best choice​.) A....
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: YEAR PROJECT A CASH FLOW PROJECT B CASH FLOW    0 −​$110,000 −​$110,000    1        30,000               0    2        30,000               0    3        30,000               0    4        30,000               0    5        30,000      220,000 ​(Click on the icon located on the​ top-right corner of the data table above in order to copy its contents into a spreadsheet.​) If the appropriate discount rate on these...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: YEAR   PROJECT A CASH FLOW   PROJECT B CASH FLOW 0 -105,000 -105,000 1 40,000 0 2 40,000 0 3 40,000 0 4 40,000 0 5 40,000 240,000 If the appropriate discount rate on these projects is 8 ​percent, which would be chosen and​ why? What is the NPV of project​ A? What is the NPV of project...
You are evaluating two mutually exclusive projects. The cash flows for each are:
You are evaluating two mutually exclusive projects.  The cash flows for each are: Project A                      Project B             Year 0               ($60,000)                      ($85,000)             Year 1               $20,000                        $22,000             Year 2               $35,000                        $25,000             Year 3               $20,000                        $30,000             Year 4               $25,000                        $25,000             Year 5                                                   $15,000             Year 6                                                   $10,000             Year 7                                                   $10,000             Year 8                                                   $10,000 Assume that, if needed, each project is repeatable with no change in cash flows.  Your cost of capital is 13%. Using the replacement chain approach, which project would you chose to...
Problem 10.35 Crane Corp. management is evaluating two mutually exclusive projects. The cost of capital is...
Problem 10.35 Crane Corp. management is evaluating two mutually exclusive projects. The cost of capital is 15 percent. Costs and cash flows for each project are given in the following table. Year Project 1 Project 2 0 -$1,308,961 -$1,198,212 1 257,000 344,000 2 363,000 344,000 3 425,000 344,000 4 520,000 344,000 5 761,000 344,000 Calculate NPV and IRR of two projects. (Enter negative amounts using negative sign, e.g. -45.25. Do not round discount factors. Round other intermediate calculations and final...
Crane Corp. management is evaluating two mutually exclusive projects. The cost of capital is 15 percent....
Crane Corp. management is evaluating two mutually exclusive projects. The cost of capital is 15 percent. Costs and cash flows for each project are given in the following table. Year Project 1 Project 2 0 -$1,291,014 -$1,324,281 1 269,000 385,000 2 346,000 385,000 3 407,000 385,000 4 519,000 385,000 5 799,000 385,000 Calculate NPV and IRR of two projects. (Enter negative amounts using negative sign, e.g. -45.25. Do not round discount factors. Round other intermediate calculations and final answer to...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT