Question

In: Finance

You have been assigned the task of evaluating two mutually exclusive projects with the following projected...

You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows:

YEAR   PROJECT A CASH FLOW   PROJECT B CASH FLOW
0 ------------- -100,000 ---------------   -100,000
1 --------------- 33,000 --------------- 0
2 --------------- 33,000 --------------- 0
3 --------------- 33,000 --------------- 0
4 --------------- 33,000 --------------- 0
5 --------------- 33,000 --------------- 210,000

If the appropriate discount rate on these projects is 12 percent, which would be chosen and why?

1. What is the NPV of project​ A?

____(round to the nearest cent.)

2. What is the NPV of project​ B?

____(round to the nearest cent.)

3. Which project would be chosen and​ why?

a. Choose A because its NPV is higher

b. Choose B because its NPV is higher

c. Choose both because they both have positive NPVS.

d. Cannot choose without comparing their IRRS

Solutions

Expert Solution


Related Solutions

You have been assigned the task of evaluating two mutually exclusive projects with the following projected...
You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: Year Project A Cash Flow Project B Cash Flow 0 ​$(110,000​) ​$(110,000​) 1    40,000            0 2    40,000            0 3    40,000            0 4    40,000            0 5    40,000   240,000 If the appropriate discount rate on these projects is 8 ​percent, which would be chosen and​ why? The NPV of Project A is ​$_____. The NPV of Project A is ​$_____. Which would be chosen...
You have been assigned the task of evaluating two mutually exclusive projects with the following projected...
You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: YEAR      PROJECT A CASH FLOW                 PROJECT B CASH FLOW    0          -110,000                                               -110,000    1          30,000                                                   0    2          30,000                                                   0    3          30,000                                                   0    4          30,000                                                   0    5          30,000                                                   210,000 If the appropriate discount rate on these projects is 9 ​percent, which would be chosen and​ why? What is the NPV...
 You have been assigned the task of evaluating two mutually exclusive projects with the following projected...
 You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: Year Project A Cash Flow Project B Cash Flow 0 ​$(102,000​) ​$(102,000) 1 32,000            00 2    32,000            00 3    32,000            00 4    32,000            00 5    32,000   230, 000 If the appropriate discount rate on these projects is 88 ​percent, which would be chosen and​ why? The NPV of Project A is
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: If the appropriate discount rate on these projects is 11 ​percent, which would be chosen and​ why? What is the NPV of project​ A? ​$ nothing ​ (Round to the nearest​ cent.) What is the NPV of project​ B? ​$ ​(Round to the nearest​ cent.) Which project would be chosen and​ why? ​(Select the best choice​.) A....
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: YEAR PROJECT A CASH FLOW PROJECT B CASH FLOW    0 −​$110,000 −​$110,000    1        30,000               0    2        30,000               0    3        30,000               0    4        30,000               0    5        30,000      220,000 ​(Click on the icon located on the​ top-right corner of the data table above in order to copy its contents into a spreadsheet.​) If the appropriate discount rate on these...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: YEAR   PROJECT A CASH FLOW   PROJECT B CASH FLOW 0 -105,000 -105,000 1 40,000 0 2 40,000 0 3 40,000 0 4 40,000 0 5 40,000 240,000 If the appropriate discount rate on these projects is 8 ​percent, which would be chosen and​ why? What is the NPV of project​ A? What is the NPV of project...
Two projects being considered by a firm are mutually exclusive and have the following projected cash...
Two projects being considered by a firm are mutually exclusive and have the following projected cash flows: Year Project A Project B 0 ($100,000) ($100,000) 1 39,500 0 2 39,500 0 3 39,500 133,000 Based only on the information given, which of the two projects would be preferred, and why? Project A, because it has an even cash inflow stream. Project B, because it has a higher IRR. Indifferent, because the projects have equal IRRs. Include both in the capital...
Two projects being considered by a firm are mutually exclusive and have the following projected cash...
Two projects being considered by a firm are mutually exclusive and have the following projected cash flows: Project A Project B Year Cash Flow Cash Flow Proj A Project B 0 -$300,000 -$300,000 1 145,500 $150,000 2 145,500 -$ 40,000 3 145,500 $370,000 The firm’s cost of capital is 10 percent. Based only on the information given, What are the NPV for Project A and B? Which project do you choose based on the NPV? What are the payback periods...
You are evaluating two mutually exclusive projects. The cash flows for each are:
You are evaluating two mutually exclusive projects.  The cash flows for each are: Project A                      Project B             Year 0               ($60,000)                      ($85,000)             Year 1               $20,000                        $22,000             Year 2               $35,000                        $25,000             Year 3               $20,000                        $30,000             Year 4               $25,000                        $25,000             Year 5                                                   $15,000             Year 6                                                   $10,000             Year 7                                                   $10,000             Year 8                                                   $10,000 Assume that, if needed, each project is repeatable with no change in cash flows.  Your cost of capital is 13%. Using the replacement chain approach, which project would you chose to...
Two mutually exclusive projects are being considered which have the following projected cash flows:                          &nbs
Two mutually exclusive projects are being considered which have the following projected cash flows:                                 Year                       Project A               Project B                                    0                           ($50,000)              ($50,000)                                    1                           $15,625                                $         0                                    2                           $16,000                                $         0                                    3                           $15,000                                $         0                                    4                           $16,000                                $         0                                    5                           $15,500                                $99,500 a. Calculate the NPV for each of these projects using a 10% rate of return. Also, indicate which project should be chosen based on the NPV...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT