Question

In: Finance

You have two mutually exclusive projects A and B and have constructed the NPV profiles for...

You have two mutually exclusive projects A and B and have constructed the NPV profiles for these projects. You find that the IRR of A is greater than the IRR of B but at an 8% cost of capital using the NPV method you would prefer project B. What is causing the NPV profile pattern that you are observing? Which project do you prefer and why? Essentially you are preferring one method over another so you need to discuss the deficiencies of rejected method for full marks.

Solutions

Expert Solution

What is causing the NPV profile pattern that you are observing?

The two projects have different cash flow pattern. Project B must be having higher proportion of cash flows coming in later years while Project A has higher proportion of cash flows in earlier years. The situation is depicted in the graph below. The blue line is Project A which has higher IRR than Project B represented by red line. The diagram is for the purpose of illustration. The figures have no meaning.

· B’s NPV profile is steeper than A’s. This is because B’s cash inflows are further from starting point. Hence, impact of increase in hurdle rate is more prominent in case of B. B’s NPV declines at a faster rate when hurdle rate increases.

· At the hurdle rate = cross over rate, both the projects have the same NPV.

· B has higher NPV if hurdle rate < cross over rate.

· A has higher NPV if hurdle rate > cross over rate.

· Which project has a higher NPV depends on what hurdle rate is used to discount the cash flows to their present value in the analysis, and the dividing point is the crossover rate.

· When discounted at hurdle rates < the crossover rate, NPV and IRR give different results.

· When discounted at hurdle rates > the crossover rate, the NPVs and the IRRs give the same result.

Which project do you prefer and why?

This is the problem with IRR when the timing of cash flows of mutually exclusive projects is different. It can give results that conflict.

In case of a mutually exclusive projects, only one of the proposed projects can be accepted by the company. How do we resolve the conflict if we must choose one or the other?

  • The convention is to use the NPV rule when the two methods are inconsistent, as it better reflects our primary goal: to grow the financial wealth of the company.
  • NPV is a more reliable evaluation tool, because it results in an absolute amount of profit.
  • Find out which of the proposed projects has the highest NPV at the given cost of capital (hurdle rate) and the same should be selected.
  • In this case, at 8% cost of capital, Project B has higher NPV and hence Project B should be selected.

Related Solutions

​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: If the appropriate discount rate on these projects is 11 ​percent, which would be chosen and​ why? What is the NPV of project​ A? ​$ nothing ​ (Round to the nearest​ cent.) What is the NPV of project​ B? ​$ ​(Round to the nearest​ cent.) Which project would be chosen and​ why? ​(Select the best choice​.) A....
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: YEAR PROJECT A CASH FLOW PROJECT B CASH FLOW    0 −​$110,000 −​$110,000    1        30,000               0    2        30,000               0    3        30,000               0    4        30,000               0    5        30,000      220,000 ​(Click on the icon located on the​ top-right corner of the data table above in order to copy its contents into a spreadsheet.​) If the appropriate discount rate on these...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: YEAR   PROJECT A CASH FLOW   PROJECT B CASH FLOW 0 -105,000 -105,000 1 40,000 0 2 40,000 0 3 40,000 0 4 40,000 0 5 40,000 240,000 If the appropriate discount rate on these projects is 8 ​percent, which would be chosen and​ why? What is the NPV of project​ A? What is the NPV of project...
NPV PROFILES: TIMING DIFFERENCES An oil-drilling company must choose between two mutually exclusive extraction projects, and...
NPV PROFILES: TIMING DIFFERENCES An oil-drilling company must choose between two mutually exclusive extraction projects, and each costs $12 million. Under Plan A, all the oil would be extracted in 1 year, producing a cash flow at t = 1 of $14.4 million. Under Plan B, cash flows would be $2.1323 million per year for 20 years. The firm's WACC is 11.4%. Construct NPV profiles for Plans A and B. Round your answers to two decimal places. Do not round...
NPV PROFILES: TIMING DIFFERENCES An oil-drilling company must choose between two mutually exclusive extraction projects, and...
NPV PROFILES: TIMING DIFFERENCES An oil-drilling company must choose between two mutually exclusive extraction projects, and each costs $11.8 million. Under Plan A, all the oil would be extracted in 1 year, producing a cash flow at t = 1 of $14.16 million. Under Plan B, cash flows would be $2.0967 million per year for 20 years. The firm's WACC is 12%. Construct NPV profiles for Plans A and B. Round your answers to two decimal places. Do not round...
All techniques with NPV profile Mutually exclusive projects   Projects A and​ B, of equal​ risk, are...
All techniques with NPV profile Mutually exclusive projects   Projects A and​ B, of equal​ risk, are alternatives for expanding Rosa​ Company's capacity. The​ firm's cost of capital is 16​%. The cash flows for each project are shown in the following​ table: Initial investment   $130,000   $100,000 Year   Cash inflows   1   $30,000   $30,000 2   $35,000   $30,000 3   $40,000   $30,000 4   $45,000   $30,000 5   $50,000   $30,000 a.  Calculate each​ project's payback period. b.  Calculate the net present value​ (NPV) for each project. c.  ...
Heller Airlines is considering two mutually exclusive projects, A and B. The projects have the same...
Heller Airlines is considering two mutually exclusive projects, A and B. The projects have the same risk. Below are the cash flows from each project: Project A Project B Year Cash Flow Cash Flow 0 -$2,000 -$10,000 1 6,000 15,000 a. Graph the NPV profile of each investment. b. Indicate the crossover point and calculate the crossover rate. c. If the cost of capital is 8%, which project should be chosen and why?
You are considering two mutually exclusive projects. The NPV for project one is positive and higher...
You are considering two mutually exclusive projects. The NPV for project one is positive and higher than the NPV for project two, while the IRR for project two is higher than that for project one. Which project should the firm accept and why?
NPV profiles: scale differences A company is considering two mutually exclusive expansion plans. Plan A requires...
NPV profiles: scale differences A company is considering two mutually exclusive expansion plans. Plan A requires a $39 million expenditure on a large-scale integrated plant that would provide expected cash flows of $6.23 million per year for 20 years. Plan B requires a $13 million expenditure to build a somewhat less efficient, more labor-intensive plant with an expected cash flow of $2.91 million per year for 20 years. The firm's WACC is 10%. Calculate each project's NPV. Round your answers...
NPV profiles: scale differences A company is considering two mutually exclusive expansion plans. Plan A requires...
NPV profiles: scale differences A company is considering two mutually exclusive expansion plans. Plan A requires a $41 million expenditure on a large-scale integrated plant that would provide expected cash flows of $6.55 million per year for 20 years. Plan B requires a $11 million expenditure to build a somewhat less efficient, more labor-intensive plant with an expected cash flow of $2.47 million per year for 20 years. The firm's WACC is 10%. 1. NPV profiles for Plan A and...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT