Question

In: Finance

The large furniture retailer “Sofa So Good” is evaluating two mutually exclusive projects:        NPV versus...

  1. The large furniture retailer “Sofa So Good” is evaluating two mutually exclusive projects:

       NPV versus IRR. Consider the following projects, where the firms may only choose one not both:

      

       The firm’s cost of capital/required return equals 9%

       PLEASE NOTE: The firm’s cost of capital, K, acts as a hurdle rate, and is based on the costs involved in financing other firm projects. The Cost of capital allows us to decide to accept or reject an investment, using IRR, and also allows us to use it as the discount rate, R, in NPV calculations.

Years

Cash Flow Project X

Cash Flow Project Y

The differential (X - Y) or (Y – X)

0

-$69,000

-$69,000

?

1

$13,000

$29,000

?

2

$33,000

$24,000

?

3

$38,000

$27,000

?

Questions for #3:

  1. What would be the Internal Rate of Return for each investment, X and Y.?
  2. What would be the NPV’s of each project, if the cost of capital is 9% for the firm, “Sofa So Good”?
  3.    What is the crossover point, otherwise known as the discount crossover rate, where both projects cross??? (Remember to subtract X – Y cash flows or Y-X, and then set series equal to zero, and solve for IRR)
  4. Please Include an NPV Profile for the projects (see Figure 8.7 on page 253 in textbook and study guide/practice exam), including calculating the NPVs for a range of the discount rates, 0%, 5%, 10%, 15%, 20%, and 25% - this allows for more accurate plotting of the profile.
  5.    Finally, which project should you accept and when (under what circumstances)?

      

Solutions

Expert Solution


Related Solutions

​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: If the appropriate discount rate on these projects is 11 ​percent, which would be chosen and​ why? What is the NPV of project​ A? ​$ nothing ​ (Round to the nearest​ cent.) What is the NPV of project​ B? ​$ ​(Round to the nearest​ cent.) Which project would be chosen and​ why? ​(Select the best choice​.) A....
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: YEAR PROJECT A CASH FLOW PROJECT B CASH FLOW    0 −​$110,000 −​$110,000    1        30,000               0    2        30,000               0    3        30,000               0    4        30,000               0    5        30,000      220,000 ​(Click on the icon located on the​ top-right corner of the data table above in order to copy its contents into a spreadsheet.​) If the appropriate discount rate on these...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: YEAR   PROJECT A CASH FLOW   PROJECT B CASH FLOW 0 -105,000 -105,000 1 40,000 0 2 40,000 0 3 40,000 0 4 40,000 0 5 40,000 240,000 If the appropriate discount rate on these projects is 8 ​percent, which would be chosen and​ why? What is the NPV of project​ A? What is the NPV of project...
NPV versus IRR. Consider the following cash flows on two mutually exclusive projects for the Bahamas...
NPV versus IRR. Consider the following cash flows on two mutually exclusive projects for the Bahamas Recreation Corporation. Both projects require an annual return of 15 percent. Year Fishing Submarine 0 -835000 -1650000 1 450000 1050000 2 410000 675000 3 335000 520000 As a financial analyst for the company, you are asked the following questions. a) If your decision rule is to accept the project with the greater IRR, which project should you chose? b) Since you are fully aware...
​NPV versus IRR [LO1, 5] Bruin, Inc., has identified the following two mutually exclusive projects:
NPV versus IRR [LO1, 5] Bruin, Inc., has identified the following two mutually exclusive projects:a. What is the IRR for each of these projects? Using the IRR decision rule, which project should the company accept? Is this decision necessarily correct? b. If the required return is 11 percent, what is the NPV for each of these projects? Which project will the company choose if it applies the NPV decision rule?
‘Evaluating mutually exclusive projects using the IRR and NPV approaches can be problematic’. Discuss this statement...
‘Evaluating mutually exclusive projects using the IRR and NPV approaches can be problematic’. Discuss this statement with examples.
You are evaluating two mutually exclusive projects. The cash flows for each are:
You are evaluating two mutually exclusive projects.  The cash flows for each are: Project A                      Project B             Year 0               ($60,000)                      ($85,000)             Year 1               $20,000                        $22,000             Year 2               $35,000                        $25,000             Year 3               $20,000                        $30,000             Year 4               $25,000                        $25,000             Year 5                                                   $15,000             Year 6                                                   $10,000             Year 7                                                   $10,000             Year 8                                                   $10,000 Assume that, if needed, each project is repeatable with no change in cash flows.  Your cost of capital is 13%. Using the replacement chain approach, which project would you chose to...
IRR and NPV A company is analyzing two mutually exclusive projects, S and L, with the...
IRR and NPV A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $872.52 $260 $15 $10 Project L -$1,000 $0 $250 $380 $811.10 The company's WACC is 10.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places.
IRR and NPV A company is analyzing two mutually exclusive projects, S and L, with the...
IRR and NPV A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $882.76 $260 $5 $5 Project L -$1,000 $0 $250 $400 $775.11 The company's WACC is 8.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places. %
IRR AND NPV A company is analyzing two mutually exclusive projects, S and L, with the...
IRR AND NPV A company is analyzing two mutually exclusive projects, S and L, with the following cash flows:    0 1 2 3 4 Project S -$1,000 $885.37 $250 $15 $15 Project L -$1,000 $5 $240 $380 $844.53 The company's WACC is 8.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT